← Back
Zoned commercial or Manhattan residential
788 FOREST AVENUE
STATEN ISLAND · BIN 5008057
💬 Discuss this project
2025Year Built
—Stories
V1Building Class
R3-1Zoning
1,620 sfGross Floor Area
0Units
2 Open Violations ▸FDNY Report ↗
Zoned commercial or Manhattan residential · Owner of record: HAJIRAN LLC · 5,650 sf lot · 0.29 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalPlumbingGeneral
Floor 213p · 2 filings · 20 docs
Floor 112p · 2 filings · 20 docs
Cellar12p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
GOHAR CONSTRUCTION4309/29/2026
HAJIRAN LLC203/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MEDINA ENERGY GROUP, LLC1408/12/2026
AK CONSULTING SERVICES, INC111/27/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
AK CONSULTING SERVICES203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
GOHAR CONSTRUCTION CORPGeneral Contractor909/29/2026
SUPERIOR PLUMBING & HEATINGPlumbing207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MEDINA-YAN ENGINEERING CO86371208/12/2026
Building Lifecycle
All (141)Filed (15)Permit Issued (10)Signed Off (4)Violation (18)Inspection (5)Objection (59)Special Inspection (30)
09/28/2026
Permit issued — Curb Cut
S01142056-I1-CC
08/31/2026
Special inspection requirement — Exterior lighting power
JUAN MEDINA YAN
08/31/2026
Special inspection requirement — Fire-Resistance Rated Construction
JUAN MEDINA YAN
08/31/2026
Special inspection requirement — Metering
JUAN MEDINA YAN
08/31/2026
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
JUAN MEDINA YAN
08/31/2026
Special inspection requirement — Air barrier - visual inspection
JUAN MEDINA YAN
08/31/2026
Special inspection requirement — Construction Operations Influencing Adjacent Structures
JUAN MEDINA YAN
08/31/2026
Special inspection requirement — Interior lighting power
JUAN MEDINA YAN
08/31/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
JUAN MEDINA YAN
08/31/2026
Special inspection requirement — Permanent certificate
JUAN MEDINA YAN
08/31/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
JUAN MEDINA YAN
08/31/2026
Special inspection requirement — Insulation placement and R values
JUAN MEDINA YAN
08/31/2026
Special inspection requirement — Fenestration areas
JUAN MEDINA YAN
08/31/2026
Special inspection requirement — Air barrier — testing
JUAN MEDINA YAN
08/31/2026
Special inspection requirement — Subgrade Inspections
JUAN MEDINA YAN
08/31/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
JUAN MEDINA YAN
08/31/2026
Special inspection requirement — Fenestration air leakage
JUAN MEDINA YAN
08/31/2026
Special inspection requirement — Electric vehicle service equipment requirements
JUAN MEDINA YAN
08/31/2026
Special inspection requirement — Lighting controls
JUAN MEDINA YAN
08/31/2026
Special inspection requirement — Energy Code Compliance Inspections
JUAN MEDINA YAN
08/31/2026
Special inspection requirement — Wood – Seismic Resistance
JUAN MEDINA YAN
08/31/2026
Special inspection requirement — Maintenance information
JUAN MEDINA YAN
08/28/2026
Special inspection requirement — Energy Code Compliance Inspections
JUAN MEDINA YAN
08/28/2026
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
JUAN MEDINA YAN
08/28/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
JUAN MEDINA YAN
08/28/2026
Special inspection requirement — HVAC-R and service water heating system controls
JUAN MEDINA YAN
08/28/2026
Special inspection requirement — Metering
JUAN MEDINA YAN
08/28/2026
Special inspection requirement — HVAC-R and service water heating equipment
JUAN MEDINA YAN
08/28/2026
Special inspection requirement — Permanent certificate
JUAN MEDINA YAN
08/28/2026
Special inspection requirement — Maintenance information
JUAN MEDINA YAN
08/28/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
JUAN MEDINA YAN
08/12/2026
Filed — New Building
PLUMBING WORK ASSOCIATED WITH NEW BUILDING
S00928967-P5
07/21/2026
Objection resolved — Resolved
07/01/2026
Objection raised — Scope
06/18/2026
Filed — New Building
MECHANICAL WORK ASSOCIATED WITH BUILDING RECONSTRUCTION
S01141989-P1
05/14/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
04/03/2026
Permit issued — Mechanical Systems
S01141989-S3-MS
03/27/2026
Signed off — Alteration
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE AT 788 FOREST AVENUE, STATEN ISLAND AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION
S00967999-I1
03/10/2026
Objection resolved — Addressed
01/02/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/05/2025
Filed — New Building
PLUMBING WORK ASSOCIATED WITH NEW BUILDING
S00928967-P3
11/05/2025
Objection resolved — Addressed
