← Back
Elevator cooperative
789 WEST END AVENUE
MANHATTAN · Upper West Side-Manhattan Valley · BIN 1057083
💬 Discuss this project
1916Year Built
13Stories
D4Building Class
R8Zoning
106,704 sfGross Floor Area
65Units
LL97 CoveredRent Stabilized19 Open Violations ▸FISP: SAFE
Elevator cooperative · Owner of record: 789 OWNERS INC · 10,885 sf lot · 9.8 FAR built · Flood zone X
Locations of Work
ArchitectureElectricalMechanicalPlumbing
Permit Issued — active, not yet Signed-off
Floor 61p · 1 filing · 5 docs
Floor 51p · 1 filing · 11 docs
Floor 4
Floor 3
Floor 2Under Construction6p · 1 filing · 11 docs
Floor 11p · 1 filing · 11 docs
Cellar3p · 3 filings · 20 docs
Basement9p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
PLATINUM SERVICES NY707/08/2026
PEDROL CONTRACTING604/09/2026
789 OWNERS4203/22/2026
789 WERNER’S INC 789 WERNER’S INC103/22/2026
789 OWNER'S INC.503/21/2026
HOFFMAN MANAGEMENT603/21/2026
789 WEST END AVENUE103/21/2026
289 OWNERS303/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
AGOUTI CONSTRUCTION CONSULTING403/21/2026
HIERARCH-E203/21/2026
W J PROFESSIONAL EXPEDITING COMPANY203/21/2026
CODE603/21/2026
DOMANI CONSULTING603/21/2026
SYNCHRON EXPEDITING1003/21/2026
SANDEEP KAUR203/21/2026
GREEN STUDIO203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
PLATINUM SERVICES NY LLCGeneral Contractor407/08/2026
SNS ORGNIZATION LTDGeneral Contractor303/21/2026
LIEBHABER COMPANY INCGeneral Contractor307/08/2026
BEARD, JOIElectrical203/21/2026
CREO PROJECTS LLCGeneral Contractor207/01/2026
HI-TECH PLUMBING & HEATINGPlumbing207/08/2026
NEW YORK STANDARD MECH CORPPlumbing207/08/2026
LCS RESTORATION CORPGeneral Contractor207/08/2026
FABCON PRECAST LLCElectrical203/21/2026
ROMO CONSTRUCTION CORPGeneral Contractor204/09/2026
NY CONSTRUCTION&STONE INCGeneral Contractor107/08/2026
BROOK PLUMBING & HTG CORPPlumbing107/08/2026
DONATO PLUMBING, INCPlumbing107/08/2026
BASS ELECTRICAL CORP.Electrical103/22/2026
PROCORE MECHANICAL CORPPlumbing107/08/2026
FRANQUIZ, DAVIDElectrical103/21/2026
GRZEGORZ WIDELSKIElectrical103/21/2026
HARRISON, JOSEPHElectrical103/21/2026
HIRSCH, FElectrical103/21/2026
MATSIKAS VASILIOSElectrical103/21/2026
M. GANNESElectrical103/21/2026
RESCIGNO, JOSEPHElectrical103/21/2026
VASILIOS MATSIKASElectrical103/21/2026
BUCKMILLER AUTO.SPKLR.CORFire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AK ENGINEERING PC678111/05/2025
PONDOSA DESIGN INC.5126306/21/2023
GEIGER ENGINEERING. PC689106/21/2023
ALLEN+KILLCOYNE ARCHITECT2697210/17/2022
MJ ENGINEERING & DESIGN5546207/14/2022
BAZINI ENGINEERING, P.C.1808402/22/2022
ADAL ENGINEERING PLLC4205107/01/2020
Building Lifecycle
All (187)Filed (25)Permit Issued (26)Signed Off (11)Facade (FISP) (24)Violation (42)Inspection (10)Objection (21)Special Inspection (28)
06/29/2026
Permit issued — General Construction
M01225822-I1-GC
03/21/2026
Cycle 10 facade report submitted
03/21/2026
Cycle 10 facade report signed — SAFE
03/04/2026
Cycle 10 facade inspection completed
02/27/2026
Signed off — Alteration
INSTALLATION OF 300 PSF SIDEWALK SHED AS PER PLANS. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC CODE 2022. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M00830027-I1
02/24/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
