1987Year Built
2Stories
W5Building Class
R6Zoning
147,950 sfGross Floor Area
2Units
LL97 Covered77 Open Violations 76 unresolved · 1 paperwork only ▸FDNY Report ↗
City university · Owner of record: DORMITORY AUTHORITY OF THE STATE OF NEW YORK · 183,400 sf lot · 0.81 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire Protection
Roof35p · 4 filings · 20 docs
Floor 242p · 4 filings · 20 docs
Floor 135p · 4 filings · 20 docs
Basement1p · 1 filing · 6 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
DASNY5007/08/2026
DORMITORY AUTHORITY OF THE STATE OF NEW YORK703/22/2026
DORMITORY AUTHORITY STATE OF NY3603/21/2026
CUNY1503/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
CONSTRUCTION PERMIT SERVICES1003/21/2026
OUTSOURCE CONSULTANTS, INC.1403/21/2026
AK CONSULTING SERVICES203/21/2026
HERITAGE ARCHITECTURE103/21/2026
NOEL BUILDING CONSULTING INC603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
MICHAEL ANTHONY CONTRACTINGGeneral Contractor1507/08/2026
CARDOZA PLUMBING CORPPlumbing607/08/2026
A.B.C.D. CONSTRUCTION CORGeneral Contractor403/21/2026
SIRINA FIRE PROT CORPFire Protection207/08/2026
LUIS JIMENEZElectrical103/21/2026
MAC FHIONNGHAILE & SONSElectrical103/22/2026
FOY, REMERElectrical103/21/2026
ALLIANCE PLUMBING CORPPlumbing107/08/2026
PIMPINELLA, FRANKElectrical103/21/2026
H&F IRON WORKSElectrical103/21/2026
JIMENEZ LUISElectrical103/21/2026
KING, ARTHURElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
FUTURE TECH CONSULTANTS O589804/21/2023
Building Lifecycle
All (21)Filed (21)
02/10/2026
Filed — Alteration
Herewith Filing Plumbing Work in connection with courtyard renovations, work proposed is part of the irrigation system as per plans filed herewith.
B01306112-S4
02/05/2026
Filed — Alteration
Herewith Filing Plumbing Work in connection with courtyard renovations, work proposed is part of the irrigation system as per plans filed herewith.
B01306112-S2
02/04/2026
Filed — Alteration
Herewith Filing Plumbing Work in connection with courtyard renovations, work proposed is part of the irrigation system as per plans filed herewith.
B01306112-S3
01/28/2026
Filed — Alteration
Herewith Filing Plumbing Work in connection with courtyard renovations, work proposed is part of the irrigation system as per plans filed herewith.
B01306112-S1
01/22/2026
Filed — Alteration
Herewith Filing Plumbing Work in connection with courtyard renovations, work proposed is part of the irrigation system as per plans filed herewith.
B01306112-I1
01/20/2026
Filed — Alteration
INSTALLATION OF FUEL STORAGE FOR EMERGENCY GENERATOR. NO CHANGE OF USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B01274916-I1
01/20/2026
Filed — Alteration
INSTALLATION OF STRUCTURAL WORK FOR EMERGENCY GENERATOR. SEE PLANS FOR DETAIL. NO CHANGE OF USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION
B01274898-I1
01/20/2026
Filed — Alteration
INSTALLATION OF FUEL STORAGE FOR EMERGENCY GENERATOR. NO CHANGE OF USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B01274916-S1
04/28/2023
Filed — Alteration
FURNISH AND INSTALL NEW TEMP 3,500 GALLON DOUBLE WALL ABOVE GROUND FUEL TANK & ASSOC PIPING FOR THE. EMERGENCY GENERATOR IN PARKING LOT. CONNECT TEMP FUEL TANK TO THE EXISTING FUEL PIPING IN THE CHILLER ROOM. NO CHANGE IN USE, EGRESS OR OCCUPANCY
B00665408-S2
04/21/2023
Filed — Alteration
FURNISH AND INSTALL NEW TEMP 3,500 GALLON DOUBLE WALL ABOVE GROUND FUEL TANK & ASSOC PIPING FOR THE. EMERGENCY GENERATOR IN PARKING LOT. CONNECT TEMP FUEL TANK TO THE EXISTING FUEL PIPING IN THE CHILLER ROOM. NO CHANGE IN USE, EGRESS OR OCCUPANCY
