| Owner | Filings | Most Recent |
|---|---|---|
| St John's University | 40 | 10/13/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Kyle Mackenzie | 2 | 08/28/2026 |
| Lawrance Jaccard | 1 | 08/28/2026 |
| KZ Engineering | 1 | 03/20/2025 |
| AR Consulting Engineer | 1 | 02/17/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| Synergy Building Consultants | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Joreich Restoration Group | specialty_contractor | 2 | 03/21/2026 |
| Med-Tek Contracting | General Contractor | 2 | 09/10/2026 |
| Arsenal Scaffold | Scaffold | 2 | 07/08/2026 |
| Devo Fire Protection | Fire Protection | 1 | 09/13/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Philibert Engineering | 223 | 3 | 08/28/2026 |
| AR Consulting Engineer P | 4054 | 1 | 02/17/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sprinklers | Permit Issued | Devo Fire Protection | 09/11/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Med-Tek Contracting | 09/09/2026 |
| DOB NOW | General Construction | Permit Issued | Med-Tek Contracting | 09/08/2026 |
| DOB NOW | Structural | Signed-off | Joreich Restoration Group | 04/11/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | Arsenal Scaffold | 03/20/2025 |
| DOB NOW | Supported Scaffold | Signed-off | Arsenal Scaffold | 03/20/2025 |
| BIS | OT | ISSUED | Dynamic US | 12/28/2017 |
| BIS | SP | ISSUED | Devo Fire Protection | 06/06/2017 |
| BIS | MH | ISSUED | Med-Tek Contracting | 06/05/2017 |
| BIS | OT | ISSUED | Med-Tek Contracting | 06/05/2017 |
| BIS | OT | ISSUED | Dynamic US | 05/18/2017 |
| BIS | SP | ISSUED | New Era Mechanical Service | 05/01/2017 |
| BIS | SD | ISSUED | New Era Mechanical Service | 02/08/2017 |
| BIS | — | ISSUED | W.J. Regan & Company | 08/11/2016 |
| BIS | SP | ISSUED | New Era Mechanical Service | 11/24/2015 |
| BIS | PL | ISSUED | Sun Mechanical | 11/24/2015 |
| BIS | OT | ISSUED | W.J. Regan & Company | 10/14/2015 |
| BIS | MH | ISSUED | W.J. Regan & Company | 10/14/2015 |
| BIS | OT | ISSUED | W.J. Regan & Company | 10/14/2015 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/21/2025 | Complete | Nash Electric Services | — |
| 07/24/2018 | Complete | Dynamic Electric System | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/27/2026 | Fire-Resistant Penetrations and Joints | Jacky Philibert | special |
| 08/27/2026 | Maintenance information | Jacky Philibert | energy_progress |
| 08/27/2026 | Shutoff dampers | Jacky Philibert | energy_progress |
| 08/27/2026 | Exterior lighting power | Jacky Philibert | energy_progress |
| 08/27/2026 | HVAC-R and service water heating system controls | Jacky Philibert | energy_progress |
| 08/27/2026 | Duct leakage testing, insulation and design | Jacky Philibert | energy_progress |
| 08/27/2026 | Post-installed Anchors | Jacky Philibert | special |
| 08/27/2026 | Energy Code Compliance Inspections | Jacky Philibert | progress |
| 08/27/2026 | HVAC-R and service water piping design and insulation | Jacky Philibert | energy_progress |
| 08/27/2026 | HVAC-R and service water heating equipment | Jacky Philibert | energy_progress |
| 08/27/2026 | Interior lighting power | Jacky Philibert | energy_progress |
| 08/27/2026 | Lighting controls | Jacky Philibert | energy_progress |
| 07/23/2026 | Mechanical Systems | Jacky Philibert | special |
| 07/23/2026 | Final | Jacky Philibert | progress |
| 07/23/2026 | Sprinkler Systems | Jacky Philibert | special |
| 07/21/2026 | Fire-Resistant Penetrations and Joints | Jacky Philibert | special |
| 07/21/2026 | Sprayed fire-resistant materials | Jacky Philibert | special |
| 06/08/2026 | Final | Jacky Philibert | progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| St. John's University | Education | — | Project Q01165595 Project Q01190661 |