← Back
BuildNYC
Public elementary, junior or senior high
Achievement First Crown Heights Charter School
790 EAST NEW YORK AVENUE · BIN 3107129
💬 Discuss this project
1975Year Built
2Stories
W1Building Class
R6Zoning
120,520 sfGross Floor Area
1Units
LL97 Covered7 Active Violations 0 unresolved · 7 paperwork only 7 likely answered ▸FDNY Report ↗
Public elementary, junior or senior high · Owner of record: NYC Department of Education · 86,655 sf lot · 1.39 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalEquipmentGeneralOther
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofChiller, condensing unit, and piping replacementUnder Construction14p · 1 filing · 20 docs
Floor 2Chiller, condensing unit, and piping replacementUnder Construction14p · 1 filing · 20 docs
Floor 1Chiller, condensing unit, and piping replacementUnder Construction14p · 1 filing · 20 docs
CellarChiller, condensing unit, and piping replacementUnder Construction10p · 1 filing · 20 docs
BasementChiller, condensing unit, and piping replacementUnder Construction1p · 1 filing · 20 docs
Site & exteriorTemporary mobile chiller trailer installationUnder Construction22p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYC School Construction Authority5909/13/2026
NYC Department of Education503/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Systra206/22/2026
Princeton404/15/2025
NYMS Consulting402/26/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ACS System AssociatesGeneral Contractor807/17/2026
ACS System AssociatesScaffold809/09/2026
Charan Electrical Enterp'sElectrical203/22/2026
A & S ElectricElectrical203/22/2026
Gemini Electric CoElectrical103/22/2026
A & S ElectricElectrical103/21/2026
E.N.E.L. ElectricalElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Twin Peaks317806/22/2026
Building Lifecycle
All (128)Filed (10)Permit Issued (14)Violation (60)Objection (14)Special Inspection (30)
09/08/2026
Permit issued — Sidewalk Shed
B01142259-S1-SH
07/16/2026
Permit issued — General Construction
B00967664-S2-GC-CX
07/01/2026
Special inspection requirement — Structural Steel - Welding
MIKHAIL ZEYGMAN
07/01/2026
Special inspection requirement — Final
MIKHAIL ZEYGMAN
07/01/2026
Special inspection requirement — Structural Steel - High Strength Bolting
MIKHAIL ZEYGMAN
07/01/2026
Special inspection requirement — Sprayed fire-resistant materials
MIKHAIL ZEYGMAN
07/01/2026
Special inspection requirement — Structural Steel - Details
MIKHAIL ZEYGMAN
07/01/2026
Special inspection requirement — Post-installed Anchors
MIKHAIL ZEYGMAN
07/01/2026
Special inspection requirement — Concrete - Cast-In-Place
MIKHAIL ZEYGMAN
06/25/2026
Violation issued (ECB, closed)
Construction
06/25/2026
Violation issued (ECB, open)
Construction
06/25/2026
Violation issued (ECB, closed)
Construction
06/25/2026
Violation issued (ECB, open)
Construction
06/22/2026
Filed — Alteration
Replace existing (1) chiller and (1) condensing unit and associated equipment with (1) new Heat Pump Chiller/Heater and associated new equipment. Replace associated chilled water piping with new dual water piping. Provide new Split AC and condensing unit.
