| Owner | Filings | Most Recent |
|---|---|---|
| AKAM ASSOCIATES | 35 | 07/08/2026 |
| KINGS GROUP NY | 18 | 07/08/2026 |
| NTF MANAGEMENT | 3 | 07/08/2026 |
| 13TH STREET ASSOCIATES | 74 | 07/08/2026 |
| SIGNEXPO | 3 | 03/22/2026 |
| LAWERENCE PROPERTIES | 3 | 03/22/2026 |
| 7-11 13TH ST TENANTS CORP | 1 | 03/22/2026 |
| MIDBORO MANAGEMENT | 4 | 03/22/2026 |
| 7-11 EAST 13TH STREET TENANTS | 36 | 03/22/2026 |
| 7-11 E 13 ST TENNANTS | 10 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| R.J. MCGEE ENGINEERING, PLLC | 1 | 09/08/2026 |
| ANDREW FETHES ARCHITECT | 3 | 06/02/2026 |
| ZENITH HOME INSPECTIONS | 1 | 12/12/2025 |
| STUDIO HUJI | 1 | 08/22/2024 |
| LAUREN WEGEL ARCHITECT | 2 | 02/22/2024 |
| ANZ CONSULTING ENGINEERING, PLLC | 2 | 02/21/2024 |
| MJS ARCHITECT | 1 | 12/08/2023 |
| FABRICA ARCHITECTURE STUDIO | 2 | 11/08/2023 |
| ALPHA HOME DESIGN LLC | 3 | 11/06/2023 |
| CITY BUILDING NY ARCHITECT P.C. | 1 | 08/07/2023 |
| DAN IONESCU | 6 | 07/31/2023 |
| AMERILAND BROOK LLC | 2 | 04/13/2023 |
| VINCENT J. LIOTTA P.E. | 3 | 12/13/2022 |
| TWIG CONSULTING ENGINEERS PC | 4 | 10/19/2022 |
| MOHAMMAD AHEAD, PE | 1 | 02/04/2022 |
| SYED ENGINEERING, P.C. | 2 | 03/05/2021 |
| JOSE L. PENA,P.E. | 1 | 01/29/2020 |
| GURVINDER SINGH | 1 | 08/19/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| CLARKE CONSTRUCTION CONSULTANTS | 2 | 03/21/2026 |
| JP EXPEDITE | 2 | 03/21/2026 |
| J CALLAHAN CONSULTING | 10 | 03/21/2026 |
| GREEN LIGHT EXPEDITING LLC | 6 | 03/21/2026 |
| INDESIGN STUDIO | 6 | 03/21/2026 |
| LOUIS STRIAR | 4 | 03/21/2026 |
| JOE COFFEE COMPANY | 1 | 03/21/2026 |
| BOYD CONSULTING | 20 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| KINGS GROUP NY CORP | General Contractor | 12 | 07/08/2026 |
| GHCR, LLC | General Contractor | 8 | 07/08/2026 |
| HAIAN HONEST RENOVATION | General Contractor | 6 | 03/21/2026 |
| J. KANE CONTRACTING CORP | General Contractor | 4 | 07/08/2026 |
| KLE CONSTRUCTION INC | General Contractor | 3 | 03/21/2026 |
| MILLENNIUM HVAC NY INC | General Contractor | 3 | 03/21/2026 |
| CITY SIGNS | Scaffold | 2 | 07/08/2026 |
| CARY P O'BRIEN DESIGN LLC | General Contractor | 2 | 03/21/2026 |
| MCMANUS MECH MAINT P&H INC | Plumbing | 1 | 06/28/2026 |
| PAUL QUINN PLBG & HTG INC | Plumbing | 1 | 07/08/2026 |
| P.S.I. MECHANICAL | Plumbing | 1 | 07/08/2026 |
| ROCK E SMALL PLBG&HTG INC | Plumbing | 1 | 07/08/2026 |
| WHITESTONE PLUMBING CORP | Plumbing | 1 | 07/08/2026 |
| A ELECTRICAL MAIN SVC INC | Electrical | 1 | 03/22/2026 |
| L S SIGN | Scaffold | 1 | 07/08/2026 |
| KJK ELECTRIC INC | Electrical | 1 | 03/22/2026 |
| P.L. ELEC'L CONTR'G CORP | Electrical | 1 | 03/22/2026 |
| ROBIN ELECTRICAL CO., INC | Electrical | 1 | 03/22/2026 |
| PRIME PIPING & HEATING IN | Fire Protection | 1 | 07/08/2026 |
| SEAN COAKLEY P & H INC | Fire Protection | 1 | 07/08/2026 |
| PROJECT ONE CONTRACTING C | General Contractor | 1 | 07/08/2026 |
| DPH PLUMBING & HTG CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CHEN ENGINEERING SERVICES | 1826 | 2 | 02/22/2024 |
| ANZ CONSULTING ENGINEERIN | 3946 | 2 | 02/21/2024 |
| YAN GAO | 6619 | 2 | 09/26/2023 |
| CITY BUILDING NY ARCHITEC | 1394 | 1 | 08/07/2023 |
| AMERILAND BROOK LLC | 1506 | 2 | 04/13/2023 |
| VINCENT J. LIOTTA P. E. | 1974 | 3 | 12/13/2022 |
| WINTON GROUP ARCHITECTURE | 4343 | 1 | 12/08/2022 |
| TWIG SPECIAL INSPECTIONS | 885 | 2 | 10/19/2022 |
| DAN IONESCU ARCHITECTS | 8032 | 2 | 10/17/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | MCMANUS MECH MAINT P&H INC | 06/25/2026 |
| DOB NOW | Sign | Signed-off | ELMER DAWSON | 12/15/2025 |
| DOB NOW | General Construction | Signed-off | GHCR, LLC | 01/09/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | GHCR, LLC | 01/09/2025 |
| DOB NOW | Sign | Signed-off | ELMER DAWSON | 08/28/2024 |
| DOB NOW | General Construction | Signed-off | J KANE CONTRACTING | 05/01/2024 |
| DOB NOW | General Construction | Permit Issued | HAIAN HONEST RENOVATION | 04/19/2024 |
| DOB NOW | Plumbing | Signed-off | DPH PLUMBING & HTG CORP | 02/23/2024 |