01/26/2026
Permit issued — Plumbing
M01225822-S1-PL
01/20/2026
Permit issued — Sidewalk Shed
M00830027-I1-SH
01/14/2026
Permit issued — General Construction
M01225822-I1-GC
12/22/2025
Cycle 9 facade report signed — SAFE
12/04/2025
Objection resolved — Addressed
12/04/2025
Objection resolved — Addressed
12/04/2025
Objection resolved — Addressed
12/04/2025
Objection resolved — Addressed
12/04/2025
Objection resolved — Addressed
12/02/2025
Objection raised — Plumbing
12/02/2025
Objection raised — Plumbing
12/02/2025
Objection raised — Scope
12/02/2025
Objection raised — Energy
12/02/2025
Objection raised — Scope
12/01/2025
Cycle 9 facade report submitted
11/20/2025
Signed off — Alteration
FACADE REPAIRS FROM FLOORS 1-14 AS PER PLANS FILED HEREWITH. NO CHANGE IN EGRESS, USE OR OCCUPANCY.
M00865160-I1
11/20/2025
Cycle 9 facade inspection completed
11/05/2025
Filed — Alteration
Modification to existing plumbing system as per plans filed herewith. No change in use, egress or occupancy.
M01225822-S1
11/05/2025
Filed — Alteration
Modification to existing plumbing system as per plans filed herewith. No change in use, egress or occupancy.
M01225822-I1
07/07/2025
Permit issued — Suspended Scaffold
M00865160-S1-SC
06/30/2025
Cycle 9 facade report signed — UNSAFE
06/26/2025
Cycle 9 facade report submitted
06/20/2025
Cycle 9 facade inspection completed
06/12/2025
Special inspection requirement — Lighting in dwelling units
Ari Kamo
06/12/2025
Special inspection requirement — Energy Code Compliance Inspections
Ari Kamo
05/14/2025
Special inspection requirement — Final
ALLEGRA KOCHMAN
05/14/2025
Special inspection requirement — Fire-Resistance Rated Construction
Ari Kamo
05/14/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Ari Kamo
05/07/2025
Permit issued — General Construction
M00865160-I1-GC
01/28/2025
Permit issued — Sidewalk Shed
M00830027-I1-SH
12/21/2024
Cycle 9 facade report submitted
11/27/2024
Cycle 9 facade report signed — UNSAFE
11/25/2024
Cycle 9 facade inspection completed
08/29/2024
Permit issued — Suspended Scaffold
M00865160-S1-SC
08/28/2024
Filed — Alteration
FACADE REPAIRS FROM FLOORS 1-14 AS PER PLANS FILED HEREWITH. NO CHANGE IN EGRESS, USE OR OCCUPANCY.
M00865160-S1
08/22/2024
Signed off — Alteration
Herewith file plumbing plans, filed in conjunction with GC, MS, SP work types.
M00769231-I1
08/06/2024
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
08/06/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
07/18/2024
Filed — Alteration
Herewith file plumbing plans, filed in conjunction with GC, MS, SP work types.
M00769231-P1
06/21/2024
Signed off — Alteration
M00767791-I1
06/12/2024
Signed off — Alteration
Herewith file plans for a tenant accessory exercise room in the basement (per approved CCD1 #68325), work is general construction. MS,PL, SP filed under separate applications.
M00769245-I1
06/10/2024
Signed off — Alteration
Herewith file sprinkler plans, filed in conjunction with GC,MS and PL work.
M00769192-I1
05/22/2024
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
05/14/2024
Permit issued — General Construction
M00865160-I1-GC
03/22/2024
Objection raised — Other
03/12/2024
Filed — Alteration
Amending the Plans for facade work.