B00665408-P1
04/21/2023
Filed — Alteration
FURNISH AND INSTALL NEW TEMP 3,500 GALLON DOUBLE WALL ABOVE GROUND FUEL TANK & ASSOC PIPING FOR THE. EMERGENCY GENERATOR IN PARKING LOT. CONNECT TEMP FUEL TANK TO THE EXISTING FUEL PIPING IN THE CHILLER ROOM. NO CHANGE IN USE, EGRESS OR OCCUPANCY
B00665408-P2
04/13/2022
Filed — Alteration
FURNISH AND INSTALL NEW TEMP 3,500 GALLON DOUBLE WALL ABOVE GROUND FUEL TANK & ASSOC PIPING FOR THE. EMERGENCY GENERATOR IN PARKING LOT. CONNECT TEMP FUEL TANK TO THE EXISTING FUEL PIPING IN THE CHILLER ROOM. NO CHANGE IN USE, EGRESS OR OCCUPANCY
B00665408-S1
02/24/2022
Filed — Alteration
FURNISH AND INSTALL NEW TEMP 3,500 GALLON DOUBLE WALL ABOVE GROUND FUEL TANK & ASSOC PIPING FOR THE. EMERGENCY GENERATOR IN PARKING LOT. CONNECT TEMP FUEL TANK TO THE EXISTING FUEL PIPING IN THE CHILLER ROOM. NO CHANGE IN USE, EGRESS OR OCCUPANCY
B00665408-I1
02/23/2022
Filed — Alteration
Structural modifications
B00479661-P1
07/14/2021
Filed — Alteration
Structural modifications
B00479661-I1
03/26/2021
Filed — Alteration
B00322849-I1
03/19/2021
Filed — Alteration
B00323469-I1
03/19/2021
Filed — Alteration
B00322876-I1
03/19/2021
Filed — Alteration
B00322838-I1
07/06/2020
Filed — Alteration
B00365278-I1
07/03/2019
Filed — No Work
B00180227-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWStructuralPermit IssuedMICHAEL ANTHONY CONTRACTING05/31/2024
DOB NOWMechanical SystemsPermit IssuedMICHAEL ANTHONY CONTRACTING05/31/2024
DOB NOWPlumbingSigned-offCARDOZA PLUMBING WMBE12/06/2023
DOB NOWBoiler EquipmentSigned-offSERVICE TECH MECH&PLBG IN09/01/2023
DOB NOWGeneral ConstructionPermit IssuedMICHAEL ANTHONY CONTRACTING06/13/2023
DOB NOWMechanical SystemsPermit IssuedMICHAEL ANTHONY CONTRACTING06/01/2023
DOB NOWPlumbingSigned-offCARDOZA PLUMBING CORP03/17/2023
DOB NOWSprinklersPermit IssuedCARDOZA PLUMBING CORP03/17/2023
DOB NOWSprinklersPermit IssuedSIRINA FIRE PROT CORP01/31/2023
DOB NOWSprinklersPermit IssuedSIRINA FIRE PROT CORP01/10/2023
DOB NOWStructuralPermit IssuedMICHAEL ANTHONY CONTRACTING06/14/2022
DOB NOWPlumbingPermit IssuedCARDOZA PLUMBING CORP06/14/2022
DOB NOWPlumbingSigned-offCARDOZA PLUMBING CORP06/14/2022
DOB NOWMechanical SystemsPermit IssuedMICHAEL ANTHONY CONTRACTING06/02/2022
DOB NOWMechanical SystemsPermit IssuedMICHAEL ANTHONY CONTRACTING12/14/2021
DOB NOWFoundationPermit IssuedMICHAEL ANTHONY CONTRACTING11/30/2021
DOB NOWPlumbingSigned-offCARDOZA PLUMBING CORP09/09/2021
DOB NOWPlumbingPermit IssuedCARDOZA PLUMBING CORP09/07/2021
DOB NOWConstruction FencePermit IssuedA.B.C.D. CONSTRUCTION COR02/23/2021
DOB NOWConstruction FencePermit IssuedA.B.C.D. CONSTRUCTION COR07/08/2020
BISOTISSUEDMICHAEL ANTHONY CONTRACTING03/25/2024
BISOTISSUEDMICHAEL ANTHONY CONTRACTING03/27/2023
BISOTISSUEDMICHAEL ANTHONY CONTRACTING08/01/2022
BISOTISSUEDMICHAEL ANTHONY CONTRACTING10/13/2021
BISOTISSUEDA.B.C.D. CONSTRUCTION COR02/05/2021
BISOTISSUEDA.B.C.D. CONSTRUCTION COR12/09/2020
BISOTISSUEDA.B.C.D. CONSTRUCTION COR06/29/2020
BISOTISSUEDINFINITY CONTRACTING SERV11/09/2017
BISMHISSUEDINFINITY CONTRACTING SERV11/09/2017
BISOTISSUEDINFINITY CONTRACTING SERV11/09/2017
BISPLISSUEDPAR PLUMBING CO., INC03/20/2017
BISMHISSUEDINFINITY CONTRACTING SERV11/14/2016
BISOTISSUEDINFINITY CONTRACTING SERV11/14/2016
BISOTISSUEDINFINITY CONTRACTING SERV11/14/2016
BISOTISSUEDPETK, INC11/10/2016
BISOTISSUEDINFINITY CONTRACTING SERV11/09/2016
BISMHISSUEDINFINITY CONTRACTING SERV11/09/2016
