| Owner | Filings | Most Recent |
|---|---|---|
| TENERE MANAGEMENT GOUP | 2 | 09/17/2026 |
| TENERE MANAGEMENT | 1 | 08/28/2026 |
| CLP 74 LEONARD LLC | 12 | 03/22/2026 |
| TODISH & CO. | 1 | 03/22/2026 |
| 74 LEONARD ST REALTY ASSOC | 3 | 03/22/2026 |
| MICHAEL A LADISH & CO. | 1 | 03/22/2026 |
| LEORNARD REALTY CORP. | 1 | 03/22/2026 |
| CLASSIC REALTY MGMT CO | 1 | 03/22/2026 |
| SMASHER EST CORP | 1 | 03/22/2026 |
| SAMSHER ESTATES CORP | 2 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/25/2017 | $21.2M | — | — → — | $870/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| PAKNIA ENGINEERING, PC | 4 | 07/13/2026 |
| JON LIBASCI | 6 | 02/17/2026 |
| MOHAMMAD AHEAD, PE | 1 | 04/18/2023 |
| DOMINICK PILLA | 2 | 03/30/2023 |
| CES ENGINEERING LLC | 3 | 11/15/2022 |
| AFM INSPECTIONS & ENGINEERING, PLLC | 1 | 06/30/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| JAM CONSULTANTS, INC. | 22 | 03/21/2026 |
| PAKNIA ENGINEERING & ARCHITECTURE, | 2 | 03/21/2026 |
| LOUIS STRIAR | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| HI-TECH C.P.M. CORP | General Contractor | 6 | 07/08/2026 |
| AVON PLBG & HTG INC | Fire Protection | 1 | 07/08/2026 |
| FLOW-RIGHT FIRE SUPP CORP | Fire Protection | 1 | 09/17/2026 |
| ROBERT MARCHISOTTO | Electrical | 1 | 03/21/2026 |
| ULTRA GENERAL CONTRACTING INC. | General Contractor | 1 | 07/08/2026 |
| AVON PLBG & HTG INC | Plumbing | 1 | 07/08/2026 |
| FM95 NY | Scaffold | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| PAKNIA ENGINEERING, PC | 1462 | 2 | 06/15/2026 |
| JON LIBASCI | 3068 | 7 | 02/17/2026 |
| DOMINICK R. PILLA | 1300 | 2 | 03/30/2023 |
| CES ENGINEERING LLC | 1277 | 1 | 11/10/2022 |
| METRIC CONSULTING AND INS | 1803 | 1 | 11/09/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sprinklers | Permit Issued | FLOW-RIGHT FIRE SUPP CORP | 09/16/2026 |
| DOB NOW | Structural | Signed-off | HI-TECH C.P.M. CORP | 09/05/2023 |
| DOB NOW | General Construction | Permit Issued | HI-TECH C.P.M. CORP | 05/23/2023 |
| DOB NOW | Sign | Signed-off | RED HOOK SIGN AND ELECT | 04/25/2023 |
| DOB NOW | Sprinklers | Signed-off | AVON PLBG & HTG INC | 04/03/2023 |
| DOB NOW | Construction Fence | Signed-off | HI-TECH C.P.M. CORP | 03/28/2023 |
| DOB NOW | Mechanical Systems | Signed-off | HI-TECH C.P.M. CORP | 03/24/2023 |
| DOB NOW | Plumbing | Signed-off | AVON PLBG & HTG INC | 03/13/2023 |
| DOB NOW | General Construction | Signed-off | HI-TECH C.P.M. CORP | 11/04/2022 |
| DOB NOW | Construction Fence | Signed-off | ULTRA GENERAL CONTRACTING INC. | 06/30/2022 |
| BIS | OT | ISSUED | ULTRA GENERAL CONTRACTING INC. | 02/24/2026 |
| BIS | OT | ISSUED | ULTRA GENERAL CONTRACTING INC. | 07/12/2022 |
| BIS | OT | ISSUED | EMPIRE ECS, LLC | 03/03/2020 |
| BIS | SP | ISSUED | PEAK FIRE PROTECTION LLC | 08/28/2018 |
| BIS | PL | ISSUED | PRO STAR PLBG,HTG&MECH IN | 09/05/2017 |
| BIS | SP | ISSUED | PEAK FIRE PROTECTION LLC | 08/30/2017 |
| BIS | PL | ISSUED | ABSOLUTE MECH CO. INC | 04/18/2017 |
| BIS | EQ | ISSUED | S&E BRIDGE & SCAFFOLD LLC. | 12/14/2016 |
| BIS | OT | ISSUED | NORDEST SERVICES LLC | 10/07/2016 |
| BIS | SP | ISSUED | PEAK FIRE PROTECTION LLC | 08/25/2016 |
| BIS | PL | ISSUED | PRO STAR PLBG,HTG&MECH IN | 08/24/2016 |
| BIS | OT | ISSUED | GILBANE BUILDING COMPANY | 08/22/2016 |
| BIS | OT | ISSUED | GILBANE BUILDING COMPANY | 08/22/2016 |
| BIS | MH | ISSUED | GILBANE BUILDING COMPANY | 08/22/2016 |
| BIS | PL | ISSUED | ABSOLUTE MECH CO. INC | 03/25/2016 |
| BIS | BL | ISSUED | ABSOLUTE MECH CO. INC | 03/24/2016 |
| BIS | OT | ISSUED | RITE-WAY INTERNAL REMOVAL INC | 01/12/2016 |
| BIS | OT | ISSUED | LOS DOS ASES INC | 12/14/2015 |