B00967664-P2
06/22/2026
Special inspection requirement — Concrete - Cast-In-Place
MIKHAIL ZEYGMAN
06/22/2026
Special inspection requirement — Final
MIKHAIL ZEYGMAN
06/22/2026
Special inspection requirement — Structural Steel - Welding
MIKHAIL ZEYGMAN
06/22/2026
Special inspection requirement — Structural Steel - High Strength Bolting
MIKHAIL ZEYGMAN
06/22/2026
Special inspection requirement — Structural Steel - Details
MIKHAIL ZEYGMAN
06/22/2026
Special inspection requirement — Sprayed fire-resistant materials
MIKHAIL ZEYGMAN
06/22/2026
Special inspection requirement — Post-installed Anchors
MIKHAIL ZEYGMAN
06/02/2026
Permit issued — Sidewalk Shed
B01142259-S1-SH
04/23/2026
Permit issued — Mechanical Systems
B01142259-S3-MS
04/23/2026
Permit issued — Supported Scaffold
B01142259-S2-SF
04/22/2026
Permit issued — General Construction
B00967664-S1-GC
04/22/2026
Permit issued — Construction Fence
B01142259-I1-FN
04/22/2026
Permit issued — Mechanical Systems
B00967664-I1-MS
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
08/20/2025
Permit issued — General Construction
B00967664-S1-GC
08/20/2025
Permit issued — Mechanical Systems
B00967664-I1-MS
06/05/2025
Violation issued (ECB, open)
Construction
06/05/2025
Violation issued (ECB, open)
Construction
05/09/2025
Objection resolved — Addressed
05/09/2025
Special inspection requirement — HVAC-R and service water heating system controls
MIKHAIL ZEYGMAN
05/09/2025
Special inspection requirement — Mechanical Systems
MIKHAIL ZEYGMAN
05/09/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
MIKHAIL ZEYGMAN
05/09/2025
Special inspection requirement — Post-installed Anchors
MIKHAIL ZEYGMAN
05/09/2025
Special inspection requirement — Energy Code Compliance Inspections
MIKHAIL ZEYGMAN
05/09/2025
Special inspection requirement — Final
MIKHAIL ZEYGMAN
05/09/2025
Special inspection requirement — Lighting controls
MIKHAIL ZEYGMAN
05/09/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
MIKHAIL ZEYGMAN
05/09/2025
Special inspection requirement — HVAC-R and service water heating equipment
MIKHAIL ZEYGMAN
05/09/2025
Special inspection requirement — Maintenance information
MIKHAIL ZEYGMAN
05/09/2025
Special inspection requirement — Interior lighting power
MIKHAIL ZEYGMAN
05/05/2025
Permit issued — Sidewalk Shed
B01142259-S1-SH
05/02/2025
Violation issued (FDNY_NOV, closed)
04/22/2025
Objection raised — Other
04/15/2025
Filed — Alteration
Replace existing (1) chiller and (1) condensing unit and associated equipment with (1) new Heat Pump Chiller/Heater and associated new equipment. Replace associated chilled water piping with new dual water piping. Provide new Split AC and condensing unit.
B00967664-P1
04/14/2025
Special inspection requirement — HVAC-R and service water heating system controls
MIKHAIL ZEYGMAN
04/14/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
MIKHAIL ZEYGMAN
04/14/2025
Special inspection requirement — Mechanical Systems
MIKHAIL ZEYGMAN
04/14/2025
Special inspection requirement — Post-installed Anchors
MIKHAIL ZEYGMAN
04/14/2025
Special inspection requirement — Energy Code Compliance Inspections
MIKHAIL ZEYGMAN
04/03/2025
Permit issued — Construction Fence
B01142259-I1-FN
04/02/2025
Permit issued — Supported Scaffold
B01142259-S2-SF
04/01/2025
Permit issued — Mechanical Systems
B01142259-S3-MS
03/28/2025
Objection resolved — Addressed
03/26/2025
Objection resolved — Addressed
Latest 60 of 128 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSidewalk ShedPermit IssuedACS System Associates09/08/2026
