💬 Discuss this project
1931Year Built
8Stories
T2Building Class
M2-1Zoning
5,359,400 sfGross Floor Area
6Units
LL97 Covered85 Active Violations 1 unresolved · 84 paperwork only ▸FDNY Report ↗
Pier, dock, bulkhead · Owner of record: NYC Department of Small Business Services · 2,573,197 sf lot · 2.08 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
Floor 6NYWD5p · 1 filing · 6 docs
Floor 5
Floor 4Studio STL, Unit 4037p · 3 filings · 15 docs
Floor 3NYC Economic Development CORP4p · 1 filing · 17 docs
Floor 2Unit 20228p · 9 filings · 16 docs
Floor 1Momo Test Kitchen26p · 12 filings · 16 docs
CellarNYC Economic Development CORP5p · 1 filing · 17 docs
Site & exteriorHugel X AlessoUnder Construction7p · 5 filings · 7 docs
Filed — no permit issuedNyc-edc20p · 3 filings · 9 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYC Economic Development12909/07/2026
Nycedc1503/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Just Architecture1903/21/2026
ADG Architecture Design403/21/2026
Stracar Engineering P603/21/2026
KM Associates of New York803/21/2026
BKH Architect403/21/2026
Peter Shinoda103/21/2026
Jenny Flores Expediting103/21/2026
K & M Associates803/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CGW ConstructionGeneral Contractor707/08/2026
Macaluso General ContGeneral Contractor707/08/2026
NYFF EventsGeneral Contractor509/07/2026
Dynamic Plumbing & SprinklerPlumbing307/08/2026
Cooltech Mechanicalspecialty_contractor303/21/2026
Elbrus Air Conditioning *specialty_contractor203/21/2026
Economy P & H CoPlumbing107/08/2026
Franco Belli PLMG & Heating SonPlumbing107/08/2026
F.S. SiteFire Protection107/08/2026
Inara ElectricElectrical103/21/2026
F.S. SitePlumbing107/08/2026
Blue Seagull ElectricalElectrical103/22/2026
Ohm's ElectricalElectrical103/21/2026
Axea Construction GroupGeneral Contractor107/08/2026
Inara ElectricGeneral Contractor103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Becker Engineering633207/06/2022
Doyun Kim; RA7415407/06/2022
Hansen Engineering8174404/25/2022
BKH Architect6255311/09/2021
Steel Core Engineering PL1098110/18/2021
Stracar Special Inspectio229306/28/2021
Building Lifecycle
All (150)Filed (41)Permit Issued (17)Signed Off (6)Violation (8)Inspection (8)Objection (40)Special Inspection (30)
08/18/2026
Permit issued — General Construction
B01444134-I1-GC
08/11/2026
Filed — No Work
B01444135-I1
08/11/2026
Filed — Alteration
Temporary Installations to be used on a temporary event " Hugel X Alesso". All the Installation are to be removed upon completion of the event.
B01444134-I1
08/11/2026
Special inspection requirement — Final
Christopher Carrano
08/03/2026
Objection raised — Other
08/03/2026
Objection raised — Other
07/28/2026
Filed — Alteration
interior grading work for FEMA wet flood proofing.
B01344096-I1
07/24/2026
Permit issued — General Construction
B01431906-I1-GC
07/20/2026
Filed — Alteration
Temporary Installations to be used on a temporary event " Sammy Virji-2026 Tour Part I". All the Installations are to be removed upon completion of the event.
B01431906-I1
07/20/2026
Filed — No Work
B01431907-I1
07/16/2026
Special inspection requirement — Final
Christopher Carrano
03/16/2026
Objection resolved — Addressed
03/16/2026
Objection resolved — Addressed
03/16/2026
Objection resolved — Addressed
02/06/2026
Special inspection requirement — Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)
01/28/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
01/27/2026
Objection resolved — Addressed
01/08/2026
Special inspection requirement — Final
01/08/2026
Special inspection requirement — Footing and Foundation
12/16/2025
Objection raised — Other
12/16/2025
Objection raised — Other
12/10/2025
Objection raised — Scope
12/10/2025
Objection raised — Other
12/10/2025
Objection raised — Scope
12/10/2025
Objection raised — Structural
11/20/2025
Filed — Alteration
STRUCTURAL SCOPE FOR PROVIDING 1 NEW SAW-CUT WALL OPENING TO FACILITATE THE INSTALLATION OF AN INSULATED FLOOD VENT TO COMPLY WITH THE WET FLOOD PROOFING REQUIREMENTS OF APPENDIX G. THE INSTALLATION OF THEFLOOD VENT IS COVERED IN THE ARCHITECTURAL SCOPE.