| DOB NOW | General Construction | Signed-off | PROJECT ONE CONTRACTING C | 12/12/2023 |
| DOB NOW | General Construction | Permit Issued | HAIAN HONEST RENOVATION | 09/29/2023 |
| DOB NOW | Plumbing | Signed-off | P.S.I. MECHANICAL | 09/29/2023 |
| DOB NOW | General Construction | Signed-off | CARY P O'BRIEN DESIGN LLC | 09/22/2023 |
| DOB NOW | Mechanical Systems | Signed-off | MILLENNIUM HVAC NY INC | 09/18/2023 |
| DOB NOW | Sprinklers | Signed-off | SEAN COAKLEY P & H INC | 06/09/2023 |
| DOB NOW | Plumbing | Signed-off | PAUL QUINN PLBG & HTG INC | 05/15/2023 |
| DOB NOW | General Construction | Signed-off | J KANE CONTRACTING | 05/09/2023 |
| DOB NOW | Mechanical Systems | Signed-off | J KANE CONTRACTING | 05/05/2023 |
| DOB NOW | Plumbing | Permit Issued | WHITESTONE PLUMBING CORP | 05/05/2023 |
| DOB NOW | General Construction | Permit Issued | KLE CONSTRUCTION INC | 05/03/2023 |
| DOB NOW | Mechanical Systems | Permit Issued | GHCR, LLC | 10/11/2022 |
| DOB NOW | Sprinklers | Permit Issued | A M B MECHANICAL INC | 09/20/2022 |
| DOB NOW | Plumbing | Permit Issued | ROCK E SMALL PLBG&HTG INC | 06/28/2022 |
| DOB NOW | General Construction | Signed-off | GHCR, LLC | 05/09/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | KINGS GROUP NY CORP | 10/20/2021 |
| DOB NOW | Sidewalk Shed | Permit Issued | KINGS GROUP NY CORP | 03/10/2021 |
| DOB NOW | Supported Scaffold | Signed-off | KINGS GROUP NY CORP | 03/10/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | KINGS GROUP NY CORP | 09/22/2020 |
| DOB NOW | Sign | Signed-off | WEINFELD, ELLIOT | 01/30/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | KINGS GROUP NY CORP | 09/20/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | KINGS GROUP NY CORP | 08/20/2019 |
| BIS | — | ISSUED | NEXT GENERATION RESTORATION | 11/26/2024 |
| BIS | OT | ISSUED | COOPER WORKS INC | 08/12/2020 |
| BIS | OT | ISSUED | PA AVALANCHE CONSTRUCTION | 10/16/2019 |
| BIS | PL | ISSUED | CAM ENERGY HEATING AND ME | 04/10/2019 |
| BIS | PL | ISSUED | CHAMP PLUMBING & HTG CORP | 11/21/2018 |
| BIS | OT | ISSUED | CHAMPION COMBUSTION CORP | 11/21/2018 |
| BIS | PL | ISSUED | TOP PLUMBING SYSTEM INC | 09/26/2018 |
| BIS | OT | ISSUED | 360 INTERIOR CONCEPT HOLD | 08/16/2018 |
| BIS | OT | ISSUED | PA AVALANCHE CONSTRUCTION | 08/06/2018 |
| BIS | OT | ISSUED | AVALANCHE RENOVATION CORP | 10/17/2017 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 09/08/2026 | — | — | Air Conditioning Systems | Cooling |
| 04/13/2023 | Permit Issued | KLE CONSTRUCTION INC | Air Conditioning Systems | Cooling Mitsubishi Electric MXZ-SM36NAMHZ 36,000 BTU · Condensing Unit ×2 |
| 10/17/2022 | Permit Issued | GHCR, LLC | Air Conditioning Systems | Cooling Mitsubishi Electric DLCLRBH48MK 48,000 BTU · Split System ×10 DLCLRAH58AAK 42,000 BTU · Split System ×5 DLCSRBH18AAK 18,000 BTU · Split System ×5 PUMY-P48NKMU1 54,000 BTU · Vrf Outdoor ×5 __Junk__ DLCLRAH48MK 42,000 BTU · Split System ×5 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/08/2026 | — | — | Sprinkler System |
| 02/21/2024 | — | — | 10 heads |
| 10/19/2022 | Permit Issued | PRIME PIPING & HEATING IN | 106 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/08/2026 | — | — | Gas, Water/Sanitary |
| 06/02/2026 | Permit Issued | MCMANUS MECH MAINT P&H IN | Gas, Water/Sanitary |
| 02/21/2024 | Signed-off | DPH PLUMBING & HTG CORP | Water/Sanitary |
| 09/26/2023 | Signed-off | P.S.I. MECHANICAL | Water/Sanitary |
| 07/19/2023 | Permit Issued | ROCK E SMALL PLBG&HTG INC | Gas, Water/Sanitary |
| 04/13/2023 | Permit Issued | WHITESTONE PLUMBING CORP | Plumbing-Sprinkler, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/12/2025 | Complete | AMPERE ELECL SERVICES COR | — |
| 09/11/2024 | Complete | A ELECTRICAL MAIN SVC INC | — |
| 07/12/2024 | Complete | ROBIN ELECTRICAL CO., INC | General Wiring |
| 01/22/2024 | Complete | VALENTIS ELECTRIC, INC. | General Wiring |
| 10/04/2023 | Permit Issued | KJK ELECTRIC INC | General Wiring |
