| Owner | Filings | Most Recent |
|---|---|---|
| NYC School Construction Authority | 122 | 10/14/2026 |
| NYC Department of Education | 4 | 03/22/2026 |
| BOE | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| SBLM Architects | 3 | 10/13/2026 |
| Queens | 1 | 10/05/2026 |
| KPFF Consulting Engineers | 5 | 09/22/2026 |
| Synergy Strategic Design Architects | 6 | 10/15/2025 |
| AK Consulting Services | 2 | 11/04/2024 |
| Hansen Engineering | 1 | 08/16/2024 |
| Shenoy Engineering | 7 | 06/11/2024 |
| Princeton | 8 | 04/02/2024 |
| AKRF | 2 | 10/05/2023 |
| Ame Services | 2 | 08/14/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| JMV Associates | 30 | 03/21/2026 |
| Ame Services | 4 | 03/21/2026 |
| AK Consulting Services | 4 | 03/21/2026 |
| Tarek M. Zeid, P.E | 1 | 03/21/2026 |
| Tarek M Zeid P E | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| A.T.J. Electrical Co | specialty_contractor | 10 | 07/08/2026 |
| Technico Construction | General Contractor | 9 | 07/08/2026 |
| Technico Construction | Scaffold | 5 | 07/08/2026 |
| Singh Landscaping & Lawn | Scaffold | 5 | 07/08/2026 |
| Singh Landscaping & Lawn | specialty_contractor | 5 | 07/08/2026 |
| Forsythe P&H | Plumbing | 3 | 07/08/2026 |
| Varsity Plumbing and Heating | Plumbing | 2 | 07/08/2026 |
| Stanco System Electrical Cont | Electrical | 2 | 03/22/2026 |
| R.A.M.S. Mechanical | specialty_contractor | 2 | 07/08/2026 |
| WDF | General Contractor | 2 | 07/08/2026 |
| Roma Scaffolding | Scaffold | 2 | 04/09/2026 |
| Ajit One Mechanical & General Contracting | Plumbing | 2 | 07/08/2026 |
| Par Plumbing Co | Plumbing | 2 | 07/08/2026 |
| Dynamic Electric Service | Electrical | 1 | 03/21/2026 |
| Anco Electl Contctng | Electrical | 1 | 03/22/2026 |
| A.T.J. Electrical Co | Electrical | 1 | 03/21/2026 |
| Katco Electric | Electrical | 1 | 03/21/2026 |
| Precision Electrical Cont | Electrical | 1 | 03/22/2026 |
| Charan Electrical Enterp's | Electrical | 1 | 03/22/2026 |
| Ajit One Mechanical & General | General Contractor | 1 | 07/08/2026 |
| New Phase Electrical Contractors | Electrical | 1 | 03/22/2026 |
| Ajit One Mechanical & Gen Contracting | Fire Protection | 1 | 07/08/2026 |
| Murray Stanley | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Tectonic Engineering Cons | 106 | 12 | 10/13/2026 |
| Universal Testing and Ins | 400 | 18 | 06/11/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | R.A.M.S. Mechanical | 03/03/2026 |
| DOB NOW | Structural | Permit Issued | Technico Construction | 01/26/2026 |
| DOB NOW | Supported Scaffold | Signed-off | Roma Scaffolding | 01/26/2026 |
| DOB NOW | Support of Excavation | Signed-off | Technico Construction | 01/26/2026 |
| DOB NOW | Construction Fence | Signed-off | Technico Construction | 01/26/2026 |
| DOB NOW | General Construction | Permit Issued | Technico Construction | 01/26/2026 |
| DOB NOW | Plumbing | Permit Issued | Par Plumbing Co | 01/12/2026 |
| DOB NOW | General Construction | Signed-off | A.T.J. Electrical Co | 09/30/2025 |
| DOB NOW | Plumbing | Permit Issued | Har JI Plumbing & Heating | 08/14/2025 |
| DOB NOW | Plumbing | Signed-off | Forsythe P&H | 06/20/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | R.A.M.S. Mechanical | 03/14/2025 |
| DOB NOW | Structural | Permit Issued | Technico Construction | 03/14/2025 |
| DOB NOW | General Construction | Permit Issued | Technico Construction | 03/13/2025 |
| DOB NOW | Support of Excavation | Signed-off | Technico Construction | 03/11/2025 |
| DOB NOW | Plumbing | Permit Issued | Par Plumbing Co | 02/11/2025 |
| DOB NOW | Construction Fence | Signed-off | Technico Construction | 02/05/2025 |
| DOB NOW | Supported Scaffold | Signed-off | Roma Scaffolding | 01/31/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | Singh Landscaping & Lawn | 12/09/2024 |
| DOB NOW | Construction Fence | Signed-off | Technico Construction | 11/05/2024 |
| DOB NOW | General Construction | Signed-off | A.T.J. Electrical Co | 10/10/2024 |
| DOB NOW | Sprinklers | Permit Issued | Har JI Plumbing & Heating | 10/03/2024 |
| DOB NOW | Plumbing | Signed-off | Forsythe P&H | 06/18/2024 |
| DOB NOW | General Construction | Signed-off | A.T.J. Electrical Co | 02/01/2024 |
| DOB NOW | Mechanical Systems | Signed-off | Ajit One Mechanical Gen | 11/09/2023 |
| DOB NOW | Plumbing | Permit Issued | Har JI Plumbing & Heating | 11/09/2023 |
| DOB NOW | Structural | Signed-off | Singh Landscaping & Lawn | 10/27/2023 |
| DOB NOW | Mechanical Systems | Signed-off | WDF | 10/17/2023 |
| DOB NOW | General Construction | Permit Issued | Singh Landscaping & Lawn | 10/16/2023 |
| DOB NOW | General Construction | Permit Issued | Singh Landscaping & Lawn | 10/16/2023 |
| DOB NOW | General Construction | Signed-off | A.T.J. Electrical Co | 09/28/2023 |
| DOB NOW | General Construction | Signed-off | A.T.J. Electrical Co | 09/27/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | Singh Landscaping & Lawn | 09/05/2023 |
