← Back
BuildNYC
Office with commercial, 7-19 stories
850 7TH AVENUE
MANHATTAN · BIN 1024854
💬 Discuss this project
1910Year Built
12.5Stories
O6Building Class
C6-6Zoning
78,750 sfGross Floor Area
50Units
LL97 Covered8 Active Violations 1 unresolved · 7 paperwork only 4 likely answered 4 old, status unconfirmed ▸FISP: UNSAFE
Office with commercial, 7-19 stories · Owner of record: Texwood Investment · 7,500 sf lot · 10.5 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentCivilGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
Whole building & multi-floor projectsTexwood Investment, Inc.Under Construction1 filing
RoofPlumbing work and interior renovations, 1st floor commercial2p · 2 filings · 14 docs
Floor 5Under Construction1 filing · 2 docs
Floor 4Under Construction1 filing · 2 docs
Floor 3Under Construction1 filing · 2 docs
Floor 2Boulevard Retail LLC3p · 2 filings · 14 docs
Floor 1Boulevard Retail LLCUnder Construction5p · 8 filings · 14 docs
CellarBoulevard Retail LLCUnder Construction11p · 9 filings · 14 docs
Site & exteriorBetamax hoist installationUnder Construction8 filings · 19 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Texwood Investment7303/22/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Arcometric Design403/21/2026
AE Design Solution803/21/2026
Millennium Designs of New York203/21/2026
Rand Engineering & Arch203/21/2026
Bonsignore Architects803/21/2026
Sotir Associates103/21/2026
GC Engineering & Associates203/21/2026
Expediting103/21/2026
Millennium Designs203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Andamio ScaffoldingScaffold1407/08/2026
Preserv BLD Restoration ManagementGeneral Contractor404/09/2026
Wesbuilt Construction ManGeneral Contractor307/08/2026
Kaj NY ConstructionScaffold303/21/2026
JT Magen & CompanyGeneral Contractor307/08/2026
Mill Brook Fire ProtectionFire Protection207/08/2026
Busko RealtyGeneral Contractor203/21/2026
Kings Group NYScaffold207/08/2026
Preserv BLD Restoration ManagementScaffold207/10/2026
A + SprinklerFire Protection209/16/2026
Economy P & H CoPlumbing107/08/2026
Katan P & HPlumbing107/08/2026
Ashland PlumbingPlumbing107/08/2026
Corzo Electl SystemsElectrical103/22/2026
W.J. Regan & CompanyGeneral Contractor107/08/2026
Vai ConstructionGeneral Contractor107/08/2026
R.j.electrical ContractorElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Leo Y Lee Associates2481908/06/2026
Century Testing & Consulting4081105/13/2024
SCA Code and Planning6599305/13/2024
Rand Engineering & Architects266105/09/2024
MJ Engineering & Design5546101/26/2024
Sotir Associates7473207/26/2023
Bonsignore Architects1109306/17/2022
Building Lifecycle
All (230)Filed (36)Permit Issued (38)Signed Off (10)Facade (FISP) (19)Violation (60)Inspection (11)Objection (26)Special Inspection (30)
09/21/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
09/16/2026
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
09/15/2026
Permit issued — Sprinklers
M00922395-I1-EW-SP
09/02/2026
Inspection — Pass-Final SP - Up to 3 Requested Floors
Pass
View inspection ↗
08/17/2026
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
Leo Lee
08/17/2026
Special inspection requirement — Post-installed Anchors
Leo Lee
08/14/2026
Objection resolved — Resolved
08/13/2026
Objection raised — Other
08/07/2026
Filed — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
M01412662-P1
08/06/2026
Filed — Alteration
Installation of suspended scaffold for facade work and/or inspection. Amend #2, changer in tieback and lifeline location
M01082108-P7
07/09/2026
Permit issued — Protection and Mechanical Methods
M01416268-I1-PMM
07/07/2026
Objection resolved — Addressed
07/06/2026
Objection raised — Other
06/26/2026
Filed — Alteration
Installation of suspended scaffold for facade work and/or inspection. Amend #2, changer in tieback and lifeline location
M01082108-P6
06/23/2026
Filed — Alteration
INSTALLATION OF TEMPORARY BETA MAX HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01416268-I1
06/16/2026
Signed off — Alteration
M01133013-I1
06/09/2026
Filed — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
M01412662-I1
06/09/2026
Permit issued — Supported Scaffold
M01412662-I1-SF
05/05/2026
Filed — Alteration
Installation of suspended scaffold for facade work and/or inspection. Amend #2, changer in tieback and lifeline location
M01082108-P5
05/05/2026
Special inspection requirement — Post-installed Anchors
Leo Lee
05/05/2026
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
