← Back
Two family frame
68-29 SPRINGFIELD BLVD
QUEENS · BIN 4163509
💬 Discuss this project
1952Year Built
2Stories
B2Building Class
R3-2Zoning
2,496 sfGross Floor Area
2Units
0 Open ViolationsFDNY Report ↗
Two family frame · 4,128 sf lot · 0.6 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionGeneral
Roof1p · 1 filing · 17 docs
Floor 219p · 2 filings · 20 docs
Floor 120p · 2 filings · 20 docs
Cellar18p · 2 filings · 20 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
12/06/2023$704K—— → —$282/sf building
06/11/2021$900K—Private party → Private party$361/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
THOMAS C. TUNG, P.E.203/06/2025
2 BY 4 ARCHITECTURE PC803/14/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
K A INTERIOR DESIGN1203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
WXF INCGeneral Contractor1107/08/2026
MPS PLUMBING & HEATING INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
2 BY 4 ARCHITECTURE P.C.4737903/06/2025
BIG APPLE GROUP NY A RMA9168403/06/2025
DINGS ENGINEERING PC2051403/06/2025
FLUSHING ENGINEERING SERV4373403/06/2025
Building Lifecycle
All (108)Filed (9)Permit Issued (6)Signed Off (3)Violation (9)Inspection (7)Objection (44)Special Inspection (30)
06/25/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
05/20/2025
Objection resolved — Addressed
03/18/2025
Objection raised — Scope
03/06/2025
Filed — Alteration CO
PROPOSED VERTICAL ENLARGEMENT AT CELLAR. 1ST THRU 2ND FLOOR, ATTIC AND ROOF. PROPOSED CONSTRUCTION WORKS TO CONVERT A ONE FAMILY TO A TWO FAMILY DWELLING AS PER PLAN. OBTAIN NEW CERTIFICATE OF OCCUPANCY.
Q00578381-P3
03/05/2025
Special inspection requirement — Concrete - Cast-In-Place
CHI WANG LEE
03/05/2025
Special inspection requirement — Fire-Resistance Rated Construction
CHI WANG LEE
03/05/2025
Special inspection requirement — Lighting controls
CHI WANG LEE
03/05/2025
Special inspection requirement — Fenestration areas
CHI WANG LEE
03/05/2025
Special inspection requirement — Insulation placement and R values
CHI WANG LEE
03/05/2025
Special inspection requirement — Interior lighting power
CHI WANG LEE
03/05/2025
Special inspection requirement — Fenestration air leakage
CHI WANG LEE
03/05/2025
Special inspection requirement — Air barrier - visual inspection
CHI WANG LEE
03/05/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
CHI WANG LEE
03/05/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
CHI WANG LEE
03/05/2025
Special inspection requirement — Masonry
CHI WANG LEE
03/05/2025
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
SOORJBALLY HARILALL
03/05/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
KY FU
03/05/2025
Special inspection requirement — Subgrade Inspections
Yanqi Ding
03/05/2025
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
Soorjbally Harilall
03/05/2025
Special inspection requirement — Energy Code Compliance Inspections
CHI WANG LEE
06/20/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
12/21/2023
Permit issued — General Construction
Q00578381-I1-GC
03/21/2023
Signed off — Alteration
Q00611388-I1
03/21/2023
Signed off — Alteration
PROPOSED GAS AND PLUMBING WORK ON CEL, 1ST AND 2ND FLOOR. GENERAL CONSTRUCTION WORK WAS FILED UNDER JOB# Q00578381.
Q00611405-I1
03/21/2023
Signed off — Alteration
INTERIOR RENOVATION ON 1ST AND 2ND FLOORS, ATTIC AND OSP, INSTALL SPLIT AC UNITS AS PER PLAN IN CONJUNCTION WITH A1 JOB# Q00578381.
