| Owner | Filings | Most Recent |
|---|---|---|
| ORSID REALTY | 49 | 07/08/2026 |
| KINGS GROUP NY | 18 | 07/08/2026 |
| ANDAMIO SCAFFOLDING LLC | 15 | 03/22/2026 |
| 80 CPW APT CORP | 5 | 03/22/2026 |
| TOWER BLDG SERVICES | 3 | 03/22/2026 |
| YATES REST GROUP | 1 | 03/22/2026 |
| GOODSTEIN MANAGEMENT | 15 | 03/22/2026 |
| G.P. WINTER ASSOCIATES IN | 1 | 03/22/2026 |
| 80 CPW CORP | 1 | 03/22/2026 |
| RESIDENCE | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| RAD DESIGN & ARCHITECTURE PLLC | 5 | 07/31/2026 |
| ARCHETYPE ARCHITECTURE | 5 | 07/29/2026 |
| JAMES MAYNARD ARCHITECT LLC | 44 | 05/21/2026 |
| BRYNNEMARIE LANCIOTTI | 1 | 02/04/2026 |
| HOWARD L ZIMMERMAN ARCH & ENG DPC | 10 | 06/23/2025 |
| JOSEPH K. BLUM CO. LLP | 2 | 01/02/2025 |
| PENTA WINDMILLER ARCHITECTURE, PC | 1 | 08/20/2024 |
| A2 ARCHITECT, PC | 5 | 11/17/2023 |
| KATZ ARCHITECTURE | 2 | 03/09/2023 |
| JUNG H. CHOI, ARCHITECT, PC | 3 | 09/19/2022 |
| ENTHINK ENGINEERS LLC | 5 | 07/20/2022 |
| CES ENGINEERING LLC | 3 | 05/11/2022 |
| GREEN DESIGN | 1 | 10/02/2020 |
| SYED ENGINEERING, P.C. | 2 | 08/20/2020 |
| PAUL PERDEK, PROF. ENG. PLLC | 1 | 04/25/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| CLARKE CONSTRUCTION CONSULTANTS | 43 | 03/21/2026 |
| NEXUS CONSULTING NYC, INC | 8 | 03/21/2026 |
| HOWARD L ZIMMERMAN ARCHITECTS | 20 | 03/21/2026 |
| D D EXPEDITORS | 4 | 03/21/2026 |
| JAM CONSULTANTS, INC. | 6 | 03/21/2026 |
| J A EXPEDITING | 14 | 03/21/2026 |
| CODE | 4 | 03/21/2026 |
| AE DESIGN SOLUTION | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| KINGS GROUP NY CORP | General Contractor | 18 | 07/08/2026 |
| ANDAMIO SCAFFOLDING LLC | General Contractor | 16 | 07/08/2026 |
| RG DECORATING & PAINTING | General Contractor | 13 | 07/08/2026 |
| H & N RESTORATION CORP | General Contractor | 12 | 03/21/2026 |
| J.R. FORDHAM PAINTING COR | General Contractor | 7 | 07/08/2026 |
| EVEREST SCAFFOLDING INC | General Contractor | 7 | 07/08/2026 |
| MAGNUM PLUMBING & HEATING CORP. | Plumbing | 6 | 07/08/2026 |
| TOP DOG PLBG & HTG CORP | Plumbing | 3 | 07/08/2026 |
| HAKKA CONTRACTING, INC | General Contractor | 3 | 03/21/2026 |
| SCUTARI RENOVATIONS LLC | General Contractor | 3 | 03/21/2026 |
| SCORDIO CONSTRUCTION INC | General Contractor | 3 | 07/08/2026 |
| NICHIBI ORGANIZATION INC | General Contractor | 3 | 07/08/2026 |
| G.BASSOLINO PLUMBING LTD | Plumbing | 3 | 07/08/2026 |
| ORBIT PLBG & HTG INC | Plumbing | 2 | 07/08/2026 |
| PHILIP ZUARDI | Electrical | 2 | 03/21/2026 |
| AP PLUMBING & HVAC LLC | Plumbing | 2 | 07/08/2026 |
| DOVAL PLBG & HTG CORP | Plumbing | 2 | 07/08/2026 |
| EUROYAL NY CORP | General Contractor | 2 | 07/08/2026 |
| ROMEL CONSTRUCTION CORP | General Contractor | 2 | 03/21/2026 |
| ROXY INTERIORS LLC | General Contractor | 2 | 04/09/2026 |
| S.A.L. ELECTRIC CO INC. | Electrical | 2 | 03/22/2026 |
| INTERIORS BY GLEN LLC | General Contractor | 2 | 03/21/2026 |
| WORLDKOR CONSTRUCTION CORP | General Contractor | 2 | 03/21/2026 |
| ROBERT COVELLO | Electrical | 1 | 03/21/2026 |
| RAMDATHSINGH, PURAN | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| RAD DESIGN & ARCHITECTURE | 2082 | 5 | 07/31/2026 |
| MARCH CHADWICK, ARCHITECT | 2253 | 3 | 07/29/2026 |
| WINTON GROUP ARCHITECTURE | 4343 | 12 | 05/21/2026 |
| HOWARD L ZIMMERMAN ARCHIT | 1712 | 10 | 06/23/2025 |
| JOSEPH K. BLUM CO. LLP | 1741 | 2 | 01/02/2025 |
| A2 ARCHITECT, PC | 2504 | 3 | 11/17/2023 |
| INTEGRITY CONSULTING SERV | 666 | 2 | 03/09/2023 |
| CATALPA SPECIAL INSPECTIO | 2004 | 3 | 05/11/2022 |
| METRO INSPECTIONS LLC | 7363 | 3 | 11/08/2021 |
| GROUP-S LLC | 5216 | 1 | 06/04/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | SCUTARI NY CORP | 09/30/2026 |
| DOB NOW | Plumbing | Permit Issued | RJ BRUNO INC | 09/23/2026 |
| DOB NOW | General Construction | Permit Issued | EUROYAL NY CORP | 06/16/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | EUROYAL NY CORP | 06/08/2026 |