| DOB NOW | Construction Fence | Signed-off | Singh Landscaping & Lawn | 08/30/2023 |
| DOB NOW | Plumbing | Signed-off | Forsythe P&H | 07/18/2023 |
| DOB NOW | General Construction | Signed-off | A.T.J. Electrical Co | 07/18/2023 |
| DOB NOW | Plumbing | Signed-off | Varsity Plumbing and Heating | 06/28/2023 |
| DOB NOW | General Construction | Signed-off | A.T.J. Electrical Co | 02/01/2023 |
| DOB NOW | Mechanical Systems | Signed-off | WDF | 07/06/2022 |
| DOB NOW | Plumbing | Signed-off | Varsity Plumbing and Heating | 06/24/2022 |
| DOB NOW | General Construction | Signed-off | A.T.J. Electrical Co | 06/23/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/11/2024 | Permit Issued | Ajit One Mechanical & Gen Contracting | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/11/2024 | Permit Issued | Ajit One Mechanical & General Contracting | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/02/2026 | Complete | Pacific Electrical Contracting | Lighting |
| 05/13/2025 | Complete | Gemini Electric Co | — |
| 05/06/2025 | Complete | New Phase Electrical Contractors | General Wiring |
| 04/25/2025 | Complete | Charan Electrical Enterp's | — |
| 10/24/2024 | Complete | Anco Electl Contctng | — |
| 09/17/2024 | Complete | Charan Electrical Enterp's | — |
| 08/27/2024 | Permit Issued | Stanco System Electrical Cont | — |
| 04/05/2024 | Complete | Lit Mode Electrical Contg | — |
| 02/20/2024 | Complete | Pacific Electrical Contracting | — |
| 02/01/2024 | Complete | Pacific Electrical Contracting | — |
| 11/27/2023 | Complete | Gemini Electric Co | — |
| 10/18/2023 | Complete | Charan Electrical Enterp's | General Wiring |
| 10/11/2023 | Complete | Precision Electrical Cont | General Wiring |
| 09/07/2023 | Complete | Stanco System Electrical Cont | — |
| 08/29/2023 | Permit Issued | New Phase Electrical Contractors | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/13/2026 | Permit Issued | R.A.M.S. Mechanical | Steel, Concrete |
| 08/16/2024 | Signed-off | Technico Construction | 1 scope_items |
| 06/11/2024 | Permit Issued | Ajit One Mechanical & General Contracting | Steel, Concrete, Masonry |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/06/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/13/2026 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 02/25/2026 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 02/03/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/03/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/08/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/09/2025 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 05/31/2024 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 10/30/2023 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 08/24/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/17/2026 | Structural Stability – Alterations of existing buildings | GEORGE GHEBRYAL | special |
| 08/17/2026 | Concrete - Cast-In-Place | GEORGE GHEBRYAL | special |
| 08/17/2026 | Post-installed Anchors | GEORGE GHEBRYAL | special |
| 08/17/2026 | Final | GEORGE GHEBRYAL | progress |
| 08/17/2026 | Structural Steel - Welding | GEORGE GHEBRYAL | special |
| 08/17/2026 | Structural Steel - High Strength Bolting | GEORGE GHEBRYAL | special |
| 08/17/2026 | Structural Steel - Details | GEORGE GHEBRYAL | special |
| 10/13/2025 | Fire-Resistant Penetrations and Joints | GEORGE GHEBRYAL | special |
| 10/13/2025 | Fire-Resistance Rated Construction | GEORGE GHEBRYAL | progress |
| 09/12/2024 | Structural Stability – Alterations of existing buildings | GEORGE GHEBRYAL | special |
| 08/27/2024 | Post-installed Anchors | GEORGE GHEBRYAL | special |
| 08/14/2024 | Excavations - Sheeting, Shoring, and Bracing | GEORGE GHEBRYAL | special |
| 06/18/2024 | Post-installed Anchors | NELSON LOPEZ | special |
| 06/13/2024 | Concrete - Cast-In-Place | GEORGE GHEBRYAL | special |
| 06/13/2024 | Structural Steel - Welding | GEORGE GHEBRYAL | special |
| 06/13/2024 | Structural Stability – Alterations of existing buildings | GEORGE GHEBRYAL | special |
| 06/13/2024 | Structural Steel - High Strength Bolting | GEORGE GHEBRYAL | special |
| 06/13/2024 | Structural Steel - Details | GEORGE GHEBRYAL | special |
| 06/13/2024 | Post-installed Anchors | GEORGE GHEBRYAL | special |
| 06/13/2024 | Subsurface Conditions – Fill Placement & In-Place Density | GEORGE GHEBRYAL | special |
| 06/13/2024 | Final | GEORGE GHEBRYAL | progress |
| 06/13/2024 | Subgrade Inspections | GEORGE GHEBRYAL | special |
| 06/11/2024 | Sprinkler Systems | NELSON LOPEZ | special |
| 06/10/2024 | Structural Steel - Welding | GEORGE GHEBRYAL | special |
| 06/10/2024 | Final | GEORGE GHEBRYAL | progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| J.H.S. 216 Queens | Education | Sub-basement, Floors 1–3, Roof | Project Q01461214 Project Q00908990 Project Q00857440 Project Q00808647 |
| J.H.S 216q | Education | — | Project Q01044219 |