| BIS | OT | ISSUED | EFFICIENT PL & HEATING CORP | 06/29/2007 |
| BIS | PL | ISSUED | GO GREENER PLUMBING LLC | 06/18/2007 |
| BIS | — | ISSUED | GEIGER ROOFING CO. INC. | 04/13/2001 |
| BIS | PL | ISSUED | AMOK INC | 04/13/2001 |
| BIS | PL | ISSUED | AMOK INC | 11/28/1994 |
| BIS | — | ISSUED | KNITTING FACTORY CLUB INC | 08/01/1994 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 02/17/2026 | Signed-off | HI-TECH C.P.M. CORP | Associated Ducts and Piping | Ducts & Piping N/A n/a 1 BTU · Ductwork ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/17/2026 | Permit Issued | FLOW-RIGHT FIRE SUPP CORP | 1 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/13/2026 | — | — | Gas, Water/Sanitary |
| 02/17/2026 | Signed-off | AVON PLBG & HTG INC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/20/2026 | Permit Issued | OMD ELECTRICAL CORP | 19 meters, 1 new_meters |
| 07/23/2026 | Permit Issued | LEADER ELECTRIC CO., INC | General Wiring |
| 07/23/2026 | Permit Issued | LEADER ELECTRIC CO., INC | General Wiring |
| 10/23/2025 | Complete | LEADER ELECTRIC CO., INC | 21 meters |
| 01/10/2024 | Complete | Y.S ELECTRIC | General Wiring, Lighting |
| 11/16/2022 | Complete | Y.S ELECTRIC | General Wiring, Lighting |
| 08/18/2022 | Permit Issued | ROBERT CHIMENTI | 19 meters, 1 new_meters |
| 08/12/2022 | Permit Issued | LEADER ELECTRIC CO., INC | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/12/2024 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 07/23/2024 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 03/25/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/06/2024 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 08/16/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/14/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 04/07/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 03/20/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/14/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/27/2026 | Fire-Resistant Penetrations and Joints | Edouard Paknia | special |
| 03/11/2026 | Sprinkler Systems | — | special |
| 03/10/2026 | Fire-Resistant Penetrations and Joints | jon libasci | special |
| 03/10/2026 | Fire-Resistance Rated Construction | jon libasci | progress |
| 02/04/2026 | Fire-Resistance Rated Construction | jon libasci | progress |
| 02/04/2026 | Fire-Resistant Penetrations and Joints | jon libasci | special |
| 05/23/2024 | Fire-Resistant Penetrations and Joints | jon libasci | special |
| 05/23/2024 | Fire-Resistance Rated Construction | jon libasci | progress |
| 09/06/2023 | Fire-Resistant Penetrations and Joints | — | special |
| 09/06/2023 | Fire-Resistance Rated Construction | — | progress |
| 08/14/2023 | Post-installed Anchors | Dominick Pilla | special |
| 08/14/2023 | Structural Stability – Alterations of existing buildings | Dominick Pilla | special |
| 08/14/2023 | Structural Steel - High Strength Bolting | Dominick Pilla | special |
| 08/14/2023 | Aluminum Construction | SAMI HAJJAR P.E | special |
| 08/14/2023 | Tenant Protection Plan Compliance | jon libasci | special |
| 08/14/2023 | Structural Wood Frame | Dominick Pilla | progress |
| 08/14/2023 | Structural Steel - Details | Dominick Pilla | special |
| 08/14/2023 | Final | Dominick Pilla | progress |
| 08/14/2023 | Structural Steel - Welding | Dominick Pilla | special |
| 08/01/2023 | Aluminum Construction | — | special |
| 04/18/2023 | Final | MOHAMMAD AHEAD | progress |
| 03/24/2023 | Structural Steel - Details | Dominick Pilla | special |
| 03/24/2023 | Structural Steel - Welding | Dominick Pilla | special |
| 03/24/2023 | Tenant Protection Plan Compliance | — | special |
| 03/24/2023 | Final | Dominick Pilla | progress |