Leo Lee
04/28/2026
Permit issued — Protection and Mechanical Methods
M01389056-I1-PMM
04/22/2026
Filed — Alteration
M01389056-I1
04/20/2026
Filed — Alteration
Installation of suspended scaffold for facade work and/or inspection. Amend #2, changer in tieback and lifeline location
M01082108-P4
03/20/2026
Objection raised — Other
03/20/2026
Objection resolved — Addressed
03/19/2026
Filed — Alteration
Installation of suspended scaffold for facade work and/or inspection. Amend #2, changer in tieback and lifeline location
M01082108-P3
03/19/2026
Special inspection requirement — Post-installed Anchors
Leo Lee
03/19/2026
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
Leo Lee
03/10/2026
Filed — Alteration
Installation of suspended scaffold for facade work and/or inspection. Amend #2, changer in tieback and lifeline location
M01082108-P2
03/10/2026
Special inspection requirement — Post-installed Anchors
Leo Lee
03/10/2026
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
Leo Lee
02/27/2026
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
02/05/2026
Permit issued — Suspended Scaffold
M01082108-I1-SC
02/04/2026
Permit issued — Construction Fence
M01174573-I1-FN
12/30/2025
Permit issued — General Construction
M00964686-I1-GC
10/27/2025
Permit issued — Supported Scaffold
M01133013-I1-SF
10/27/2025
Permit issued — Protection and Mechanical Methods
M01133015-I1-PMM
10/27/2025
Permit issued — Sidewalk Shed
M01133010-I1-SH
10/01/2025
Signed off — Alteration
INSTALLATION OF 300 PSF SIDEWALK SHED AS PER PLANS. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE 2014 CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M00753821-I1
08/25/2025
Violation issued (ECB, open)
Construction
08/01/2025
Permit issued — General Construction
M00964686-I1-GC
05/16/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
05/06/2025
Permit issued — Sprinklers
M01036463-S1-EW-SP
03/27/2025
Objection raised — Other
03/27/2025
Objection resolved — Addressed
03/26/2025
Filed — Alteration
Installation of suspended scaffold for facade work and/or inspection. Amend #2, changer in tieback and lifeline location
M01082108-P1
03/25/2025
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
Leo Lee
03/25/2025
Special inspection requirement — Post-installed Anchors
Leo Lee
03/13/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
03/13/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
03/13/2025
Inspection — Certified Sprinkler - SP - Roughing
Certified
View inspection ↗
02/22/2025
Filed — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
M01133010-P1
02/18/2025
Permit issued — Sprinklers
M01036463-S1-EW-SP
02/14/2025
Permit issued — Suspended Scaffold
M01082108-I1-SC
02/03/2025
Filed — Alteration
M01174573-I1
02/03/2025
Permit issued — Construction Fence
M01174573-I1-FN
12/04/2024
Permit issued — Suspended Scaffold
M01138427-I1-SC
12/01/2024
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
11/13/2024
Filed — Alteration
M01138427-I1
Latest 60 of 230 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSprinklersPermit IssuedA + Sprinkler09/15/2026
DOB NOWProtection and Mechanical MethodsPermit IssuedPreserv BLD Restoration Management07/09/2026
DOB NOWSupported ScaffoldPermit IssuedAndamio Scaffolding06/09/2026
DOB NOWProtection and Mechanical MethodsPermit IssuedPreserv BLD Restoration Management04/28/2026
DOB NOWSuspended ScaffoldPermit IssuedPreserv BLDNG RST Management I02/05/2026
DOB NOWConstruction FencePermit IssuedAndamio Scaffolding02/04/2026
DOB NOWGeneral ConstructionPermit IssuedPreserv BLD Restoration Management12/30/2025
DOB NOWSupported ScaffoldSigned-offAndamio Scaffolding10/27/2025
DOB NOWProtection and Mechanical MethodsPermit IssuedAndamio Scaffolding10/27/2025
DOB NOWSidewalk ShedPermit IssuedAndamio Scaffolding10/27/2025
DOB NOWGeneral ConstructionPermit IssuedPreserv BLD Restoration Management08/01/2025
DOB NOWSprinklersSigned-offLeguci Piping & Heating05/06/2025
DOB NOWSprinklersSigned-offLeguci Piping & Heating02/18/2025
DOB NOWSuspended ScaffoldPermit IssuedPreserv BLDNG RST Management I02/14/2025
DOB NOWConstruction FencePermit IssuedAndamio Scaffolding02/03/2025
DOB NOWSuspended ScaffoldPermit IssuedPreserv Building Restoration12/04/2024
DOB NOWSidewalk ShedPermit IssuedAndamio Scaffolding10/30/2024
DOB NOWProtection and Mechanical MethodsPermit IssuedAndamio Scaffolding10/30/2024
DOB NOWSupported ScaffoldSigned-offAndamio Scaffolding10/30/2024