B01290319-I1
11/20/2025
Filed — Alteration
WET FLOOD PROOFING OF BROOKLYN ARMY TERMINAL ANNEX BUILDING. INSTALLATION OF INSULATED FLOOD VENTS, REPLACEMENT OF EXISTING PARTITIONS WITH FEMA-COMPLIANT WALL TYPE, AND INSTALLATION OF "IN CASE OF FLOODING" SIGNAGE AT ELEVATORS ON EVERY LEVEL.
B01290311-I1
11/17/2025
Special inspection requirement — Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)
11/07/2025
Special inspection requirement — Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)
11/07/2025
Special inspection requirement — Final
11/07/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
11/07/2025
Special inspection requirement — Fire-Resistance Rated Construction
09/19/2025
Special inspection requirement — Final
09/14/2025
Violation issued (FDNY_ORDER, closed)
06/03/2025
Signed off — Alteration
B00311539-I1
02/27/2025
Signed off — Alteration
HEREBY FILING FOR INTERIOR FITOUT FOR UNIT #403. NO CHANGE TO OCCUPANCY, USE, NOR EGRESS.
B01096294-I1
11/12/2024
Permit issued — General Construction
B01096294-I1-GC
10/21/2024
Filed — Alteration
HEREBY FILING FOR INTERIOR FITOUT FOR UNIT #403. NO CHANGE TO OCCUPANCY, USE, NOR EGRESS.
B01096294-I1
10/03/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
05/10/2024
Objection resolved — Resolved
05/09/2024
Objection raised — Scope
05/08/2024
Filed — No Work
B01040041-I1
10/05/2022
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
09/21/2022
Permit issued — Plumbing
B00311539-I1-PL
08/09/2022
Signed off — Alteration
NEW VRV HEAT PUMP SYSTEM. NO CHANGE IN USE, OCCUPANCY OR EGRESS
B00554917-I1
07/22/2022
Objection resolved — Resolved
07/21/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
07/15/2022
Objection raised — Other
07/15/2022
Objection raised — Other
07/15/2022
Objection raised — Fire_Protection
07/13/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
DOYUN KIM
07/13/2022
Special inspection requirement — HVAC-R and service water heating equipment
DOYUN KIM
07/13/2022
Special inspection requirement — HVAC-R and service water heating system controls
DOYUN KIM
07/13/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
DOYUN KIM
07/13/2022
Special inspection requirement — Energy Code Compliance Inspections
DOYUN KIM
07/06/2022
Filed — Alteration
Mechanical work for mechanical distribution to demised commercial tenant space at 002.