| 08/01/2022 | Complete | T. DIRUSSO ELEC'L CONT IN | General Wiring |
| 05/25/2022 | Permit Issued | ASCUATECH ELECTRICAL CORP | General Wiring |
| 03/18/2021 | Permit Issued | HIGH QUALITY ELECTRIC OF | — |
| 08/14/2019 | Permit Issued | RICHARD NEU | — |
| 01/13/2019 | Complete | ITKIN ELECTRIC CORP. | Boiler Controls |
| 06/07/2018 | Permit Issued | P.L. ELEC'L CONTR'G CORP | — |
| 05/25/2018 | Complete | P.S. MARCATO ELEV. CO INC | — |
| 05/08/2018 | Permit Issued | P.L. ELEC'L CONTR'G CORP | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/06/2023 | — | — | Fence |
| 02/04/2022 | — | — | Scaffold, Sidewalk Shed |
| 03/05/2021 | Permit Issued | KINGS GROUP NY CORP | Sidewalk Shed |
| 08/19/2019 | Signed-off | KINGS GROUP NY CORP | Sidewalk Shed |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/07/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/05/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/28/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/28/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/16/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 09/19/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/10/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/18/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/12/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/26/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 12/14/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/21/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/31/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/01/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 06/01/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/27/2022 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 11/29/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 11/02/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 10/04/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/30/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/30/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/20/2026 | Mechanical Systems | — | special |
| 07/20/2026 | Tenant Protection Plan Compliance | — | special |
| 07/20/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 07/20/2026 | Final | Robert McGee | progress |
| 07/20/2026 | HVAC-R and service water piping design and insulation | Christopher Middleton | energy_progress |
| 07/20/2026 | HVAC-R and service water heating equipment | Christopher Middleton | energy_progress |
| 07/20/2026 | HVAC-R and service water heating system controls | Christopher Middleton | energy_progress |
| 08/22/2024 | Final | Ryan Hung | progress |
| 03/01/2024 | Fire-Resistant Penetrations and Joints | HENLIA CHEN | special |
| 03/01/2024 | Structural Stability – Alterations of existing buildings | HENLIA CHEN | special |
| 03/01/2024 | Lighting controls | LAUREN WEGEL | energy_progress |
| 03/01/2024 | Lighting in dwelling units | LAUREN WEGEL | energy_progress |
| 03/01/2024 | Final | LAUREN WEGEL | progress |
| 03/01/2024 | Construction Operations Influencing Adjacent Structures | HENLIA CHEN | special |
| 02/22/2024 | Structural Stability – Alterations of existing buildings | HENLIA CHEN | special |
| 02/22/2024 | Lighting controls | LAUREN WEGEL | energy_progress |
| 02/22/2024 | Final | LAUREN WEGEL | progress |
| 02/22/2024 | Lighting in dwelling units | LAUREN WEGEL | energy_progress |
| 02/22/2024 | Fire-Resistant Penetrations and Joints | HENLIA CHEN | special |
| 02/22/2024 | Construction Operations Influencing Adjacent Structures | HENLIA CHEN | special |
| 02/15/2024 | HVAC-R and service water piping design and insulation | ALBERT ZIRINO | energy_progress |
| 02/15/2024 | HVAC-R and service water heating equipment | ALBERT ZIRINO | energy_progress |
| 02/15/2024 | Fire-Resistant Penetrations and Joints | ALBERT ZIRINO | special |
| 02/15/2024 | HVAC-R and service water heating system controls | ALBERT ZIRINO | energy_progress |
| 12/08/2023 | HVAC-R and service water heating system controls | ALBERT ZIRINO | energy_progress |