| DOB NOW | Plumbing | Permit Issued | ARCH PLUMBING & HTNG CORP | 05/27/2026 |
| DOB NOW | General Construction | Signed-off | GRAND DESIGNS NY LLC | 02/24/2026 |
| DOB NOW | General Construction | Signed-off | ROXY INTERIORS LLC | 01/09/2026 |
| DOB NOW | Plumbing | Permit Issued | NEW YORK PARK PLBG&HTG CO | 10/15/2025 |
| DOB NOW | General Construction | Permit Issued | HIGHER STANDARD INTERIORS | 09/23/2025 |
| DOB NOW | Plumbing | Signed-off | TAP PLUMBING CORP | 09/08/2025 |
| DOB NOW | General Construction | Signed-off | ROXY INTERIORS LLC | 09/05/2025 |
| DOB NOW | General Construction | Signed-off | EURO GROUP DESIGN GROUP | 07/15/2025 |
| DOB NOW | General Construction | Signed-off | RG DECORATING & PAINTING | 07/10/2025 |
| DOB NOW | General Construction | Permit Issued | J.R. FORDHAM PAINTING | 06/18/2025 |
| DOB NOW | Plumbing | Signed-off | G.BASSOLINO PLUMBING LTD | 05/09/2025 |
| DOB NOW | Plumbing | Signed-off | DOVAL PLBG & HTG CORP | 10/29/2024 |
| DOB NOW | General Construction | Permit Issued | J.R. FORDHAM PAINTING | 10/07/2024 |
| DOB NOW | General Construction | Signed-off | MICHAEL G O'MARA | 08/22/2024 |
| DOB NOW | Plumbing | Signed-off | P.S.I. MECHANICAL | 07/10/2024 |
| DOB NOW | General Construction | Signed-off | SCUTARI RENOVATIONS LLC | 07/08/2024 |
| DOB NOW | Plumbing | Signed-off | G.BASSOLINO PLUMBING LTD | 05/13/2024 |
| DOB NOW | Plumbing | Signed-off | MAGNUM PLUMBING & HEATING CORP. | 03/04/2024 |
| DOB NOW | General Construction | Signed-off | H & N RESTORATION CORP | 02/14/2024 |
| DOB NOW | General Construction | Permit Issued | LAKE CONTRACTING LLC | 01/22/2024 |
| DOB NOW | General Construction | Signed-off | HAKKA CONTRACTING, INC | 12/14/2023 |
| DOB NOW | Plumbing | Signed-off | SURPASS PLBG & HTG INC | 12/13/2023 |
| DOB NOW | Plumbing | Signed-off | CROSSFIELD PLBG.&HTG | 09/22/2023 |
| DOB NOW | General Construction | Signed-off | RG DECORATING & PAINTING | 09/13/2023 |
| DOB NOW | Supported Scaffold | Signed-off | KINGS GROUP NY CORP | 09/11/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | KINGS GROUP NY CORP | 09/11/2023 |
| DOB NOW | Plumbing | Signed-off | DOVAL PLBG & HTG CORP | 09/11/2023 |
| DOB NOW | Plumbing | Signed-off | BYPASS MECHANICAL CORP | 08/17/2023 |
| DOB NOW | General Construction | Permit Issued | J.R. FORDHAM PAINTING | 06/29/2023 |
| DOB NOW | Plumbing | Signed-off | DOUG'S PLBG & HTG SERV CO | 04/11/2023 |
| DOB NOW | General Construction | Signed-off | RG DECORATING & PAINTING | 04/11/2023 |
| DOB NOW | Plumbing | Signed-off | G.BASSOLINO PLUMBING LTD | 12/27/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | ANDAMIO SCAFFOLDING LLC | 12/02/2022 |
| DOB NOW | General Construction | Signed-off | RG DECORATING & PAINTING | 11/16/2022 |
| DOB NOW | General Construction | Signed-off | RG DECORATING & PAINTING | 11/16/2022 |
| DOB NOW | Plumbing | Signed-off | MAGNUM PLUMBING & HEATING CORP. | 11/07/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/31/2026 | Signed-off | TAP PLUMBING CORP | Gas, Water/Sanitary |
| 07/29/2026 | Permit Issued | NEW YORK PARK PLBG&HTG CO | Gas, Water/Sanitary |
| 05/21/2026 | Permit Issued | RJ BRUNO INC | Gas, Water/Sanitary |
| 05/09/2023 | Signed-off | DOVAL PLBG & HTG CORP | Gas, Water/Sanitary |
| 04/27/2021 | — | — | Water/Sanitary |
| 03/16/2021 | Signed-off | MAGNUM PLUMBING & HEATING | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/25/2026 | Permit Issued | APN ELECTRICAL CORP | General Wiring |
| 07/22/2026 | Permit Issued | GREEN APPLE ELECL SVCS LL | General Wiring |
| 02/26/2026 | Complete | AMOR ELECTRIC CORP | General Wiring |
| 12/28/2025 | Complete | A & S MASTER ELEC'L CORP | — |
| 10/11/2025 | Permit Issued | SPIRO ELECTRIC INC. | General Wiring |
| 06/09/2025 | Complete | E & M ELECTRICAL NY CORP | General Wiring |
| 05/29/2025 | Permit Issued | CENTENNIAL ELEVATOR INDUS | General Wiring |
| 03/30/2025 | Permit Issued | EVS ELECTRIC CORP | General Wiring |