BISOTISSUEDINFINITY CONTRACTING SERV11/09/2016
BISMHISSUEDMANHATTAN BUSINESS INTERIORS05/13/2015
BISOTISSUEDMANHATTAN BUSINESS INTERIORS05/13/2015
+ 30 more permits on file
1 project · most recent 01/20/2026
Generators
FiledStatusContractorScopeMake / Model / Capacity
01/20/2026——Generators
Generators
Cummins DQCB 750 kW · Generator ×1
1 project · most recent 02/10/2026
Water/Sanitary
FiledStatusContractorScope
02/10/2026——Water/Sanitary
3 projects · most recent 10/27/2021
General Wiring Lighting
FiledStatusContractorScope
10/27/2021CompleteEGG ELECTRIC INC.General Wiring, Lighting
10/20/2021CompleteMAC FHIONNGHAILE & SONSGeneral Wiring
04/18/2019CompleteJ.H. ELEC. OF NEW YORK INGeneral Wiring
2 projects · most recent 01/20/2026
Steel Concrete
FiledStatusContractorScope
01/20/2026——Steel, Concrete
02/23/2022Permit IssuedMICHAEL ANTHONY CONTRACTISteel, Concrete
1 project · most recent 04/28/2023
Fence
FiledStatusContractorScope
04/28/2023Signed-offSERVICE TECH MECH&PLBG INFence
▾Field Inspections (DOB CAP) — 12
DateTypeResultReport
02/05/2025Pass-Final Boiler Equipment Withdrawal InspectionPassView ↗
06/10/2024Certified Storm Drainage-ST-Fixtures-FinishCertifiedView ↗
06/10/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
06/07/2024Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
01/29/2024Pass-Final SP - Up to 3 Requested FloorsPassView ↗
12/05/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
12/05/2023Pass-Final CND-Occupancy InspectionPassView ↗
04/28/2023Certified Gas-Gas-Piping-RoughingCertifiedView ↗
04/28/2023Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
04/28/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
04/19/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
04/05/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 48
DateRequirementInspectorRole
01/22/2026Lighting controls—energy_progress
01/08/2026Exterior lighting power—energy_progress
10/21/2025Structural Steel - Welding—special
10/21/2025Structural Steel - Details—special
10/21/2025Final—progress
10/21/2025Fire-Resistant Penetrations and Joints—special
10/21/2025Final—progress
10/21/2025Footing and Foundation—progress
10/21/2025Final—progress
10/21/2025Deep Foundation Elements—special
10/21/2025Concrete - Cast-In-Place—special
10/21/2025Subsurface Conditions – Fill Placement & In-Place Density—special
10/21/2025Subgrade Inspections—special
10/02/2025Fuel-Oil Storage and Fuel-Oil Piping Systems—special
10/02/2025Post-installed Anchors—special
10/02/2025Fire-Resistant Penetrations and Joints—special
10/02/2025Emergency and Standby Power Systems (Generator)—special
10/02/2025Structural Steel - Details—special
10/02/2025Fire-Resistance Rated Construction—progress
08/20/2025Mechanical Systems—special
08/20/2025Final—progress
08/20/2025Final—progress
07/24/2023Fire-Resistant Penetrations and JointsMARISA HARTEspecial
07/24/2023Fuel-Oil Storage and Fuel-Oil Piping SystemsMARISA HARTEspecial
04/13/2023Final—progress
Latest 25 of 48.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
City University Of New York Ing Buili Medgar Evers CollegeEducationBasement
Project B01274916 Alteration · Approved · 01/20/2026
Medgar Ever CollegeEducation—
Project B00365278 Alteration · Permit Entire · 07/06/2020
The City University of New York MEDGAR EVERS COLLEGEEducation—
Project B00180227 No Work · Approved · 07/03/2019
Read from each project’s drawing title blocks and cover sheets and checked twice; a name appears only when it is the occupant, never the owner, landlord or designer.