M00977512-P1
02/09/2024
Violation issued (ECB, closed)
Construction
02/09/2024
Violation issued (ECB, closed)
Construction
02/02/2024
Permit issued — General Construction
M00865160-I1-GC
01/29/2024
Permit issued — Sidewalk Shed
M00830027-I1-SH
12/21/2023
Filed — Alteration
Amending the Plans for facade work.
M00977512-I1
12/21/2023
Permit issued — Suspended Scaffold
M00977512-I1-SC
09/21/2023
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
09/21/2023
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
Latest 60 of 187 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedCREO PROJECTS LLC06/29/2026
DOB NOWPlumbingPermit IssuedPROCORE MECHANICAL CORP01/26/2026
DOB NOWSidewalk ShedSigned-offPLATINUM SERVICES NY LLC01/20/2026
DOB NOWGeneral ConstructionPermit IssuedCREO PROJECTS LLC01/14/2026
DOB NOWSuspended ScaffoldPermit IssuedPEDROL CONTRACTING INC07/07/2025
DOB NOWGeneral ConstructionSigned-offLCS RESTORATION CORP05/07/2025
DOB NOWSidewalk ShedSigned-offPLATINUM SERVICES NY LLC01/28/2025
DOB NOWSuspended ScaffoldPermit IssuedPEDROL CONTRACTING INC08/29/2024
DOB NOWGeneral ConstructionSigned-offLCS RESTORATION CORP05/14/2024
DOB NOWGeneral ConstructionSigned-offROMO CONSTRUCTION CORP02/02/2024
DOB NOWSidewalk ShedSigned-offPLATINUM SERVICES NY LLC01/29/2024
DOB NOWSuspended ScaffoldPermit IssuedSPD CONSTRUCTION CORP12/21/2023
DOB NOWGeneral ConstructionSigned-offROMO CONSTRUCTION CORP08/02/2023
DOB NOWSidewalk ShedSigned-offPLATINUM SERVICES NY LLC02/17/2023
DOB NOWPlumbingSigned-offDONATO PLUMBING, INC12/20/2022
DOB NOWSprinklersSigned-offBUCKMILLER AUTO.SPKLR.COR10/25/2022
DOB NOWMechanical SystemsSigned-offLIEBHABER COMPANY09/13/2022
DOB NOWGeneral ConstructionSigned-offLIEBHABER COMPANY08/23/2022
DOB NOWBoiler EquipmentSigned-offSTUART N SCHWARTZ12/27/2021
DOB NOWGeneral ConstructionSigned-offSNS ORGNIZATION LTD12/23/2021
DOB NOWPlumbingSigned-offNEW YORK STANDARD MECH CORP08/11/2021
DOB NOWPlumbingSigned-offNEW YORK STANDARD MECH CORP05/13/2021
DOB NOWMechanical SystemsSigned-offNY CONSTRUCTION&STONE INC04/16/2021
DOB NOWPlumbingSigned-offHI-TECH PLUMBING & HEATIN12/03/2020
DOB NOWPlumbingSigned-offBROOK PLUMBING & HTG CORP08/10/2020
DOB NOWPlumbingSigned-offHI-TECH PLUMBING & HEATIN03/03/2020
BISPLISSUEDFRED SMITH P&H CO INC04/22/2021
BISOTISSUEDSF CONSTRUCTION SVCS INC08/06/2020
BISOTISSUEDPAULO CONSTRUCTION LLC02/10/2020
BISOTISSUEDA. ROBESON PARTNERS, LLC04/05/2019
BISOTISSUEDA. ROBESON PARTNERS, LLC02/22/2019
BISPLISSUEDS & L PLUMBING INC11/20/2017
BISOTISSUEDKTC DESIGN GROUP INC10/12/2017
BISOTISSUEDHERITAGE CHIMNEY SERVICE08/04/2016
BISMHISSUEDSICULA RENOVATIONS,INC05/02/2016
BISOTISSUEDSICULA RENOVATIONS,INC05/02/2016
BISOTISSUEDSICULA RENOVATIONS,INC04/25/2016
BISMHISSUEDSICULA RENOVATIONS,INC04/25/2016
BISPLISSUEDDH EAGLE PLBG & HTG INC04/07/2016
BISOTISSUEDSICULA RENOVATIONS,INC04/01/2016
+ 36 more permits on file
1 project · most recent 11/05/2025
Water/Sanitary
FiledStatusContractorScope
11/05/2025Permit IssuedPROCORE MECHANICAL CORPWater/Sanitary
