RoofUnder Construction3p · 4 filings · 20 docs
ArchitectureGeneralMechanicalStructural
FACADE REPAIRS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE,EGRESS OR OCCUPANCY.
On file for this project
14 documents · 2 drawing sheets
FACADE RESTORATION AND INSPECTION. Designated Primary Site Supervisor: Russel Perrier
On file for this project
15 documents · 1 drawing sheet
FISP INSPECTION (Facade Inspection Safety Program) INDUSTRIAL ROPE ACCESS TECHNIQUES AND METHODS. SEE ATTACHED PLANS. Designated Primary Site supervisor: Jesus Decola
On file for this project
2 documents · 1 drawing sheet
Latest 3 of 4 filings on this floor.
Floor 281p · 1 filing · 5 docs
Architecture
INSTALLATION OF NON LOAD BEARING PARTITIONS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents · 1 drawing sheet
Floor 27
Floor 26
Floor 251p · 1 filing · 5 docs
Architecture
INSTALLATION OF NON LOAD BEARING PARTITIONS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents · 1 drawing sheet
Floor 24
Floor 23
Floor 22
Floor 21
Floor 20
Floor 19Under Construction2 filings · 11 docs
Issued Permit Scope
Protection and Mechanical Methods · Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents
SHORING AND NETTING TO BE INSTALLED AS PER DRAWINGS FOR LOCAL LAW 11 REPAIRS
On file for this project
6 documents
Floor 18Under Construction24p · 6 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbing
Issued Permit Scope
Plumbing · Sprinklers · Supported Scaffold
Modification to the existing sprinkler system and removal and installation of plumbing fixtures as per plans filed.
On file for this project
6 documents · 2 drawing sheets
Modification to existing HVAC system as per plans filed herewith.
On file for this project
9 documents · 2 drawing sheets
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents
Latest 3 of 6 filings on this floor.
Floor 17Under Construction1 filing · 5 docs
Issued Permit Scope
Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents
Floor 16Under Construction1 filing · 5 docs
Issued Permit Scope
Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents
Floor 15Under Construction10p · 5 filings · 20 docs
Fire ProtectionMechanicalPlumbing
Issued Permit Scope
Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents
PLUMBING/SPRINKLER FILING AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents · 3 drawing sheets
MECHANICAL FILING AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
6 documents · 1 drawing sheet
Latest 3 of 5 filings on this floor.
Floor 14Under Construction1 filing · 5 docs
Issued Permit Scope
Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents
Floor 13Under Construction1 filing · 5 docs
Issued Permit Scope
Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents
Floor 12Under Construction24p · 3 filings · 19 docs
ArchitectureFire ProtectionPlumbing
Issued Permit Scope
General Construction · Plumbing · Sprinklers · Supported Scaffold
FILING PLUMBING AND SPRINKLER AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY,
On file for this project
8 documents
FILING HEREWITH FOR INTERIOR FIT OUT AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
6 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents
Floor 11Under Construction1 filing · 5 docs
Issued Permit Scope
Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents
Floor 10Under Construction1 filing · 5 docs
Issued Permit Scope
Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents
Floor 9Under Construction1 filing · 5 docs
Issued Permit Scope
Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents
Floor 8Under Construction6p · 4 filings · 19 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents
PROPOSE TO INSTALL (2) 3 TON SPLIT AC SYSTEMS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
3 documents · 1 drawing sheet
MODIFICATION TO EXISTING STANDPIPE SYSTEM AS PER PLANS FILED HEREWITH.NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents · 1 drawing sheet
Latest 3 of 4 filings on this floor.
Floor 7Under Construction22p · 6 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbing
Issued Permit Scope
Plumbing · Supported Scaffold
FACADE REPAIRS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE,EGRESS OR OCCUPANCY.
On file for this project
14 documents · 1 drawing sheet
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents
Mechanical demolition and renovations / modifications to existing ductwork as per plans filed herewith. No change to use, egress, or occupancy.
On file for this project
5 documents · 2 drawing sheets
Latest 3 of 6 filings on this floor.
Floor 6Under Construction16p · 5 filings · 20 docs
DMFire ProtectionMechanicalPlumbing
Issued Permit Scope
Plumbing · Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents
Mechanical demolition and renovations / modifications to existing ductwork as per plans filed herewith. No change to use, egress, or occupancy.
On file for this project
5 documents · 1 drawing sheet
Plumbing / sprinkler modifications and demolition as per plans filed herewith. No change to use, egress, or occupancy.
On file for this project
7 documents · 3 drawing sheets
Latest 3 of 5 filings on this floor.
Floor 5Under Construction32p · 9 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Supported Scaffold
FILING HEREWITH PLUMBING FILING AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents
FILING HEREWITH MECHANICAL FILING AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents
Latest 3 of 8 filings on this floor.
Floor 4Under Construction1 filing · 5 docs
Issued Permit Scope
Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents
Floor 3Under Construction1p · 2 filings · 17 docs
Structural
Issued Permit Scope
Supported Scaffold
Filing herewith for Anchor point supports and infills on cellar, 1st-4th & Roof.
On file for this project
12 documents · 1 drawing sheet
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents
Floor 2Under Construction1p · 3 filings · 19 docs
Structural
Issued Permit Scope
Protection and Mechanical Methods · Supported Scaffold
INSTALLATION OF TEMPORARY OVERHEAD PROTECTION AS PER PLAN. THERE IS NO CHANGE IN USE, EGRESS, OR OCCUPANCY. THE OVERHEAD PROTECTION ON THE 219 EAST 44TH STREET BUILDING SOUTH ELEVATION 2ND FLOOR TERRACE.
On file for this project
2 documents
Filing herewith for Anchor point supports and infills on cellar, 1st-4th & Roof.
On file for this project
12 documents · 1 drawing sheet
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents
Floor 1Under Construction1p · 2 filings · 16 docs
Architecture
Issued Permit Scope
Supported Scaffold
Garage repairs. No change in egress, use or occupancy.
On file for this project
11 documents · 1 drawing sheet
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents
Cellar3p · 1 filing · 11 docs
ArchitectureStructural
Garage repairs. No change in egress, use or occupancy.
On file for this project
11 documents · 3 drawing sheets
Sub-Cellar3p · 1 filing · 11 docs
ArchitectureStructural
Garage repairs. No change in egress, use or occupancy.
On file for this project
11 documents · 3 drawing sheets
Basement2p · 1 filing · 7 docs
Mechanical
Condenser water piping and valve replacements from cellar to roof
On file for this project
7 documents · 2 drawing sheets