Q00752175-I1
03/15/2023
Special inspection requirement — HVAC-R and service water heating equipment
CHI WANG LEE
03/15/2023
Special inspection requirement — HVAC-R and service water heating system controls
CHI WANG LEE
03/15/2023
Special inspection requirement — Final
CHI WANG LEE
03/15/2023
Special inspection requirement — Mechanical Systems
CHI WANG LEE
03/14/2023
Filed — Alteration
INTERIOR RENOVATION ON 1ST AND 2ND FLOORS, ATTIC AND OSP, INSTALL SPLIT AC UNITS AS PER PLAN IN CONJUNCTION WITH A1 JOB# Q00578381.
Q00752175-P1
03/14/2023
Special inspection requirement — Final
CHI WANG LEE
03/14/2023
Special inspection requirement — HVAC-R and service water heating equipment
CHI WANG LEE
03/14/2023
Special inspection requirement — HVAC-R and service water heating system controls
CHI WANG LEE
03/14/2023
Special inspection requirement — Mechanical Systems
CHI WANG LEE
02/23/2023
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
02/13/2023
Objection resolved — Addressed
02/07/2023
Objection resolved — Addressed
02/07/2023
Objection resolved — Addressed
01/22/2023
Objection raised — Fire_Protection
01/22/2023
Objection raised — Fire_Protection
01/22/2023
Objection raised — Other
01/19/2023
Filed — Alteration CO
PROPOSED VERTICAL ENLARGEMENT AT CELLAR. 1ST THRU 2ND FLOOR, ATTIC AND ROOF. PROPOSED CONSTRUCTION WORKS TO CONVERT A ONE FAMILY TO A TWO FAMILY DWELLING AS PER PLAN. OBTAIN NEW CERTIFICATE OF OCCUPANCY.
Q00578381-P2
01/11/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/04/2023
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
10/05/2022
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
08/01/2022
Filed — Alteration
PROPOSED GAS AND PLUMBING WORK ON CEL, 1ST AND 2ND FLOOR. GENERAL CONSTRUCTION WORK WAS FILED UNDER JOB# Q00578381.
Q00611405-P1
08/01/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
CHI WANG LEE
08/01/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
CHI WANG LEE
08/01/2022
Special inspection requirement — Energy Code Compliance Inspections
CHI WANG LEE
08/01/2022
Special inspection requirement — HVAC-R and service water heating equipment
CHI WANG LEE
08/01/2022
Special inspection requirement — HVAC-R and service water heating system controls
CHI WANG LEE
07/26/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
CHI WANG LEE
07/15/2022
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
07/12/2022
Permit issued — Mechanical Systems
Q00752175-I1-MS
07/08/2022
Filed — Alteration
INTERIOR RENOVATION ON 1ST AND 2ND FLOORS, ATTIC AND OSP, INSTALL SPLIT AC UNITS AS PER PLAN IN CONJUNCTION WITH A1 JOB# Q00578381.
Q00752175-I1
04/19/2022
Filed — Alteration CO
PROPOSED VERTICAL ENLARGEMENT AT CELLAR. 1ST THRU 2ND FLOOR, ATTIC AND ROOF. PROPOSED CONSTRUCTION WORKS TO CONVERT A ONE FAMILY TO A TWO FAMILY DWELLING AS PER PLAN. OBTAIN NEW CERTIFICATE OF OCCUPANCY.
Q00578381-P1
04/15/2022
Permit issued — Plumbing
Q00611405-I1-PL
04/04/2022
Permit issued — General Construction
Q00578381-I1-GC
02/11/2022
Permit issued — Construction Fence
Q00611388-I1-FN
02/10/2022
Filed — Alteration
PROPOSED GAS AND PLUMBING WORK ON CEL, 1ST AND 2ND FLOOR. GENERAL CONSTRUCTION WORK WAS FILED UNDER JOB# Q00578381.