9 projects · most recent 11/12/2025
General Wiring
FiledStatusContractorScope
11/12/2025Permit IssuedPOWER SURGE ELECTRIC, INCGeneral Wiring
07/25/2025CompleteA TO Z NY ELECTRICAL CONT—
10/22/2024Permit IssuedHYLAN DATACOM & ELECL LLC1 meters, 1 new_meters
01/03/2024CompleteBASS ELECTRICAL CORP.General Wiring
11/06/2023CompleteJAS ELEC'L SERVICES, INCGeneral Wiring
02/15/2023CompleteILLUMINOUS ELECTRIC CORP.General Wiring
10/03/2022CompleteLINA ELECTRIC, CORP—
03/10/2021CompletePRUDENT ELECTRIC INCGeneral Wiring
12/14/2017Permit IssuedKJK ELECTRIC INCGeneral Wiring
1 project · most recent 03/12/2024
Suspended Scaffold (SC)
FiledStatusContractorScope
03/12/2024Permit Issued—Suspended Scaffold (SC)
▾Field Inspections (DOB CAP) — 10
DateTypeResultReport
02/24/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
08/06/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
08/06/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
05/22/2024Pass-Final General Construction Non-Directive 14PassView ↗
09/21/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
09/21/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
09/20/2023Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
05/25/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/31/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/31/2022Pass-Final Boiler Equipment InspectionPassView ↗
▾Special Inspection Requirements (DOB NOW) — 28
DateRequirementInspectorRole
06/12/2025Lighting in dwelling unitsAri Kamoenergy_progress
06/12/2025Energy Code Compliance InspectionsAri Kamoprogress
05/14/2025FinalALLEGRA KOCHMANprogress
05/14/2025Fire-Resistance Rated ConstructionAri Kamoprogress
05/14/2025Fire-Resistant Penetrations and JointsAri Kamospecial
04/25/2023FinalFADY HABEELprogress
04/25/2023Structural Stability – Alterations of existing buildingsFADY HABEELspecial
04/25/2023Tenant Protection Plan ComplianceMANG WONGspecial
12/01/2022Fire-Resistance Rated ConstructionDaniel Allenprogress
12/01/2022Energy Code Compliance InspectionsDaniel Allenprogress
12/01/2022Lighting controlsDaniel Allenenergy_progress
12/01/2022Interior lighting powerDaniel Allenenergy_progress
12/01/2022Fenestration and door U-factor and product ratingsDaniel Allenenergy_progress
12/01/2022Post-installed AnchorsMANG WONGspecial
12/01/2022Fire-Resistant Penetrations and JointsDaniel Allenspecial
10/07/2022Fire-Resistance Rated ConstructionDaniel Allenprogress
10/07/2022Fenestration and door U-factor and product ratingsDaniel Allenenergy_progress
10/07/2022Lighting controlsDaniel Allenenergy_progress
10/07/2022Fire-Resistant Penetrations and JointsDaniel Allenspecial
10/07/2022Post-installed AnchorsMANG WONGspecial
10/07/2022Energy Code Compliance InspectionsDaniel Allenprogress
10/07/2022Interior lighting powerDaniel Allenenergy_progress
02/23/2022Fire-Resistance Rated ConstructionJoseph Baziniprogress
02/23/2022Fire-Resistant Penetrations and JointsJoseph Bazinispecial
02/23/2022FinalJoseph Baziniprogress
Latest 25 of 28.
