← Back
BuildNYC
Public elementary, junior or senior high
64-20 175TH STREET
QUEENS · BIN 4149078
💬 Discuss this project
1960Year Built
3Stories
W1Building Class
R4Zoning
120,350 sfGross Floor Area
1Units
LL97 Covered10 Active Violations 0 unresolved · 10 paperwork only ▸FDNY Report ↗
Public elementary, junior or senior high · Owner of record: NYC Department of Education · 103,000 sf lot · 1.17 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentGeneralOther
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofJ.H.S. 216 QueensUnder Construction14p · 1 filing · 20 docs
Floor 3J.H.S. 216 QueensUnder Construction13p · 3 filings · 20 docs
Floor 2J.H.S. 216 QueensUnder Construction35p · 1 filing · 20 docs
Floor 1J.H.S. 216 QueensUnder Construction57p · 2 filings · 20 docs
BasementJ.H.S. 216 Queens3p · 1 filing · 20 docs
Sub-BasementJ.H.S. 216 QueensUnder Construction22p · 2 filings · 20 docs
Site & exteriorJ.H.S 216q, J.H.S. 216 Queens34p · 6 filings · 18 docs
Filed — no permit issuedJ.H.S. 216 Queens5p · 1 filing · 5 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYC School Construction Authority12210/14/2026
NYC Department of Education403/22/2026
BOE103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
SBLM Architects310/13/2026
Queens110/05/2026
KPFF Consulting Engineers509/22/2026
Synergy Strategic Design Architects610/15/2025
AK Consulting Services211/04/2024
Hansen Engineering108/16/2024
Shenoy Engineering706/11/2024
Princeton804/02/2024
AKRF210/05/2023
Ame Services208/14/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JMV Associates3003/21/2026
Ame Services403/21/2026
AK Consulting Services403/21/2026
Tarek M. Zeid, P.E103/21/2026
Tarek M Zeid P E103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
A.T.J. Electrical Cospecialty_contractor1007/08/2026
Technico ConstructionGeneral Contractor907/08/2026
Technico ConstructionScaffold507/08/2026
Singh Landscaping & LawnScaffold507/08/2026
Singh Landscaping & Lawnspecialty_contractor507/08/2026
Forsythe P&HPlumbing307/08/2026
Varsity Plumbing and HeatingPlumbing207/08/2026
Stanco System Electrical ContElectrical203/22/2026
R.A.M.S. Mechanicalspecialty_contractor207/08/2026
WDFGeneral Contractor207/08/2026
Roma ScaffoldingScaffold204/09/2026
Ajit One Mechanical & General ContractingPlumbing207/08/2026
Par Plumbing CoPlumbing207/08/2026
Dynamic Electric ServiceElectrical103/21/2026
Anco Electl ContctngElectrical103/22/2026
A.T.J. Electrical CoElectrical103/21/2026
Katco ElectricElectrical103/21/2026
Precision Electrical ContElectrical103/22/2026
Charan Electrical Enterp'sElectrical103/22/2026
Ajit One Mechanical & GeneralGeneral Contractor107/08/2026
New Phase Electrical ContractorsElectrical103/22/2026
Ajit One Mechanical & Gen ContractingFire Protection107/08/2026
Murray StanleyElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Tectonic Engineering Cons1061210/13/2026
Universal Testing and Ins4001806/11/2024
Building Lifecycle
All (223)Filed (37)Permit Issued (40)Signed Off (10)Violation (60)Inspection (10)Objection (36)Special Inspection (30)
10/14/2026
Objection raised — Other
10/13/2026
Filed — Alteration
PS216Q-EXISTING BUILDING STRUCTURAL- WORK .The scope of work consists of the removal of an existing concrete column as well as the supplementary framing required to accomplish this scope at each floor.2. SEE COMMENTS...
Q00857440-P3
10/07/2026
Objection raised — Other
10/05/2026
Filed — Alteration
INSTALLATION OF NEW SIDEWALK SHED AT 64-02 175TH STREET, QUEENS, NY 11365. AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
Q01461214-I1
09/25/2026
Signed off — Alteration
Q01044214-I1
09/22/2026
Filed — Alteration
PS216Q-EXISTING BUILDING STRUCTURAL- WORK .The scope of work consists of the removal of an existing concrete column as well as the supplementary framing required to accomplish this scope at each floor.2. SEE COMMENTS...
