| Owner | Filings | Most Recent |
|---|---|---|
| Dasny | 92 | 07/08/2026 |
| Dormitory Authority of the State | 33 | 03/21/2026 |
| Skanska | 1 | 03/21/2026 |
| CUNY | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Michielli & Wyetzner Architects | 1 | 10/19/2026 |
| Genesys Engineering | 4 | 05/21/2025 |
| Ramboll | 2 | 05/15/2025 |
| Ahuja Partnership Architects | 2 | 11/30/2022 |
| Silman | 2 | 11/30/2022 |
| Elemental Architecture | 1 | 09/07/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| Municipal Building Consultants | 8 | 03/21/2026 |
| Nyccode | 4 | 03/21/2026 |
| Stacie Scorcia Company | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Aks International | General Contractor | 21 | 07/08/2026 |
| Dynamic US | General Contractor | 4 | 07/08/2026 |
| Skanska USA Building | General Contractor | 4 | 03/22/2026 |
| Kleinberg Electric | Electrical | 2 | 03/21/2026 |
| Gottlieb Electric | Electrical | 1 | 03/22/2026 |
| Eastern Plumbing & Mechanical Contracting | Plumbing | 1 | 07/08/2026 |
| Sage Electrical Contracting | Electrical | 1 | 03/21/2026 |
| Wilson Dennis | Electrical | 1 | 03/21/2026 |
| Sirina Fire Protection | Plumbing | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Tectonic Engineering Cons | 106 | 2 | 05/15/2025 |
| Future Tech Consultants O | 589 | 6 | 02/14/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | Eastern Plumbing & Mechanical Contracting | 11/03/2025 |
| DOB NOW | Structural | Signed-off | Dynamic US | 10/17/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | Aks International | 09/18/2025 |
| DOB NOW | Structural | Permit Issued | Aks International | 09/18/2025 |
| DOB NOW | General Construction | Permit Issued | Aks International | 09/17/2025 |
| DOB NOW | Structural | Permit Issued | Aks International | 07/18/2024 |
| DOB NOW | General Construction | Permit Issued | Aks International | 07/18/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | Aks International | 07/18/2024 |
| DOB NOW | General Construction | Permit Issued | Aks International | 03/18/2024 |
| DOB NOW | Structural | Permit Issued | Aks International | 03/18/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | Aks International | 03/18/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | Aks International | 12/07/2023 |
| DOB NOW | Structural | Permit Issued | Aks International | 12/07/2023 |
| DOB NOW | General Construction | Permit Issued | Aks International | 12/06/2023 |
| DOB NOW | Mechanical Systems | Signed-off | Dynamic US | 09/11/2023 |
| DOB NOW | Mechanical Systems | Signed-off | Dynamic US | 01/30/2023 |
| DOB NOW | Mechanical Systems | Permit Issued | Aks International | 12/07/2022 |
| DOB NOW | Structural | Permit Issued | Aks International | 12/02/2022 |
| DOB NOW | General Construction | Permit Issued | Aks International | 12/02/2022 |
| BIS | OT | ISSUED | Pro Con Group | 06/24/2022 |
| BIS | MH | ISSUED | Pro Con Group | 06/24/2022 |
| BIS | MH | ISSUED | Pro Con Group | 08/13/2021 |
| BIS | OT | ISSUED | Pro Con Group | 08/13/2021 |
| BIS | SP | ISSUED | Sirina Fire Protection | 11/24/2020 |
| BIS | MH | ISSUED | Pro Con Group | 06/29/2020 |
| BIS | OT | ISSUED | Pro Con Group | 06/29/2020 |
| BIS | SP | ISSUED | Sirina Fire Protection | 12/02/2019 |
| BIS | PL | ISSUED | Clean Tech Mechanical | 11/26/2019 |
| BIS | MH | ISSUED | Pro Con Group | 08/20/2019 |
| BIS | MH | ISSUED | Hellman Construction Co | 01/18/2019 |
| BIS | OT | ISSUED | Hellman Construction Co | 01/18/2019 |
| BIS | PL | ISSUED | Almar Plumbing & Heating | 12/06/2018 |