10/20/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
09/08/2025
Signed off — New Building
MECHANICAL WORK ASSOCIATED WITH BUILDING RECONSTRUCTION
S01141989-S1
08/27/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
08/27/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
08/02/2025
Filed — New Building
PLUMBING WORK ASSOCIATED WITH NEW BUILDING
S00928967-P2
07/28/2025
Objection resolved — Addressed
07/28/2025
Objection resolved — Addressed
07/28/2025
Objection resolved — Addressed
07/28/2025
Objection resolved — Addressed
07/09/2025
Signed off — New Building
MECHANICAL WORK ASSOCIATED WITH BUILDING RECONSTRUCTION
S01141989-S2
06/09/2025
Permit issued — Plumbing
S00928967-S1-PL
05/28/2025
Permit issued — Structural
S01141989-S1-ST
05/28/2025
Permit issued — Foundation
S01141989-S2-FO
05/16/2025
Permit issued — General Construction
S01141989-I1-GC
05/16/2025
Permit issued — Construction Fence
S00967999-I1-FN
05/07/2025
Objection resolved — Addressed
02/25/2025
Violation issued (ECB, closed)
Construction
Latest 60 of 141 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWCurb CutPermit IssuedGOHAR CONSTRUCTION CORP09/28/2026
DOB NOWMechanical SystemsSigned-offGOHAR CONSTRUCTION CORP04/03/2026
DOB NOWPlumbingPermit IssuedSUPERIOR PLUMBING & HEATI06/09/2025
DOB NOWStructuralSigned-offGOHAR CONSTRUCTION CORP05/28/2025
DOB NOWFoundationSigned-offGOHAR CONSTRUCTION CORP05/28/2025
DOB NOWGeneral ConstructionPermit IssuedGOHAR CONSTRUCTION CORP05/16/2025
DOB NOWConstruction FenceSigned-offGOHAR CONSTRUCTION CORP05/16/2025
DOB NOWPlumbingPermit IssuedSUPERIOR PLUMBING & HEATI05/07/2024
DOB NOWFull DemolitionSigned-offGOHAR CONSTRUCTION CORP01/02/2024
DOB NOWConstruction FenceSigned-offGOHAR CONSTRUCTION CORP11/28/2023
1 project · most recent 06/18/2026
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
06/18/2026Signed-offGOHAR CONSTRUCTION CORPHeating and Air Conditioning Systems
Heat / Cool
Gree GREE - 4LIV18HP230V1AO 18,000 BTU · Split System ×2
GREE - MUL18HP230V1R32AO 18,000 BTU · Split System ×2
GREE - MUL30HP230V1R32AO 30,000 BTU · Split System ×2
1 project · most recent 08/12/2026
Gas Water/Sanitary
FiledStatusContractorScope
08/12/2026Permit IssuedSUPERIOR PLUMBING & HEATIGas, Water/Sanitary
1 project · most recent 06/27/2025
General Wiring
FiledStatusContractorScope
06/27/2025CompleteDORION NORTON ELECL CONTGeneral Wiring
1 project · most recent 06/18/2026
Steel Concrete Wood
FiledStatusContractorScope
06/18/2026Signed-offGOHAR CONSTRUCTION CORPSteel, Concrete, Wood
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
05/14/2026Pass-Final CND-Occupancy InspectionPassView ↗
01/02/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
10/20/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/27/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
08/27/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 138
DateRequirementInspectorRole
08/31/2026Fenestration and door U-factor and product ratingsJUAN MEDINA YANenergy_progress
08/31/2026Permanent certificateJUAN MEDINA YANenergy_progress
08/31/2026Fenestration air leakageJUAN MEDINA YANenergy_progress
08/31/2026Exterior lighting powerJUAN MEDINA YANenergy_progress
08/31/2026Fenestration areasJUAN MEDINA YANenergy_progress
08/31/2026Insulation placement and R valuesJUAN MEDINA YANenergy_progress
08/31/2026MeteringJUAN MEDINA YANenergy_progress
08/31/2026Air barrier - visual inspectionJUAN MEDINA YANenergy_progress
08/31/2026Interior lighting powerJUAN MEDINA YANenergy_progress
08/31/2026Air barrier — testing JUAN MEDINA YANenergy_progress
08/31/2026Lighting controlsJUAN MEDINA YANenergy_progress
08/31/2026Electric vehicle service equipment requirementsJUAN MEDINA YANenergy_progress
08/31/2026Maintenance informationJUAN MEDINA YANenergy_progress
08/31/2026Wood – Seismic ResistanceJUAN MEDINA YANspecial
08/31/2026Fire-Resistant Penetrations and JointsJUAN MEDINA YANspecial
08/31/2026Subgrade InspectionsJUAN MEDINA YANspecial
08/31/2026Structural Stability – Alterations of existing buildingsJUAN MEDINA YANspecial
08/31/2026Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationJUAN MEDINA YANspecial
08/31/2026Construction Operations Influencing Adjacent StructuresJUAN MEDINA YANspecial
08/31/2026Energy Code Compliance InspectionsJUAN MEDINA YANprogress
08/31/2026Fire-Resistance Rated ConstructionJUAN MEDINA YANprogress
08/28/2026Energy Code Compliance InspectionsJUAN MEDINA YANprogress
08/28/2026HVAC-R and service water heating equipmentJUAN MEDINA YANenergy_progress
08/28/2026Permanent certificateJUAN MEDINA YANenergy_progress
08/28/2026MeteringJUAN MEDINA YANenergy_progress
Latest 25 of 138.