Q00857440-P2
09/08/2026
Signed off — Alteration
Q01044219-I1
08/17/2026
Special inspection requirement — Final
GEORGE GHEBRYAL
08/17/2026
Special inspection requirement — Structural Steel - Welding
GEORGE GHEBRYAL
08/17/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
GEORGE GHEBRYAL
08/17/2026
Special inspection requirement — Structural Steel - High Strength Bolting
GEORGE GHEBRYAL
08/17/2026
Special inspection requirement — Concrete - Cast-In-Place
GEORGE GHEBRYAL
08/17/2026
Special inspection requirement — Structural Steel - Details
GEORGE GHEBRYAL
08/17/2026
Special inspection requirement — Post-installed Anchors
GEORGE GHEBRYAL
08/06/2026
Signed off — Alteration
216Q- EB_ SOE DESIGN FOR THE EXISTING BUILDING ELEVATOR LIFT PIT AND ENTRANCE STAIR REMOVALS FILED IN CONJUNCTION WITH Q00857440. ALL AS PER PLANS FILED HEREWITH
Q01093550-I1
08/06/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
05/13/2026
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
04/28/2026
Violation issued (ECB, open)
Construction
04/28/2026
Violation issued (ECB, open)
Construction
04/28/2026
Violation issued (ECB, open)
Construction
04/28/2026
Violation issued (ECB, open)
Construction
04/28/2026
Violation issued (ECB, open)
Construction
03/23/2026
Violation issued (FDNY_NOV, closed)
03/03/2026
Signed off — Alteration
Q216_ Provide new drinking fountains along the Path of Travel to Room 317. PAA: Proposed 2-hour fire rating for corridor wall will be achieved from inside the duct space adjacent to Room 308.
Q00788465-S1
03/03/2026
Signed off — Alteration
Q216_ Provide new drinking fountains along the Path of Travel to Room 317. PAA: Proposed 2-hour fire rating for corridor wall will be achieved from inside the duct space adjacent to Room 308.
Q00788465-I1
03/03/2026
Permit issued — Mechanical Systems
Q00857440-S2-MS
02/25/2026
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
02/03/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
01/26/2026
Permit issued — Structural
Q00857440-S3-ST
01/26/2026
Permit issued — Supported Scaffold
Q01044219-I1-SF
01/26/2026
Permit issued — Support of Excavation
Q01093550-I1-SE
01/26/2026
Permit issued — Construction Fence
Q01044214-I1-FN
01/26/2026
Permit issued — General Construction
Q00857440-I1-GC
01/23/2026
Violation issued (FDNY_ORDER, closed)
01/12/2026
Permit issued — Plumbing
Q00857440-S1-PL
12/05/2025
Violation issued (FDNY_ORDER, closed)
12/05/2025
Violation issued (FDNY_ORDER, closed)
12/05/2025
Violation issued (FDNY_ORDER, closed)
12/05/2025
Violation issued (FDNY_ORDER, closed)
12/05/2025
Violation issued (FDNY_ORDER, closed)
12/03/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
11/13/2025
Violation issued (FDNY_NOV, closed)
10/15/2025
Filed — Alteration
Q216_ Provide new drinking fountains along the Path of Travel to Room 317. PAA: Proposed 2-hour fire rating for corridor wall will be achieved from inside the duct space adjacent to Room 308.