▾Documents — 574 on file (BIS + DOB NOW)
▸Plans & Drawings22
▸DOB NOWPlans/Sketch15
08/31/2026B00479661-P1Request digital key ↗
08/31/2026B00479661-I1Request digital key ↗
08/31/2026B00665408-I1Request digital key ↗
Showing 3 of 15 on file for this type
▸DOB NOWPlans/Sketch - Sprinkler2
09/01/2026B00323469-I1Request digital key ↗
09/01/2026B00322849-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing2
09/01/2026B00322838-I1Request digital key ↗
09/01/2026B00322849-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Place of Assembly1
09/02/2026B00180227-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Construction Fence1
09/02/2026B00365278-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Mechanical Systems1
09/01/2026B00322876-I1Request digital key ↗
▸Applications & Permits108
▸BISPLAN / WORK APPROVAL APPLICATION72
03/18/2024340762534Open ↗
02/05/2024340762534Open ↗
09/01/2021340762534Open ↗
Showing 3 of 72 on file for this type
▸BISWORK PERMIT APPLICATION35
10/13/2021340762534Open ↗
06/29/2020340723195Open ↗
11/13/2017321393782Open ↗
Showing 3 of 35 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION1
08/26/2019321393782Open ↗
▸Zoning, Tax Lot & Property Records2
▸BISZONING DIAGRAM2
08/31/2021340762534Open ↗
Showing 1 of 2 on file for this type
▸Seals & Professional Certifications128
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION76
08/30/2021340762534Open ↗
08/23/2019321393782Open ↗
08/23/2019321393782Open ↗
Showing 3 of 76 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature21
08/31/2026B00479661-I1Open ↗
08/31/2026B00479661-P1Open ↗
08/31/2026B00665408-I1Open ↗
Showing 3 of 21 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST8
08/31/2021340762534Open ↗
08/30/2021340762534Open ↗
03/19/2015321089399Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWProgress Inspector Seal & Signature6
08/26/2026B00479661-P1Open ↗
08/26/2026B00479661-P1Open ↗
08/26/2026B00479661-P1Open ↗
Showing 3 of 6 on file for this type
▸BISProfessional and Owner Certification (POC3)4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/23/2026B00665408-I1Open ↗
08/26/2026B00479661-P1Open ↗
08/24/2026B00479661-I1Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT3
01/12/2021340762534Open ↗
03/19/2015321089399Open ↗
Showing 2 of 3 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISAPPLICANT OWNER SIGNATURE2
04/29/2020340723195Open ↗
03/06/2015340220754Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
01/12/2021340762534Open ↗
▸Trade Schedules & Equipment36
▸BISSCHEDULE B - PLUMBING20
03/06/2015340220754Open ↗
10/17/2014320419695Open ↗
10/07/2014320759611Open ↗
Showing 3 of 20 on file for this type
▸BISSELF-CERT PLUMBING NOTICE6
08/11/2015320759611Open ↗
09/24/2014320759611Open ↗
09/17/2014320419695Open ↗
Showing 3 of 6 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE5
07/10/2017321615132Open ↗
06/02/2016321393782Open ↗
Showing 2 of 5 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA3
12/21/2018320881006Open ↗
10/11/2014320420077Open ↗
09/20/2014320571467Open ↗
▸BISEQUIPMENT USE APPLICATION/PERMIT1
07/16/2015320419695Open ↗
▸BISEQUIPMENT USE PERMITS1
07/16/2015320419695Open ↗
▸Environmental & Asbestos43
▸BISASBESTOS: CERTIFICATION (DEP ACP5)13
08/30/2021340762534Open ↗
09/13/2019321393782Open ↗
08/23/2019321393782Open ↗
Showing 3 of 13 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report11
08/31/2026B00479661-I1Open ↗
08/31/2026B00479661-P1Open ↗
08/31/2026B00665408-I1Open ↗
Showing 3 of 11 on file for this type
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)3