Q00611405-I1
Latest 60 of 108 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedWXF INC12/21/2023
DOB NOWMechanical SystemsSigned-offWXF INC07/12/2022
DOB NOWPlumbingSigned-offMPS PLUMBING & HEATING IN04/15/2022
DOB NOWGeneral ConstructionPermit IssuedWXF INC04/04/2022
DOB NOWConstruction FenceSigned-offWXF INC02/11/2022
DOB NOWConstruction FenceSigned-offWXF INC10/19/2021
BISOTISSUEDACCORD POWER INC01/10/2023
2 projects · most recent 01/09/2023
General Wiring
FiledStatusContractorScope
01/09/2023CompleteNEWGRANGE ELECTRIC, INC—
04/11/2022CompleteKJK ELECTRIC INCGeneral Wiring
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
06/25/2025Pass-Final CND-Occupancy InspectionPassView ↗
06/20/2024Pass-Final CND-Occupancy InspectionPassView ↗
02/23/2023Pass-Final CND-Occupancy InspectionPassView ↗
01/11/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/04/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
10/05/2022Pass-Final PL - UndergroundPassView ↗
07/15/2022Pass-Final PL - UndergroundPassView ↗
▾Special Inspection Requirements (DOB NOW) — 52
DateRequirementInspectorRole
03/05/2025Concrete - Cast-In-PlaceCHI WANG LEEspecial
03/05/2025Fire-Resistance Rated ConstructionCHI WANG LEEprogress
03/05/2025Lighting controlsCHI WANG LEEenergy_progress
03/05/2025Fenestration areasCHI WANG LEEenergy_progress
03/05/2025Insulation placement and R valuesCHI WANG LEEenergy_progress
03/05/2025Interior lighting powerCHI WANG LEEenergy_progress
03/05/2025Fenestration air leakageCHI WANG LEEenergy_progress
03/05/2025Air barrier - visual inspectionCHI WANG LEEenergy_progress
03/05/2025Fenestration and door U-factor and product ratingsCHI WANG LEEenergy_progress
03/05/2025Fire-Resistant Penetrations and JointsCHI WANG LEEspecial
03/05/2025MasonryCHI WANG LEEspecial
03/05/2025Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationSOORJBALLY HARILALLspecial
03/05/2025Structural Stability – Alterations of existing buildingsKY FUspecial
03/05/2025Subgrade InspectionsYanqi Dingspecial
03/05/2025Subsurface Investigations (Borings/Test Pits)Soorjbally Harilallspecial
03/05/2025Energy Code Compliance InspectionsCHI WANG LEEprogress
03/15/2023HVAC-R and service water heating equipmentCHI WANG LEEenergy_progress
03/15/2023HVAC-R and service water heating system controlsCHI WANG LEEenergy_progress
03/15/2023FinalCHI WANG LEEprogress
03/15/2023Mechanical SystemsCHI WANG LEEspecial
03/14/2023FinalCHI WANG LEEprogress
03/14/2023HVAC-R and service water heating equipmentCHI WANG LEEenergy_progress
03/14/2023HVAC-R and service water heating system controlsCHI WANG LEEenergy_progress
03/14/2023Mechanical SystemsCHI WANG LEEspecial
08/01/2022HVAC-R and service water piping design and insulationCHI WANG LEEenergy_progress
Latest 25 of 52.