Q00788465-P3
10/15/2025
Violation issued (FDNY_ORDER, closed)
10/15/2025
Violation issued (FDNY_ORDER, closed)
10/13/2025
Special inspection requirement — Fire-Resistance Rated Construction
GEORGE GHEBRYAL
10/13/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
GEORGE GHEBRYAL
09/30/2025
Permit issued — General Construction
Q00788465-I1-GC
09/08/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
08/14/2025
Permit issued — Plumbing
Q00808647-S2-PL
06/20/2025
Permit issued — Plumbing
Q00788465-S1-PL
06/17/2025
Signed off — Alteration
Filing for the installation of construction fence on behalf of contractor
Q00908994-I1
06/17/2025
Signed off — Alteration
Filing for the installation of sidewalk shed on behalf of contractor
Q00908990-I1
05/29/2025
Violation issued (FDNY_ORDER, closed)
05/12/2025
Violation issued (ECB, open)
Construction
05/12/2025
Violation issued (ECB, open)
Construction
05/12/2025
Violation issued (ECB, closed)
Construction
05/12/2025
Violation issued (ECB, open)
Construction
05/09/2025
Inspection — Pass-Final SP - Up to 3 Requested Floors
Pass
View inspection ↗
03/14/2025
Permit issued — Mechanical Systems
Q00857440-S2-MS
Latest 60 of 223 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsPermit IssuedR.A.M.S. Mechanical03/03/2026
DOB NOWStructuralPermit IssuedTechnico Construction01/26/2026
DOB NOWSupported ScaffoldSigned-offRoma Scaffolding01/26/2026
DOB NOWSupport of ExcavationSigned-offTechnico Construction01/26/2026
DOB NOWConstruction FenceSigned-offTechnico Construction01/26/2026
DOB NOWGeneral ConstructionPermit IssuedTechnico Construction01/26/2026
DOB NOWPlumbingPermit IssuedPar Plumbing Co01/12/2026
DOB NOWGeneral ConstructionSigned-offA.T.J. Electrical Co09/30/2025
DOB NOWPlumbingPermit IssuedHar JI Plumbing & Heating08/14/2025
DOB NOWPlumbingSigned-offForsythe P&H06/20/2025
DOB NOWMechanical SystemsPermit IssuedR.A.M.S. Mechanical03/14/2025
DOB NOWStructuralPermit IssuedTechnico Construction03/14/2025
DOB NOWGeneral ConstructionPermit IssuedTechnico Construction03/13/2025
DOB NOWSupport of ExcavationSigned-offTechnico Construction03/11/2025
DOB NOWPlumbingPermit IssuedPar Plumbing Co02/11/2025
DOB NOWConstruction FenceSigned-offTechnico Construction02/05/2025
DOB NOWSupported ScaffoldSigned-offRoma Scaffolding01/31/2025
DOB NOWSidewalk ShedSigned-offSingh Landscaping & Lawn12/09/2024
DOB NOWConstruction FenceSigned-offTechnico Construction11/05/2024
DOB NOWGeneral ConstructionSigned-offA.T.J. Electrical Co10/10/2024
DOB NOWSprinklersPermit IssuedHar JI Plumbing & Heating10/03/2024
DOB NOWPlumbingSigned-offForsythe P&H06/18/2024
DOB NOWGeneral ConstructionSigned-offA.T.J. Electrical Co02/01/2024
DOB NOWMechanical SystemsSigned-offAjit One Mechanical Gen11/09/2023
DOB NOWPlumbingPermit IssuedHar JI Plumbing & Heating11/09/2023
DOB NOWStructuralSigned-offSingh Landscaping & Lawn10/27/2023
DOB NOWMechanical SystemsSigned-offWDF10/17/2023
DOB NOWGeneral ConstructionPermit IssuedSingh Landscaping & Lawn10/16/2023
DOB NOWGeneral ConstructionPermit IssuedSingh Landscaping & Lawn10/16/2023
DOB NOWGeneral ConstructionSigned-offA.T.J. Electrical Co09/28/2023
DOB NOWGeneral ConstructionSigned-offA.T.J. Electrical Co09/27/2023
DOB NOWSidewalk ShedSigned-offSingh Landscaping & Lawn09/05/2023
DOB NOWConstruction FenceSigned-offSingh Landscaping & Lawn08/30/2023
DOB NOWPlumbingSigned-offForsythe P&H07/18/2023
DOB NOWGeneral ConstructionSigned-offA.T.J. Electrical Co07/18/2023
DOB NOWPlumbingSigned-offVarsity Plumbing and Heating06/28/2023