08/31/2021340762534Open ↗
07/18/2020340723195Open ↗
Showing 2 of 3 on file for this type
▸BISASBESTOS: VARIANCE (DEP FORM V5)1
06/29/2020340723195Open ↗
▸BISASBESTOS-WORK UNDET 1000 SQ FT (DEP ACP7)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISAPPLICANT SHALL PROVIDE 1 ACP-21 FORMPRIOR TO SIGN OFF: TRU0651BX201
11/15/2022340723195Open ↗
▸Energy Compliance20
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS10
08/30/2021340762534Open ↗
12/07/2017321615132Open ↗
09/07/2017321615132Open ↗
Showing 3 of 10 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY4
12/02/2022340723195Open ↗
11/14/2022340723195Open ↗
09/29/2021340762534Open ↗
Showing 3 of 4 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS3
11/14/2022340723195Open ↗
08/23/2019321393782Open ↗
07/16/2015320419695Open ↗
▸BISTR8: Energy Code Progress Inspections2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISTECHNICAL REPORT: ENERGY1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Inspections & Test Reports23
▸BISTECHNICAL REPORT: RESPONSIBILITY7
12/02/2022340723195Open ↗
11/14/2022340723195Open ↗
09/29/2021340762534Open ↗
Showing 3 of 7 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER4
11/09/2016321393782Open ↗
11/07/2014320419695Open ↗
Showing 2 of 4 on file for this type
▸BISTECHNICAL REPORT: SOIL INSPECTION4
07/16/2015320419695Open ↗
11/07/2014320419695Open ↗
Showing 2 of 4 on file for this type
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX3
11/09/2016321393782Open ↗
Showing 1 of 3 on file for this type
▸BISHYDRO FLOW TEST LETTER3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISFIRESTOP, DRAFTSTOP, AND FIREBLOCKSYSTEM1
05/21/2015340220754Open ↗
▸BISHYDRAULIC FLOW CALCULATIONS1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Approvals, Objections & Sign-offs67
▸BISADMINISTRATIVE OBJECTIONS21
03/19/2015321089399Open ↗
Showing 1 of 21 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter21
08/31/2026B00479661-I1Open ↗
08/31/2026B00479661-P1Open ↗
08/31/2026B00665408-S1Open ↗
Showing 3 of 21 on file for this type
▸BISCERTIFICATE OF OCCUPANCY - LOC: REQUEST14
01/06/2015320420077Open ↗
01/06/2015320759611Open ↗
10/17/2014320759611Open ↗
Showing 3 of 14 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION11
07/16/2015320419695Open ↗
10/17/2014320759611Open ↗
10/17/2014320759611Open ↗
Showing 3 of 11 on file for this type
▸Cost, Insurance & Ownership61
▸BISCOST AFFIDAVIT56
11/14/2022340723195Open ↗
01/12/2021340762534Open ↗
04/29/2020340723195Open ↗
Showing 3 of 56 on file for this type
▸BISPROJECT SPECIFIC GENERAL LIABILITY INSURANCE (PGLI)3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISPROJECT-SPECIFIC GL INSURANCE2
10/06/2021340762534Open ↗
Showing 1 of 2 on file for this type
▸Filing & Intake Forms58
▸BISEFILING COVER SHEET39
07/10/2017321615132Open ↗
07/10/2017321615132Open ↗
07/10/2017321615132Open ↗
Showing 3 of 39 on file for this type
▸BISADDITIONAL INFORMATION12
03/18/2024340762534Open ↗
09/30/2021340762534Open ↗
05/21/2020340723195Open ↗
Showing 3 of 12 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET4
01/12/2021340762534Open ↗
04/29/2020340723195Open ↗
03/06/2015340220754Open ↗
Showing 3 of 4 on file for this type
▸BISBOROUGH INTAKE FORM3
04/03/2020321615132Open ↗
09/14/2019321393782Open ↗
08/23/2019321393782Open ↗
▸Other Documents6
▸BISPLOT DIAGRAM4
08/31/2021340762534Open ↗
08/30/2021340762534Open ↗
Showing 2 of 4 on file for this type
▸BISSUSTAINABLE ROOF ZONE FORM1
09/29/2021340762534Open ↗
▸DOB NOWWaiver Document1
08/15/2026B00665408-S2Open ↗