▾Documents — 149 on file (BIS + DOB NOW)
▸Plans & Drawings9
▸DOB NOWPlans/Sketch9
08/27/2026Q00611388-I1Request digital key ↗
08/26/2026Q00611405-I1Request digital key ↗
08/26/2026Q00611405-P1Request digital key ↗
Showing 3 of 9 on file for this type
▸Applications & Permits4
▸BISPLAN / WORK APPROVAL APPLICATION3
09/21/2023402470072Open ↗
07/19/2023402470072Open ↗
01/06/2023440762480Open ↗
▸BISWORK PERMIT APPLICATION1
01/10/2023440762480Open ↗
▸Zoning, Tax Lot & Property Records6
▸DOB NOWZD1: DOB Zoning Diagram5
08/13/2026Q00578381-I1Open ↗
08/13/2026Q00578381-P1Open ↗
08/13/2026Q00578381-P2Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026Q00578381-I1Open ↗
▸Seals & Professional Certifications64
▸DOB NOWProgress Inspector Seal & Signature32
09/02/2026Q00578381-P1Open ↗
09/02/2026Q00578381-P1Open ↗
09/02/2026Q00578381-P1Open ↗
Showing 3 of 32 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature20
09/02/2026Q00578381-P1Open ↗
09/02/2026Q00578381-P1Open ↗
09/02/2026Q00578381-P1Open ↗
Showing 3 of 20 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature10
08/27/2026Q00611388-I1Open ↗
08/26/2026Q00611405-I1Open ↗
08/26/2026Q00611405-P1Open ↗
Showing 3 of 10 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
01/06/2023440762480Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
01/06/2023440762480Open ↗
▸Trade Schedules & Equipment4
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)4
08/13/2026Q00578381-I1Open ↗
08/13/2026Q00578381-P2Open ↗
08/13/2026Q00578381-P1Open ↗
Showing 3 of 4 on file for this type
▸Safety & Tenant Protection9
▸DOB NOWStreet Tree Checklist5
08/13/2026Q00578381-P3Open ↗
08/13/2026Q00578381-P2Open ↗
08/13/2026Q00578381-P1Open ↗
Showing 3 of 5 on file for this type
▸BISTPP1: TENANT PROTECTION PLAN1
01/09/2023440762480Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026Q00578381-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026Q00578381-I1Open ↗
▸DOB NOWStreet Tree Sign Off1
08/13/2026Q00578381-I1Open ↗
▸Environmental & Asbestos8
▸DOB NOWDEP ACP-5: Asbestos Assessment Report8
08/26/2026Q00611405-I1Open ↗
08/26/2026Q00611405-P1Open ↗
08/25/2026Q00752175-I1Open ↗
Showing 3 of 8 on file for this type
▸Energy Compliance10
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
07/12/2023440762480Open ↗
01/10/2023440762480Open ↗
01/09/2023440762480Open ↗
▸DOB NOWEN2: As Built Energy Analysis.3
08/13/2026Q00578381-I1Open ↗
08/13/2026Q00611405-I1Open ↗
08/13/2026Q00752175-I1Open ↗
▸BISSOLAR TAX ABATEMENT APPLICATION1
07/19/2023440762480Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
01/06/2023440762480Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
07/12/2023440762480Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
01/06/2023440762480Open ↗
▸Inspections & Test Reports9
▸DOB NOWSOIL REPORT4
08/13/2026Q00578381-I1Open ↗
08/13/2026Q00578381-P1Open ↗
08/13/2026Q00578381-P2Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY3
07/12/2023440762480Open ↗
01/10/2023440762480Open ↗
01/09/2023440762480Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026Q00578381-I1Open ↗
▸DOB NOWTR4 Plot Diagram1
08/13/2026Q00578381-I1Open ↗
▸Approvals, Objections & Sign-offs3
▸BISLETTERS - SUPPORTING DOCUMENTATION1
07/19/2023440762480Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
07/19/2023440762480Open ↗
▸BISRevocation Letter1
02/12/2014402470072Open ↗
▸Cost, Insurance & Ownership3
▸BISCOST AFFIDAVIT3
07/18/2023440762480Open ↗
07/12/2023440762480Open ↗
01/06/2023440762480Open ↗
▸Filing & Intake Forms2
▸BISEFILING JOB APPLICATION COVER SHEET1
01/06/2023440762480Open ↗
▸BISADDITIONAL INFORMATION1
01/06/2023440762480Open ↗
▸Other Documents18
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone5
08/13/2026Q00578381-P1Open ↗
08/13/2026Q00584854-I1Open ↗
08/13/2026Q00578381-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWProperty Ownership Certification5
08/20/2026Q00578381-P1Open ↗
08/15/2026Q00578381-I1Open ↗
08/15/2026Q00578381-P3Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWPlot Diagram4
08/13/2026Q00578381-I1Open ↗
08/13/2026Q00578381-P2Open ↗
08/13/2026Q00578381-P3Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSite Survey: Initial3
08/13/2026Q00578381-I1Open ↗
08/13/2026Q00578381-P3Open ↗
08/13/2026Q00578381-P2Open ↗
▸DOB NOWFinal Survey1
08/13/2026Q00578381-I1Open ↗