B00483194-P1
07/06/2022
Filed — Alteration
Plumbing work to install 1 sink and 1 electric hot water heater with related piping at second floor unit 202,
B00479939-P1
06/01/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
04/26/2022
Special inspection requirement — HVAC-R and service water heating system controls
Ryan Hansen
04/26/2022
Special inspection requirement — HVAC-R and service water heating equipment
Ryan Hansen
Latest 60 of 150 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedNYFF Events08/18/2026
DOB NOWGeneral ConstructionPermit IssuedNYFF Events07/24/2026
DOB NOWGeneral ConstructionSigned-offAxea Construction Group11/12/2024
DOB NOWPlumbingSigned-offCitywide Plumbing & Heating & SPKLS09/21/2022
DOB NOWMechanical SystemsPermit IssuedMacaluso General Cont01/10/2022
DOB NOWSprinklersPermit IssuedAlan J. Brutosky Plumbing Con11/05/2021
DOB NOWMechanical SystemsSigned-offCooltech Mechanical11/04/2021
DOB NOWGeneral ConstructionPermit IssuedMacaluso General Cont10/20/2021
DOB NOWMechanical SystemsSigned-offElbrus Air Conditioning *10/07/2021
DOB NOWPlumbingSigned-offFranco Belli PLMG & Heating Son08/19/2021
DOB NOWGeneral ConstructionSigned-offNYFF Events08/12/2021
DOB NOWMechanical SystemsPermit IssuedCGW Construction08/07/2021
DOB NOWGeneral ConstructionPermit IssuedCGW Construction08/06/2021
DOB NOWPlumbingSigned-offAlan J Brutosky PLBR Cont07/28/2021
DOB NOWGeneral ConstructionPermit IssuedMacaluso General Cont07/23/2021
DOB NOWMechanical SystemsPermit IssuedCGW Construction06/04/2021
DOB NOWPlumbingPermit IssuedEconomy P & H Co03/27/2020
BISOTISSUEDUnique Construction Concepts08/18/2021
BIS—ISSUEDGirandola & Shutkind Cons06/19/2020
BISOTISSUEDGirandola & Shutkind Cons10/04/2019
BISOTISSUEDGirandola & Shutkind Cons05/08/2019
BISMHISSUEDHD HVAC of NY04/11/2019
BISPLISSUEDEconomy P & H Co01/08/2019
BISSPISSUEDVip Fire Sprinkler11/13/2018
BISMHISSUEDHD HVAC of NY10/30/2018
BIS—ISSUEDHunter Roberts Construction10/04/2018
BISPLISSUEDEconomy P & H Co09/13/2018
BISOTISSUEDHunter Roberts Construction02/15/2018
BISOTISSUEDHunter Roberts Construction02/15/2018
BISOTISSUEDHunter Roberts Construction02/15/2018
BISOTISSUEDSpencer Contracting02/05/2018
BISPLISSUEDEconomy P & H Co09/11/2017
BISSDISSUEDLouis L.buttermark & Sons08/26/2015
BISEQISSUEDBrickens Construction07/29/2015
BISSDISSUEDLouis L.buttermark & Sons06/08/2015
BISPLISSUEDLouis L.buttermark & Sons03/31/2015
BIS—ISSUEDHunter Roberts Construction03/27/2015
BIS—ISSUEDHunter Roberts Construction03/16/2015
BISOTISSUEDEts Contracting09/15/2014
BISEQISSUEDEts Contracting09/12/2014
1 project · most recent 03/22/2022
FiledStatusContractorScope
03/22/2022——9 heads
2 projects · most recent 07/06/2022
Water/Sanitary
FiledStatusContractorScope
07/06/2022——Water/Sanitary
04/25/2022Signed-offF.S. SiteWater/Sanitary
20 projects · most recent 10/08/2026
General Wiring Lighting
FiledStatusContractorScope
10/08/2026Permit IssuedDemand Electric—
06/17/2026CompleteAxcel Electric Co—
06/12/2026CompleteMer Electric—
06/12/2026CompleteMer Electric—
06/10/2026CompleteAxcel Electric Co—
08/20/2025CompleteJason Salome Electrical Contg—
01/08/2025CompleteBlue Seagull ElectricalGeneral Wiring
04/22/2024CompleteOhm's ElectricalLighting
03/28/2023CompleteDeborah Bradley Conts & MGeneral Wiring
09/20/2021Permit IssuedMartin DorkinGeneral Wiring
09/08/2021CompleteI.P. ElectricGeneral Wiring
08/08/2021CompleteJason Salome Electrical Contg—
06/30/2021Permit IssuedDaven Electric—
11/13/2020CompleteInara ElectricGeneral Wiring
11/02/2020CompleteAntonio Ceriello ElectricGeneral Wiring
2 projects · most recent 07/28/2026
FiledStatusContractorScope
07/28/2026——2 scope_items
11/20/2025——2 scope_items
▾Field Inspections (DOB CAP) — 8
DateTypeResultReport