| 12/09/2024 | Complete | S.A.L. ELECTRIC CO INC. | — |
| 07/11/2024 | Complete | US1 ELECTRIC CORP | General Wiring |
| 06/23/2024 | Complete | S.A.L. ELECTRIC CO INC. | General Wiring |
| 03/04/2024 | Complete | DENMAR ELECTRIC CORP | General Wiring |
| 02/14/2024 | Permit Issued | J.G.C. ELECTRIC, LLC | General Wiring |
| 02/12/2024 | Complete | BIG CITY ELECL SOLUTIONS | General Wiring |
| 01/26/2024 | Complete | ATMOS ELECTRIC SVCE CORP | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/31/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/29/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/28/2026 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 04/24/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/14/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/13/2026 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 03/13/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/03/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/03/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 12/10/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/19/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/28/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 08/08/2025 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 07/28/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/03/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 01/17/2025 | Pass-Final PL - More than 10 Requested Floors | Pass | View ↗ |
| 12/17/2024 | Pass-Final PL - More than 10 Requested Floors | Pass | View ↗ |
| 12/03/2024 | Fail-Final PL - More than 10 Requested Floors | Fail | View ↗ |
| 10/24/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/05/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/23/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/20/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/13/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/31/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/25/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/13/2026 | Fire-Resistant Penetrations and Joints | Radoslaw Kurek | special |
| 07/31/2026 | Fire-Resistant Penetrations and Joints | Radoslaw Kurek | special |
| 07/30/2026 | Fire-Resistant Penetrations and Joints | MARCH CHADWICK | special |
| 07/28/2026 | Fire-Resistant Penetrations and Joints | MARCH CHADWICK | special |
| 05/04/2026 | Fire-Resistant Penetrations and Joints | Radoslaw Kurek | special |
| 05/04/2026 | Energy Code Compliance Inspections | Radoslaw Kurek | progress |
| 05/04/2026 | Final | Radoslaw Kurek | progress |
| 05/04/2026 | Interior lighting power | Radoslaw Kurek | energy_progress |
| 05/04/2026 | Lighting in dwelling units | Radoslaw Kurek | energy_progress |
| 03/27/2026 | Final | Radoslaw Kurek | progress |
| 03/27/2026 | Interior lighting power | Radoslaw Kurek | energy_progress |
| 03/27/2026 | Lighting in dwelling units | Radoslaw Kurek | energy_progress |
| 03/27/2026 | Fire-Resistant Penetrations and Joints | Radoslaw Kurek | special |
| 03/27/2026 | Energy Code Compliance Inspections | Radoslaw Kurek | progress |
| 03/27/2026 | Fire-Resistant Penetrations and Joints | Radoslaw Kurek | special |
| 03/12/2026 | HVAC-R and service water heating system controls | MARCH CHADWICK | energy_progress |
| 03/12/2026 | Lighting in dwelling units | Alan Berman | energy_progress |
| 03/12/2026 | HVAC-R and service water heating equipment | MARCH CHADWICK | energy_progress |
| 03/12/2026 | HVAC-R and service water piping design and insulation | MARCH CHADWICK | energy_progress |
| 03/12/2026 | Lighting controls | Alan Berman | energy_progress |
| 03/12/2026 | Maintenance information | MARCH CHADWICK | energy_progress |
| 03/12/2026 | Energy Code Compliance Inspections | Alan Berman | progress |
| 03/12/2026 | Final | Alan Berman | progress |
| 03/03/2026 | Lighting in dwelling units | James Maynard | energy_progress |
| 03/03/2026 | Lighting controls | James Maynard | energy_progress |