DOB NOWGeneral ConstructionPermit IssuedACS System Associates07/16/2026
DOB NOWSidewalk ShedPermit IssuedACS System Associates06/02/2026
DOB NOWMechanical SystemsPermit IssuedACS System Associates04/23/2026
DOB NOWSupported ScaffoldPermit IssuedACS System Associates04/23/2026
DOB NOWGeneral ConstructionPermit IssuedACS System Associates04/22/2026
DOB NOWConstruction FencePermit IssuedACS System Associates04/22/2026
DOB NOWMechanical SystemsPermit IssuedACS System Associates04/22/2026
DOB NOWGeneral ConstructionPermit IssuedACS System Associates08/20/2025
DOB NOWMechanical SystemsPermit IssuedACS System Associates08/20/2025
DOB NOWSidewalk ShedPermit IssuedACS System Associates05/05/2025
DOB NOWConstruction FencePermit IssuedACS System Associates04/03/2025
DOB NOWSupported ScaffoldPermit IssuedACS System Associates04/02/2025
DOB NOWMechanical SystemsPermit IssuedACS System Associates04/01/2025
BISOTISSUEDFritch Construction Co03/26/2013
BISOTISSUEDFritch Construction Co01/02/2013
BISMHISSUEDTomco Mechanical05/27/2011
BISOTISSUEDKomi Construction03/29/2010
BISEQISSUEDNYC Construction Service08/03/2009
BISEQISSUEDNYC Construction Service08/03/2009
BISEQISSUEDKomi Construction07/02/2009
BISOTISSUEDKomi Construction03/23/2009
BISEQISSUEDKomi Construction03/19/2009
BISEQISSUEDNYC Construction Service03/18/2009
BISEQISSUEDNYC Construction Service03/12/2009
BISOTISSUEDFritch Construction Co08/25/2006
BISPLISSUEDForsythe P&H01/20/2006
BISFPISSUEDFiremasters01/13/2006
BISEQISSUEDScaffolding One12/21/2005
BISOTISSUEDEco-Contractors08/01/2005
BISOTISSUEDEmb Contracting04/19/2005
BISEQISSUEDScaffolding One04/13/2005
BISEQISSUEDEmb Contracting04/08/2005
BISEQISSUEDScaffolding One04/01/2005
BISOTISSUEDSci07/23/2004
BISOTISSUEDLiberty Architectural Products04/22/2004
BISOTISSUEDImperial Developement and09/16/2002
BISPLISSUEDFranco Belli Plumbing & Heating07/27/2000
BISOTISSUEDImperial Developement and07/27/2000
2 projects · most recent 06/22/2026
Refrigeration Systems Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
06/22/2026Permit IssuedACS System AssociatesHeating and Air Conditioning Systems, Refrigeration Systems
Heat / Cool
Trane AXM030 239 tons · Chiller ×2
Refrigeration
Mitsubishi Electric PKA-AL12NL 12,000 BTU · Split System ×2
PUY-AK12NL 12,000 BTU · Condensing Unit ×2
02/26/2025Permit IssuedACS System AssociatesRefrigeration Systems
Refrigeration
Trane 120 ton Air-Cooled CGAM - Mode # CSCA0120 120 tons · Chiller ×1
16 projects · most recent 04/29/2025
General Wiring
FiledStatusContractorScope
04/29/2025Permit IssuedAujla Electric—
01/21/2025Permit IssuedHexagon Construction & Electrical GroupGeneral Wiring
01/21/2025Permit IssuedHexagon Construction & Electrical GroupGeneral Wiring
10/11/2023Permit IssuedAce Electrical ConstructionGeneral Wiring
03/20/2023CompleteGemini Electric Co—
12/23/2022CompleteCharan Electrical Enterp's—
12/23/2022CompleteCharan Electrical Enterp'sGeneral Wiring
08/19/2021CompleteCharan Electrical Enterp's—
05/07/2021Permit IssuedA & S ElectricGeneral Wiring
04/04/2020Permit IssuedA & S ElectricGeneral Wiring
06/20/2019CompleteCharan Electrical Enterp's—
04/09/2019CompleteCharan Electrical Enterp'sGeneral Wiring
10/04/2018CompleteCharan Electrical Enterp's—
05/14/2018CompleteCharan Electrical Enterp's—
05/10/2018CompletePrince Electric—
1 project · most recent 06/22/2026
Steel Concrete
FiledStatusContractorScope
06/22/2026Permit IssuedACS System AssociatesSteel, Concrete