DOB NOWGeneral ConstructionSigned-offA.T.J. Electrical Co02/01/2023
DOB NOWMechanical SystemsSigned-offWDF07/06/2022
DOB NOWPlumbingSigned-offVarsity Plumbing and Heating06/24/2022
DOB NOWGeneral ConstructionSigned-offA.T.J. Electrical Co06/23/2022
+ 50 more permits on file
1 project · most recent 06/11/2024
FiledStatusContractorScope
06/11/2024Permit IssuedAjit One Mechanical & Gen Contracting—
1 project · most recent 06/11/2024
Storm Water/Sanitary
FiledStatusContractorScope
06/11/2024Permit IssuedAjit One Mechanical & General ContractingStorm, Water/Sanitary
25 projects · most recent 06/02/2026
General Wiring Lighting
FiledStatusContractorScope
06/02/2026CompletePacific Electrical ContractingLighting
05/13/2025CompleteGemini Electric Co—
05/06/2025CompleteNew Phase Electrical ContractorsGeneral Wiring
04/25/2025CompleteCharan Electrical Enterp's—
10/24/2024CompleteAnco Electl Contctng—
09/17/2024CompleteCharan Electrical Enterp's—
08/27/2024Permit IssuedStanco System Electrical Cont—
04/05/2024CompleteLit Mode Electrical Contg—
02/20/2024CompletePacific Electrical Contracting—
02/01/2024CompletePacific Electrical Contracting—
11/27/2023CompleteGemini Electric Co—
10/18/2023CompleteCharan Electrical Enterp'sGeneral Wiring
10/11/2023CompletePrecision Electrical ContGeneral Wiring
09/07/2023CompleteStanco System Electrical Cont—
08/29/2023Permit IssuedNew Phase Electrical Contractors—
3 projects · most recent 10/13/2026
Steel Concrete Masonry
FiledStatusContractorScope
10/13/2026Permit IssuedR.A.M.S. MechanicalSteel, Concrete
08/16/2024Signed-offTechnico Construction1 scope_items
06/11/2024Permit IssuedAjit One Mechanical & General ContractingSteel, Concrete, Masonry
▾Field Inspections (DOB CAP) — 10
DateTypeResultReport
08/06/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
05/13/2026Pass-Final General Construction Non-Directive 14PassView ↗
02/25/2026Pass-Final General Construction Non-Directive 14PassView ↗
02/03/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
12/03/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
09/08/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/09/2025Pass-Final SP - Up to 3 Requested FloorsPassView ↗
05/31/2024Pass-Final General Construction Non-Directive 14PassView ↗
10/30/2023Pass-Final PL - Up to 9 Requested FloorsPassView ↗
08/24/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 124
DateRequirementInspectorRole
08/17/2026Structural Stability – Alterations of existing buildingsGEORGE GHEBRYALspecial
08/17/2026Concrete - Cast-In-PlaceGEORGE GHEBRYALspecial
08/17/2026Post-installed AnchorsGEORGE GHEBRYALspecial
08/17/2026FinalGEORGE GHEBRYALprogress
08/17/2026Structural Steel - WeldingGEORGE GHEBRYALspecial
08/17/2026Structural Steel - High Strength BoltingGEORGE GHEBRYALspecial
08/17/2026Structural Steel - DetailsGEORGE GHEBRYALspecial
10/13/2025Fire-Resistant Penetrations and JointsGEORGE GHEBRYALspecial
10/13/2025Fire-Resistance Rated ConstructionGEORGE GHEBRYALprogress
09/12/2024Structural Stability – Alterations of existing buildingsGEORGE GHEBRYALspecial
08/27/2024Post-installed AnchorsGEORGE GHEBRYALspecial
08/14/2024Excavations - Sheeting, Shoring, and BracingGEORGE GHEBRYALspecial
06/18/2024Post-installed AnchorsNELSON LOPEZspecial
06/13/2024Concrete - Cast-In-PlaceGEORGE GHEBRYALspecial
06/13/2024Structural Steel - WeldingGEORGE GHEBRYALspecial
06/13/2024Structural Stability – Alterations of existing buildingsGEORGE GHEBRYALspecial
06/13/2024Structural Steel - High Strength BoltingGEORGE GHEBRYALspecial
06/13/2024Structural Steel - DetailsGEORGE GHEBRYALspecial