▾Documents — 515 on file (BIS + DOB NOW)
▸Plans & Drawings25
▸DOB NOWPlans/Sketch17
09/02/2026M00590856-I1Request digital key ↗
09/02/2026M00590856-P1Request digital key ↗
09/02/2026M00590847-I1Request digital key ↗
Showing 3 of 17 on file for this type
▸DOB NOWPlans/Sketch - Plumbing7
09/04/2026M00299049-P1Request digital key ↗
09/04/2026M00299049-I1Request digital key ↗
09/03/2026M00358442-P2Request digital key ↗
Showing 3 of 7 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems1
08/15/2026M00359016-I1Request digital key ↗
▸Applications & Permits94
▸BISWORK PERMIT APPLICATION42
05/05/2021140911440Open ↗
04/22/2021120277645Open ↗
08/06/2020140911440Open ↗
Showing 3 of 42 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION33
06/28/2021120277645Open ↗
06/22/2021120277645Open ↗
06/18/2021120277645Open ↗
Showing 3 of 33 on file for this type
▸DOB NOWLPC Approval/Permit18
09/02/2026M00590856-I1Open ↗
09/02/2026M00769231-I1Open ↗
09/02/2026M00769231-P1Open ↗
Showing 3 of 18 on file for this type
▸BISNon-Directive 14 Construction Sign Off Including Sign Applications1
06/17/2020123490294Open ↗
▸Seals & Professional Certifications116
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION48
01/24/2020123700557Open ↗
01/24/2020123700557Open ↗
02/21/2019123490294Open ↗
Showing 3 of 48 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature23
09/04/2026M00359016-I1Open ↗
09/04/2026M00299049-P2Open ↗
09/04/2026M00299049-P1Open ↗
Showing 3 of 23 on file for this type
▸DOB NOWProgress Inspector Seal & Signature17
09/01/2026M00590856-I1Open ↗
09/01/2026M00590856-I1Open ↗
08/29/2026M01225822-I1Open ↗
Showing 3 of 17 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature10
09/01/2026M00590856-I1Open ↗
08/29/2026M01225822-I1Open ↗
08/29/2026M00769245-I1Open ↗
Showing 3 of 10 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT4
10/11/2017140698564Open ↗
08/03/2016140529989Open ↗
02/22/2016140459554Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY4
06/22/2020140911440Open ↗
10/11/2017140698564Open ↗
08/03/2016140529989Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION3
10/11/2017140698564Open ↗
08/03/2016140529989Open ↗
02/22/2016140459554Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISApplicant / Owner Signature2
06/22/2020140911440Open ↗
Showing 1 of 2 on file for this type
▸Trade Schedules & Equipment42
▸BISSELF-CERT PLUMBING NOTICE19
10/17/2014140168823Open ↗
07/14/2014140168823Open ↗
Showing 2 of 19 on file for this type
▸BISSCHEDULE B - PLUMBING14
06/28/2021120277645Open ↗
10/11/2017140698564Open ↗
02/22/2016140459554Open ↗
Showing 3 of 14 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT3
05/09/2017122673393Open ↗
05/08/2017122673393Open ↗
Showing 2 of 3 on file for this type
▸BISEQUIPMENT USE PERMITS3
05/09/2017122673393Open ↗
05/08/2017122673393Open ↗
Showing 2 of 3 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE2
12/03/2018123490294Open ↗
02/03/2016122673393Open ↗
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT1
02/22/2016140459554Open ↗
▸Safety & Tenant Protection15
▸DOB NOWTenant Protection Plan8
08/15/2026M00359016-I1Open ↗
08/13/2026M00299049-P1Open ↗
08/13/2026M00299049-I1Open ↗
Showing 3 of 8 on file for this type
▸BISTENANT PROTECTION PLAN AND NOTES6
04/14/2021120277645Open ↗
06/22/2020140911440Open ↗
08/03/2016140529989Open ↗
Showing 3 of 6 on file for this type
▸BISSTREET TREE CHECKLIST1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Environmental & Asbestos42
▸DOB NOWDEP ACP-5: Asbestos Assessment Report21
09/04/2026M00299049-P2Open ↗