1 project · most recent 02/26/2025
Fence Scaffold Sidewalk Shed
FiledStatusContractorScope
02/26/2025Permit IssuedACS System AssociatesFence, Scaffold, Sidewalk Shed
▾Special Inspection Requirements (DOB NOW) — 52
DateRequirementInspectorRole
07/01/2026Structural Steel - WeldingMIKHAIL ZEYGMANspecial
07/01/2026FinalMIKHAIL ZEYGMANprogress
07/01/2026Structural Steel - High Strength BoltingMIKHAIL ZEYGMANspecial
07/01/2026Sprayed fire-resistant materialsMIKHAIL ZEYGMANspecial
07/01/2026Structural Steel - DetailsMIKHAIL ZEYGMANspecial
07/01/2026Post-installed AnchorsMIKHAIL ZEYGMANspecial
07/01/2026Concrete - Cast-In-PlaceMIKHAIL ZEYGMANspecial
06/22/2026Concrete - Cast-In-PlaceMIKHAIL ZEYGMANspecial
06/22/2026FinalMIKHAIL ZEYGMANprogress
06/22/2026Structural Steel - WeldingMIKHAIL ZEYGMANspecial
06/22/2026Structural Steel - High Strength BoltingMIKHAIL ZEYGMANspecial
06/22/2026Structural Steel - DetailsMIKHAIL ZEYGMANspecial
06/22/2026Sprayed fire-resistant materialsMIKHAIL ZEYGMANspecial
06/22/2026Post-installed AnchorsMIKHAIL ZEYGMANspecial
05/09/2025HVAC-R and service water heating system controlsMIKHAIL ZEYGMANenergy_progress
05/09/2025Mechanical SystemsMIKHAIL ZEYGMANspecial
05/09/2025Fire-Resistant Penetrations and JointsMIKHAIL ZEYGMANspecial
05/09/2025Post-installed AnchorsMIKHAIL ZEYGMANspecial
05/09/2025Energy Code Compliance InspectionsMIKHAIL ZEYGMANprogress
05/09/2025FinalMIKHAIL ZEYGMANprogress
05/09/2025Lighting controlsMIKHAIL ZEYGMANenergy_progress
05/09/2025HVAC-R and service water piping design and insulationMIKHAIL ZEYGMANenergy_progress
05/09/2025HVAC-R and service water heating equipmentMIKHAIL ZEYGMANenergy_progress
05/09/2025Maintenance informationMIKHAIL ZEYGMANenergy_progress
05/09/2025Interior lighting powerMIKHAIL ZEYGMANenergy_progress
Latest 25 of 52.
▾Documents — 109 on file (BIS + DOB NOW)
▸Plans & Drawings10
▸DOB NOWPlans/Sketch10
08/22/2026B01142259-S3Request digital key ↗
08/22/2026B01142259-S2Request digital key ↗
08/22/2026B01142259-S1Request digital key ↗
Showing 3 of 10 on file for this type
▸Seals & Professional Certifications62
▸DOB NOWProgress Inspector Seal & Signature29
09/23/2026B00967664-S1Open ↗
09/23/2026B00967664-S1Open ↗
09/01/2026B01142259-S3Open ↗
Showing 3 of 29 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature23
09/23/2026B00967664-S1Open ↗
09/23/2026B00967664-S1Open ↗
09/01/2026B01142259-S3Open ↗
Showing 3 of 23 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature10
08/22/2026B01142259-S3Open ↗
08/22/2026B01142259-S2Open ↗
08/22/2026B01142259-S1Open ↗
Showing 3 of 10 on file for this type
▸Safety & Tenant Protection3
▸DOB NOWNYCSCA - Approved Site Safety Plans3
08/13/2026B01142259-S2Open ↗
08/13/2026B01142259-I1Open ↗
08/13/2026B01142259-S1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/22/2026B01142259-S3Open ↗
▸Approvals, Objections & Sign-offs23
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter10
08/21/2026B00967664-P2Open ↗
08/13/2026B00967664-S3Open ↗
08/13/2026B01142259-S1Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)10
08/21/2026B00967664-P2Open ↗
08/13/2026B01142259-S3Open ↗
08/13/2026B01142259-I1Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWDEP Variance (V5) letter3
08/13/2026B00967664-S1Open ↗
08/13/2026B00967664-S2Open ↗
08/13/2026B00967664-I1Open ↗
▸Other Documents10
▸DOB NOWNYCSCA - BCC Plan Examination Transmittal10
08/21/2026B00967664-P2Open ↗
08/13/2026B01142259-S2Open ↗
08/13/2026B00967664-P1Open ↗
Showing 3 of 10 on file for this type