06/13/2024Post-installed AnchorsGEORGE GHEBRYALspecial
06/13/2024Subsurface Conditions – Fill Placement & In-Place DensityGEORGE GHEBRYALspecial
06/13/2024FinalGEORGE GHEBRYALprogress
06/13/2024Subgrade InspectionsGEORGE GHEBRYALspecial
06/11/2024Sprinkler SystemsNELSON LOPEZspecial
06/10/2024Structural Steel - WeldingGEORGE GHEBRYALspecial
06/10/2024FinalGEORGE GHEBRYALprogress
Latest 25 of 124.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
J.H.S. 216 QueensEducationSub-basement, Floors 1–3, Roof
Project Q01461214 Alteration · Objections · 10/05/2026
Project Q00908990 Alteration · LOC Issued · 08/14/2023
Project Q00857440 Alteration · Permit Entire · 04/13/2023
Project Q00808647 Alteration · Permit Entire · 01/20/2023
J.H.S 216qEducation—
Project Q01044219 Alteration · LOC Issued · 11/04/2024
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 306 on file (BIS + DOB NOW)
▸Plans & Drawings37
▸DOB NOWPlans/Sketch37
10/06/2026Q01461214-I1Request digital key ↗
08/26/2026Q00788465-P1Request digital key ↗
08/26/2026Q00788465-P2Request digital key ↗
Showing 3 of 37 on file for this type
▸Seals & Professional Certifications96
▸DOB NOWDPL-1: Design Professional Seal & Signature37
10/06/2026Q01461214-I1Open ↗
08/26/2026Q00788465-P1Open ↗
08/26/2026Q00788465-P3Open ↗
Showing 3 of 37 on file for this type
▸DOB NOWProgress Inspector Seal & Signature33
10/17/2026Q00726573-P2Open ↗
10/17/2026Q00726573-P2Open ↗
10/17/2026Q00726573-P2Open ↗
Showing 3 of 33 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature26
10/17/2026Q00726573-P2Open ↗
10/17/2026Q00726573-P2Open ↗
10/04/2026Q00857440-P2Open ↗
Showing 3 of 26 on file for this type
▸Trade Schedules & Equipment1
▸BISFA - FDNY APPROVAL : FD-FAA1
11/07/2025421104931Open ↗
▸Safety & Tenant Protection4
▸DOB NOWNYCSCA - Approved Site Safety Plans4
08/13/2026Q00908990-I1Open ↗
08/13/2026Q00908994-I1Open ↗
Showing 2 of 4 on file for this type
▸Environmental & Asbestos15
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form15
08/26/2026Q00788465-I1Open ↗
08/26/2026Q00788465-S1Open ↗
08/24/2026Q00857440-I1Open ↗
Showing 3 of 15 on file for this type
▸Energy Compliance1
▸DOB NOWEN2: As Built Energy Analysis1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Approvals, Objections & Sign-offs102
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter37
10/06/2026Q01461214-I1Open ↗
08/25/2026Q00808647-S3Open ↗
08/24/2026Q00857440-P2Open ↗
Showing 3 of 37 on file for this type
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)37
10/06/2026Q01461214-I1Open ↗
08/25/2026Q00808647-S3Open ↗
08/24/2026Q00857440-P2Open ↗
Showing 3 of 37 on file for this type
▸DOB NOWDEP Variance (V5) letter15
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 15 on file for this type
▸DOB NOWDesign Commission Sign Off City Owned (Exterior Work)13
10/06/2026Q01461214-I1Open ↗
08/24/2026Q00857440-I1Open ↗
08/24/2026Q00857440-S1Open ↗
Showing 3 of 13 on file for this type
▸Filing & Intake Forms4
▸DOB NOWAI1 Form4
08/15/2026Q00726573-I1Open ↗
08/13/2026Q00788465-I1Open ↗
08/13/2026Q00788465-P3Open ↗
Showing 3 of 4 on file for this type
▸Other Documents46
▸DOB NOWNYCSCA - BCC Plan Examination Transmittal37
10/06/2026Q01461214-I1Open ↗
08/25/2026Q00808647-S3Open ↗
08/24/2026Q00857440-P2Open ↗
Showing 3 of 37 on file for this type
▸DOB NOWNYCSCA Exhibit 28
08/21/2026Q01093550-I1Open ↗
08/13/2026Q00908994-I1Open ↗
08/13/2026Q00908990-I1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWAdjoining Owners Notification1
08/13/2026Q01093550-I1Open ↗