10/03/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
10/05/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
07/21/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
06/01/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/16/2021Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
11/29/2021Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
09/22/2021Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/16/2021Fail-Final PL - Up to 3 Requested FloorsFailView ↗
▾Special Inspection Requirements (DOB NOW) — 68
DateRequirementInspectorRole
08/11/2026FinalChristopher Carranoprogress
07/16/2026FinalChristopher Carranoprogress
02/06/2026Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)—special
01/28/2026Structural Stability – Alterations of existing buildings—special
01/08/2026Final—progress
01/08/2026Footing and Foundation—progress
11/17/2025Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)—special
11/07/2025Fire-Resistant Penetrations and Joints—special
11/07/2025Fire-Resistance Rated Construction—progress
11/07/2025Final—progress
11/07/2025Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)—special
09/19/2025Final—progress
07/13/2022HVAC-R and service water piping design and insulationDOYUN KIMenergy_progress
07/13/2022Fire-Resistant Penetrations and JointsDOYUN KIMspecial
07/13/2022Energy Code Compliance InspectionsDOYUN KIMprogress
07/13/2022HVAC-R and service water heating system controlsDOYUN KIMenergy_progress
07/13/2022HVAC-R and service water heating equipmentDOYUN KIMenergy_progress
04/26/2022HVAC-R and service water heating system controlsRyan Hansenenergy_progress
04/26/2022HVAC-R and service water heating equipmentRyan Hansenenergy_progress
04/26/2022Fire-Resistant Penetrations and JointsRyan Hansenspecial
04/26/2022HVAC-R and service water piping design and insulationRyan Hansenenergy_progress
04/06/2022Fire-Resistant Penetrations and JointsDOYUN KIMspecial
04/06/2022Sprinkler SystemsDOYUN KIMspecial
03/17/2022Fire-Resistant Penetrations and JointsDOYUN KIMspecial
03/17/2022Sprinkler SystemsDOYUN KIMspecial
Latest 25 of 68.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Hugel X AlessoEvents & gatherings—
Project B01444134 Alteration · Permit Entire · 08/11/2026
Studio STLArts / Culture / EntertainmentFloor 4
Project B01096294 Alteration · LOC Issued · 10/21/2024
NYWDOfficeFloor 6
Project B00554917 Alteration · LOC Issued · 10/18/2021
Momo Test KitchenRestaurant / Food ServiceFloor 1
Project B00261495 Alteration · LOC Issued · 11/21/2019
Project B00261852 Alteration · LOC Issued · 11/21/2019
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 740 on file (BIS + DOB NOW)
▸Plans & Drawings41
▸DOB NOWPlans/Sketch21
09/01/2026B00479939-P1Request digital key ↗
09/01/2026B00516869-I1Request digital key ↗
09/01/2026B00520094-I1Request digital key ↗
Showing 3 of 21 on file for this type
▸DOB NOWPlans/Sketch - Temporary Place of Assembly12
09/02/2026B00156244-I1Request digital key ↗
09/02/2026B00161461-I1Request digital key ↗
09/02/2026B00179312-I1Request digital key ↗
Showing 3 of 12 on file for this type
▸DOB NOWPlans/Sketch - Plumbing6
09/02/2026B00261852-I1Request digital key ↗
09/01/2026B00322674-I1Request digital key ↗
09/01/2026B00311539-I1Request digital key ↗
Showing 3 of 6 on file for this type
▸DOB NOWPlans/Sketch - Place of Assembly1
09/02/2026B00133990-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Mechanical Systems1
09/02/2026B00261495-I1Request digital key ↗
▸Applications & Permits104
▸BISPLAN / WORK APPROVAL APPLICATION75
02/21/2024340741479Open ↗
08/13/2021340704642Open ↗
11/19/2020321386371Open ↗
Showing 3 of 75 on file for this type
▸BISWORK PERMIT APPLICATION23
08/18/2021340704642Open ↗
06/19/2020321386371Open ↗
10/07/2019321995221Open ↗