| BIS | OT | ISSUED | Pro Con Group | 06/27/2018 |
| BIS | MH | ISSUED | Pro Con Group | 06/22/2018 |
| BIS | SP | ISSUED | Sirina Fire Protection | 04/18/2018 |
| BIS | OT | ISSUED | Pro Con Group | 03/30/2018 |
| BIS | MH | ISSUED | Pro Con Group | 03/30/2018 |
| BIS | MH | ISSUED | Hellman Construction Co | 01/17/2018 |
| BIS | OT | ISSUED | Hellman Construction Co | 01/16/2018 |
| BIS | OT | ISSUED | Hellman Construction Co | 12/28/2017 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/21/2025 | Signed-off | Eastern Plumbing & Mechanical Contracting | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/09/2026 | Permit Issued | DVM Electrical Services | General Wiring |
| 06/09/2026 | Permit Issued | DVM Electrical Services | General Wiring |
| 12/31/2025 | Complete | Kleinberg Electric | General Wiring |
| 12/31/2019 | Complete | Gottlieb Electric | General Wiring |
| 11/06/2019 | Permit Issued | Everest Electric | General Wiring |
| 10/25/2019 | Complete | A.T.J. Electrical Co | — |
| 02/20/2019 | Complete | Gottlieb Electric | General Wiring |
| 01/09/2019 | Complete | Gottlieb Electric | General Wiring |
| 02/28/2018 | Complete | J.H. Electric of New York | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/19/2026 | — | — | 1 scope_items |
| 05/15/2025 | Signed-off | Dynamic US | Steel |
| 11/30/2022 | Permit Issued | Aks International | Steel |
| 09/07/2021 | — | — | Concrete |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/01/2026 | Structural Steel - High Strength Bolting | — | special |
| 10/01/2026 | Structural Steel - Welding | — | special |
| 10/01/2026 | Concrete - Cast-In-Place | — | special |
| 09/29/2026 | Final | — | progress |
| 05/05/2025 | Structural Steel - Details | GEORGE GHEBRYAL | special |
| 05/05/2025 | Structural Steel - Welding | GEORGE GHEBRYAL | special |
| 05/01/2025 | Final | GEORGE GHEBRYAL | progress |
| 03/11/2025 | Final | Firas Karkar | progress |
| 03/11/2025 | Energy Code Compliance Inspections | Stephen Marchese | progress |
| 03/11/2025 | HVAC-R and service water heating system controls | Stephen Marchese | energy_progress |
| 03/11/2025 | Maintenance information | Stephen Marchese | energy_progress |
| 03/11/2025 | HVAC-R and service water piping design and insulation | Stephen Marchese | energy_progress |
| 03/11/2025 | Mechanical Systems | MARISA HARTE | special |
| 03/11/2025 | Post-installed Anchors | MARISA HARTE | special |
| 03/11/2025 | Fire-Resistant Penetrations and Joints | MARISA HARTE | special |
| 11/06/2024 | Mechanical Systems | MARISA HARTE | special |
| 11/06/2024 | Fire-Resistant Penetrations and Joints | MARISA HARTE | special |
| 11/06/2024 | Post-installed Anchors | MARISA HARTE | special |
| 11/06/2024 | Energy Code Compliance Inspections | Stephen Marchese | progress |
| 11/06/2024 | Final | Joel Fisch | progress |
| 11/06/2024 | HVAC-R and service water piping design and insulation | Stephen Marchese | energy_progress |
| 11/06/2024 | HVAC-R and service water heating system controls | Stephen Marchese | energy_progress |
| 11/06/2024 | Maintenance information | Stephen Marchese | energy_progress |
| 12/02/2022 | Final | Joseph Tortorella | progress |
| 12/02/2022 | Structural Steel - High Strength Bolting | MARISA HARTE | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| The City College of New York | Education | Floor 1 | Project M01138289 Project M00513037 |
| CUNY Advanced Science | Laboratory | Floor 1 | Project M01219593 Project M00770710 Project M00770741 Project M00770757 Project M00672664 |