▾Documents — 112 on file (BIS + DOB NOW)
▸Plans & Drawings7
▸DOB NOWPlans/Sketch7
08/22/2026S00967999-I1Request digital key ↗
08/20/2026S01142056-I1Request digital key ↗
08/20/2026S01141989-I1Request digital key ↗
Showing 3 of 7 on file for this type
▸Applications & Permits4
▸BISPLAN / WORK APPROVAL APPLICATION2
02/25/2025540265504Open ↗
02/03/2025540265504Open ↗
▸BISBPP-16 - Application for waiver of curb alignment and/or sidewalk and curb1
04/08/2025540265504Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation1
05/06/2025540265504Open ↗
▸Zoning, Tax Lot & Property Records7
▸DOB NOWZD1: DOB Zoning Diagram3
08/14/2026S01141989-P1Open ↗
08/13/2026S00928967-I1Open ↗
08/13/2026S01141989-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)2
08/14/2026S01141989-P1Open ↗
08/13/2026S01141989-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp2
08/13/2026S01141989-I1Open ↗
08/13/2026S00928967-I1Open ↗
▸Seals & Professional Certifications54
▸DOB NOWProgress Inspector Seal & Signature21
09/02/2026S01141989-S3Open ↗
09/02/2026S01141989-S3Open ↗
09/02/2026S01141989-S3Open ↗
Showing 3 of 21 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature19
09/27/2026S00928948-I1Open ↗
09/27/2026S00928948-I1Open ↗
09/02/2026S01141989-S3Open ↗
Showing 3 of 19 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature12
08/20/2026S01142056-I1Open ↗
08/20/2026S01141989-P1Open ↗
08/13/2026S00928948-I1Open ↗
Showing 3 of 12 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
02/03/2025540265504Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
02/03/2025540265504Open ↗
▸Trade Schedules & Equipment5
▸DOB NOWElectric Cut-Off1
08/13/2026S00928948-I1Open ↗
▸DOB NOWSewer Cut-Off1
08/13/2026S00928948-I1Open ↗
▸DOB NOWWater Cut-Off1
08/13/2026S00928948-I1Open ↗
▸DOB NOWGas Cut-Off1
08/13/2026S00928948-I1Open ↗
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)1
08/13/2026S00928967-I1Open ↗
▸Safety & Tenant Protection3
▸DOB NOWStreet Tree Checklist2
08/14/2026S01141989-P1Open ↗
08/13/2026S01141989-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026S01141989-I1Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/13/2026S00928948-P1Open ↗
08/13/2026S00928948-I1Open ↗
▸DOB NOWRodent Control1
08/13/2026S00928948-I1Open ↗
▸Inspections & Test Reports4
▸BISBPP - Inspection Appointment Form1
04/08/2025540265504Open ↗
▸BISBPP-9 - Request for Builders Pavement Field Inspection1
04/22/2025540265504Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026S01141989-S2Open ↗
▸DOB NOWSOIL REPORT1
08/13/2026S01141989-S2Open ↗
▸Approvals, Objections & Sign-offs1
▸BISBPP-8 - Request Items for Builders Pavement Plan Signoff1
05/06/2025540265504Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
04/08/2025540265504Open ↗
04/08/2025540265504Open ↗
▸Filing & Intake Forms4
▸BISADDITIONAL INFORMATION2
04/22/2025540265504Open ↗
04/22/2025540265504Open ↗
▸BISEFILING COVER SHEET1
04/08/2025540265504Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
04/08/2025540265504Open ↗
▸Other Documents18
▸DOB NOWProperty Ownership Certification5
08/14/2026S01141989-P1Open ↗
08/13/2026S01141989-I1Open ↗
08/13/2026S00928948-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSite Survey: Initial3
08/14/2026S01141989-P1Open ↗
08/13/2026S01141989-I1Open ↗
08/13/2026S00928967-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone3
08/14/2026S01141989-P1Open ↗
08/13/2026S01141989-I1Open ↗
08/13/2026S00928967-I1Open ↗
▸DOB NOWStructure Photographs2
08/13/2026S00928948-P1Open ↗
08/13/2026S00928948-I1Open ↗
▸BISBPP: TOPOGRAPHIC SURVEY1
04/08/2025540265504Open ↗
▸BISBPP: PHOTOS-SIGNED/SEALED BY APPLICANT1
04/08/2025540265504Open ↗
▸BISPLOT DIAGRAM1
04/08/2025540265504Open ↗
▸DOB NOWFull Demo: 10-Day Notice1
08/13/2026S00928948-I1Open ↗
▸DOB NOWCommunity Board Notification1
08/13/2026S00928948-I1Open ↗