Showing 3 of 23 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION3
06/29/2020321386371Open ↗
Showing 1 of 3 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION3
06/06/2024321679750Open ↗
Showing 1 of 3 on file for this type
▸Zoning, Tax Lot & Property Records6
▸BISFLOOD ZONE DESIGN CERTIFICATION5
08/16/2021340704642Open ↗
07/21/2020340741479Open ↗
04/15/2020321386371Open ↗
Showing 3 of 5 on file for this type
▸BISFLOOD ZONE COMPLIANCE1
07/21/2020340741479Open ↗
▸Seals & Professional Certifications163
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION41
03/10/2020340683861Open ↗
03/10/2020340683861Open ↗
01/10/2020340683861Open ↗
Showing 3 of 41 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature41
09/02/2026B00156244-I1Open ↗
09/02/2026B00161461-I1Open ↗
09/02/2026B00133990-I1Open ↗
Showing 3 of 41 on file for this type
▸DOB NOWProgress Inspector Seal & Signature29
10/07/2026B00261852-P1Open ↗
10/07/2026B00261852-P1Open ↗
10/07/2026B00261852-P1Open ↗
Showing 3 of 29 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature13
10/07/2026B00261852-P1Open ↗
09/01/2026B00261852-I1Open ↗
09/01/2026B00520141-I1Open ↗
Showing 3 of 13 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST11
10/04/2019321995221Open ↗
Showing 1 of 11 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT9
10/04/2019321995221Open ↗
06/21/2019340683861Open ↗
Showing 2 of 9 on file for this type
▸BISAPPLICANT OWNER SIGNATURE7
07/21/2020340741479Open ↗
11/20/2019340704642Open ↗
07/31/2019340689204Open ↗
Showing 3 of 7 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY4
06/21/2019340683861Open ↗
Showing 1 of 4 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION4
06/21/2019340683861Open ↗
Showing 1 of 4 on file for this type
▸BISProfessional and Owner Certification (POC3)4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸Trade Schedules & Equipment33
▸BISSCHEDULE B - PLUMBING16
01/30/2020340609130Open ↗
09/22/2019340609167Open ↗
06/21/2019340683861Open ↗
Showing 3 of 16 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA6
05/13/2022321775879Open ↗
Showing 1 of 6 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISEQUIPMENT USE PERMITS1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISPLUMBING - SUPPORTING DOCUMENTATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Safety & Tenant Protection6
▸BISSTREET TREE CHECKLIST4
04/15/2020321386371Open ↗
Showing 1 of 4 on file for this type
▸BISSTREET TREE SIGNOFF1
07/20/2020321386371Open ↗
▸BISSTREET TREES: RECEIPT OF STREET TREES SITE PLAN1
06/11/2020321386371Open ↗
▸Environmental & Asbestos33
▸DOB NOWDEP ACP-5: Asbestos Assessment Report16
09/01/2026B00479939-P1Open ↗
09/01/2026B00516869-I1Open ↗
09/01/2026B00520094-I1Open ↗
Showing 3 of 16 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)10
09/11/2020340741479Open ↗
Showing 1 of 10 on file for this type
▸BISDEP ASBESTOS PROJECT COMPLETION FORM5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Energy Compliance49
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY19
01/21/2023340704642Open ↗
08/13/2021340704642Open ↗
09/11/2020340741479Open ↗
Showing 3 of 19 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS14
01/10/2020340609130Open ↗
01/10/2020340609167Open ↗
11/26/2019340683861Open ↗
Showing 3 of 14 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS6
01/10/2020340609167Open ↗
11/26/2019340683861Open ↗
07/19/2019340609158Open ↗
Showing 3 of 6 on file for this type
▸BISNYCECC ANALYSIS3
08/16/2021340704642Open ↗
06/21/2019340683861Open ↗
06/18/2019340683503Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)3
04/01/2025321760180Open ↗
01/21/2023340704642Open ↗
07/20/2020321386371Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS2
06/21/2019340683861Open ↗
Showing 1 of 2 on file for this type