09/04/2026M00299049-P1Open ↗
09/04/2026M00299049-I1Open ↗
Showing 3 of 21 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)10
06/22/2020140911440Open ↗
01/24/2020123700557Open ↗
12/03/2018123490294Open ↗
Showing 3 of 10 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Energy Compliance49
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS21
01/24/2020123700557Open ↗
02/12/2019123490294Open ↗
09/19/2018140698564Open ↗
Showing 3 of 21 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS11
10/21/2021140911440Open ↗
01/26/2021123700557Open ↗
06/17/2020123490294Open ↗
Showing 3 of 11 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY7
10/21/2021140911440Open ↗
01/26/2021123700557Open ↗
06/22/2020140911440Open ↗
Showing 3 of 7 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS4
06/22/2020140911440Open ↗
10/11/2017140698564Open ↗
08/03/2016140529989Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWEN2: As Built Energy Analysis3
08/13/2026M00769245-I1Open ↗
08/13/2026M00767791-I1Open ↗
08/13/2026M00590847-I1Open ↗
▸BISTR8: Energy Code Progress Inspections2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISTECHNICAL REPORT: ENERGY1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Inspections & Test Reports9
▸BISTECHNICAL REPORT: RESPONSIBILITY8
10/21/2021140911440Open ↗
01/26/2021123700557Open ↗
01/26/2021123700557Open ↗
Showing 3 of 8 on file for this type
▸BISINSPECTION REPORT - SUPPORTING DOCUMENTATION1
09/19/2018140698564Open ↗
▸Approvals, Objections & Sign-offs45
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST18
10/21/2021140911440Open ↗
08/16/2021120277645Open ↗
01/26/2021123700557Open ↗
Showing 3 of 18 on file for this type
▸BISLANDMARKS APPROVAL11
10/21/2021140911440Open ↗
02/05/2020123700557Open ↗
02/12/2019123490294Open ↗
Showing 3 of 11 on file for this type
▸BISADMINISTRATIVE OBJECTIONS8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION4
01/25/2019123490294Open ↗
04/18/2017140529989Open ↗
Showing 2 of 4 on file for this type
▸BISLANDMARKS SIGNOFF3
01/26/2021123700557Open ↗
06/17/2020123490294Open ↗
09/19/2018140698564Open ↗
▸BISSUPERSEDING LETTER1
04/22/2021120277645Open ↗
▸Cost, Insurance & Ownership35
▸BISCOST AFFIDAVIT34
10/21/2021140911440Open ↗
01/26/2021123700557Open ↗
06/22/2020140911440Open ↗
Showing 3 of 34 on file for this type
▸BISHIC LICENSE OR AFFIDAVIT1
04/12/2016122673393Open ↗
▸Filing & Intake Forms30
▸BISEFILING COVER SHEET13
01/24/2020123700557Open ↗
12/03/2018123490294Open ↗
02/03/2016122673393Open ↗
Showing 3 of 13 on file for this type
▸BISADDITIONAL INFORMATION8
07/27/2021120277645Open ↗
07/13/2021120277645Open ↗
08/03/2020140911440Open ↗
Showing 3 of 8 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET6
06/22/2020140911440Open ↗
10/11/2017140698564Open ↗
08/03/2016140529989Open ↗
Showing 3 of 6 on file for this type
▸BISBOROUGH INTAKE FORM3
04/22/2021120277645Open ↗
09/19/2018140698564Open ↗
10/25/2017140698564Open ↗
▸Other Documents13
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION3
04/12/2017140459554Open ↗
Showing 1 of 3 on file for this type
▸DOB NOWCalculations3
08/13/2026M00865160-S1Open ↗
08/13/2026M00977512-I1Open ↗
08/13/2026M00977512-P1Open ↗
▸DOB NOWDHCR Document3
08/13/2026M00358442-I1Open ↗
08/13/2026M00299049-I1Open ↗
08/13/2026M00358442-P2Open ↗
▸DOB NOWManufacturer's Specifications3
08/13/2026M00865160-S1Open ↗
08/13/2026M00977512-I1Open ↗
08/13/2026M00977512-P1Open ↗
▸BISDepartment of Consumer Affairs (DCA) Form1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type