▸BISNYCECC EXEMPTION1
06/18/2019340683503Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
09/01/2026B00554917-I1Open ↗
▸Inspections & Test Reports35
▸BISTECHNICAL REPORT: RESPONSIBILITY26
01/21/2023340704642Open ↗
08/13/2021340704642Open ↗
09/11/2020340741479Open ↗
Showing 3 of 26 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER2
03/12/2024321679750Open ↗
Showing 1 of 2 on file for this type
▸BISHYDRO FLOW TEST LETTER1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISFOOTING AND FOUNDATION INSPECTION1
03/06/2024321679750Open ↗
▸BISTR2: CONCRETE FIELD TESTING TECHNICAL REPORT1
03/11/2024321679750Open ↗
▸BISCONCRETE - CAST-IN-PLACE1
03/06/2024321679750Open ↗
▸BISSTRUCTURAL STEEL - HIGH STRENGTH BOLTING1
03/06/2024321679750Open ↗
▸BISHYDRAULIC FLOW CALCULATIONS1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Approvals, Objections & Sign-offs92
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST38
06/06/2024321679750Open ↗
10/06/2023340704642Open ↗
11/15/2022321775879Open ↗
Showing 3 of 38 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter19
09/02/2026B00156244-I1Open ↗
09/02/2026B00161461-I1Open ↗
09/02/2026B00133990-I1Open ↗
Showing 3 of 19 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE15
12/04/2020321386371Open ↗
11/19/2020321386371Open ↗
06/02/2020321386371Open ↗
Showing 3 of 15 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION9
04/15/2020321386371Open ↗
Showing 1 of 9 on file for this type
▸BISDESIGN COMM. APPROVAL: CITY-OWNED PROPERTY (EXTERIOR WORK)4
07/21/2020340741479Open ↗
06/02/2020321386371Open ↗
11/20/2019340704642Open ↗
Showing 3 of 4 on file for this type
▸BISADMINISTRATIVE OBJECTIONS3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISDESIGN COMM. SIGNOFF: CITY-OWNED PROPERTY (EXTERIOR WORK)2
01/21/2023340704642Open ↗
07/20/2020321386371Open ↗
▸BISFINAL1
03/06/2024321679750Open ↗
▸DOB NOWDesign Commission Sign Off City Owned (Exterior Work)1
09/01/2026B00554917-I1Open ↗
▸Cost, Insurance & Ownership51
▸BISCOST AFFIDAVIT48
07/26/2023321679750Open ↗
11/07/2022321775879Open ↗
11/23/2021321679750Open ↗
Showing 3 of 48 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW33
07/26/2023321679750Open ↗
01/21/2023340704642Open ↗
07/20/2020321386371Open ↗
▸Filing & Intake Forms104
▸BISADDITIONAL INFORMATION58
11/10/2022321775879Open ↗
08/16/2021340704642Open ↗
08/05/2021340741479Open ↗
Showing 3 of 58 on file for this type
▸BISEFILING COVER SHEET19
10/07/2019321995221Open ↗
07/02/2019321972772Open ↗
07/02/2019321972772Open ↗
Showing 3 of 19 on file for this type
▸BISBOROUGH INTAKE FORM16
03/13/2020340609130Open ↗
03/10/2020340683861Open ↗
03/06/2020340609167Open ↗
Showing 3 of 16 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET11
07/21/2020340741479Open ↗
11/20/2019340704642Open ↗
07/31/2019340689204Open ↗
Showing 3 of 11 on file for this type
▸Other Documents22
▸BISPLOT DIAGRAM5
06/02/2020321386371Open ↗
Showing 1 of 5 on file for this type
▸BISFEMA ELEVATION CERT (086-0-33)/ FLOODPROOFING CERT (086-0-34)5
09/26/2023340704642Open ↗
11/15/2022321775879Open ↗
04/15/2020321386371Open ↗
Showing 3 of 5 on file for this type
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION3
07/02/2019321972772Open ↗
Showing 1 of 3 on file for this type
▸BISFEMA FORM (81-31): ELEVATION CERTIFICATE2
01/10/2020340683861Open ↗
10/03/2019321972772Open ↗
▸DOB NOWLowest Floor Elevation Plan2
09/02/2026B00261495-I1Open ↗
09/02/2026B00261852-I1Open ↗
▸DOB NOWFEMA Elevation Certificate (086-0-33)/Flood Proofing Certificate (086-0-34)2
08/13/2026B00261495-I1Open ↗
08/13/2026B00261852-I1Open ↗
▸DOB NOWFlood Plan Emergency Temporary Flood Shields1
08/19/2026B01290311-I1Open ↗
▸DOB NOWSupporting Document1
08/13/2026B00133990-I1Open ↗
▸DOB NOWProof of Historic Building1