DOB NOWSprinklersPermit IssuedA + Sprinkler10/08/2024
DOB NOWGeneral ConstructionPermit IssuedPreserv BLD Restoration Management08/08/2024
DOB NOWSuspended ScaffoldPermit IssuedPreserv BLDNG RST Management I08/01/2024
DOB NOWSidewalk ShedSigned-offAndamio Scaffolding05/31/2024
DOB NOWGeneral ConstructionPermit IssuedVai Construction05/01/2024
DOB NOWSidewalk ShedSigned-offAndamio Scaffolding06/06/2023
DOB NOWPlumbingPermit IssuedKatan P & H02/07/2023
DOB NOWGeneral ConstructionSigned-offW.J. Regan & Company01/16/2023
DOB NOWMechanical SystemsSigned-offBusko Realty11/15/2022
DOB NOWMechanical SystemsSigned-offJT Magen & Company08/23/2022
DOB NOWPlumbingSigned-offAshland Plumbing07/05/2022
DOB NOWGeneral ConstructionSigned-offJT Magen & Company06/29/2022
DOB NOWSidewalk ShedSigned-offAndamio Scaffolding06/10/2022
DOB NOWMechanical SystemsSigned-offWesbuilt Construction Man03/19/2021
DOB NOWPlumbingSigned-offEconomy P & H Co01/26/2021
DOB NOWMechanical SystemsSigned-offWesbuilt Construction Man01/25/2021
DOB NOWSidewalk ShedSigned-offKings Group NY09/23/2019
DOB NOWSidewalk ShedPermit IssuedKaj NY Construction09/20/2019
DOB NOWSidewalk ShedSigned-offKings Group NY08/12/2019
BISOTISSUEDWesbuilt Construction Man03/18/2021
BISOTISSUEDWesbuilt Construction Man03/18/2021
+ 48 more permits on file
2 projects · most recent 05/13/2024
Heating and Air Conditioning Systems Associated Ducts and Piping Refrigeration Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
05/13/2024Permit IssuedVai ConstructionHeating and Air Conditioning Systems
Heat / Cool
Mitsubishi Electric Model: MXZ-4C36NA3 3 tons · Split System ×2
Model: MXZ-SM48NAM 4 tons · Split System ×2
07/26/2023Signed-offBusko RealtyAssociated Ducts and Piping, Heating and Air Conditioning Systems, Refrigeration Systems, Ventilation Systems
Heat / Cool
Fujitsu AOU45RLXFZ 45,000 BTU · Condensing Unit ×2
Ventilation
Greenheck CUBE-220-VGD7X 5,174 CFM · Exhaust Fan ×2
Refrigeration
Copeland XFAM-050Z-TFC-081 29,000 BTU · Refrigeration Unit ×4
XFAM-370Z-TFC-081 23,200 BTU · Refrigeration Unit ×2
Ducts & Piping
Greenheck N/A Ductwork ×1
1 project · most recent 05/13/2024
FiledStatusContractorScope
05/13/2024Signed-offLeguci Piping & Heating—
2 projects · most recent 05/13/2024
Water/Sanitary Gas
FiledStatusContractorScope
05/13/2024——Water/Sanitary
07/26/2023Permit IssuedKatan P & HGas, Water/Sanitary
8 projects · most recent 11/14/2023
General Wiring
FiledStatusContractorScope
11/14/2023CompleteKleinknecht Electric CoGeneral Wiring
06/28/2022CompleteRobert B. Samuels—
06/28/2022Permit IssuedBorowide Elect'l Contractors—
09/18/2020Permit IssuedCorzo Electl SystemsGeneral Wiring
06/17/2020Permit IssuedCentennial Elevator IndustriesGeneral Wiring
09/21/2019Permit IssuedRichard Neu—
09/12/2019Permit IssuedCorzo Electl SystemsGeneral Wiring
08/08/2019Permit IssuedRichard Neu—
2 projects · most recent 08/07/2026
Scaffold Sidewalk Shed
FiledStatusContractorScope
08/07/2026Permit IssuedAndamio ScaffoldingScaffold
02/22/2025Permit IssuedAndamio ScaffoldingSidewalk Shed
1 project · most recent 08/06/2026
Suspended Scaffold (SC)
FiledStatusContractorScope
08/06/2026Permit IssuedPreserv BLDNG RST Management ISuspended Scaffold (SC)
▾Field Inspections (DOB CAP) — 11
DateTypeResultReport
09/21/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
09/16/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
09/02/2026Pass-Final SP - Up to 3 Requested FloorsPassView ↗
05/16/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
03/13/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
03/13/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
03/13/2025Certified Sprinkler - SP - RoughingCertifiedView ↗
08/22/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/16/2023Certified Gas-Gas-Piping-RoughingCertifiedView ↗
02/17/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
08/23/2022Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 52
DateRequirementInspectorRole
08/17/2026Alternative Materials - OTCR Buildings Bulletin NumberLeo Leespecial
08/17/2026Post-installed AnchorsLeo Leespecial
05/05/2026Post-installed AnchorsLeo Leespecial
05/05/2026Alternative Materials - OTCR Buildings Bulletin NumberLeo Leespecial
03/19/2026Post-installed AnchorsLeo Leespecial
03/19/2026Alternative Materials - OTCR Buildings Bulletin NumberLeo Leespecial
03/10/2026Post-installed AnchorsLeo Leespecial
03/10/2026Alternative Materials - OTCR Buildings Bulletin NumberLeo Leespecial
03/25/2025Alternative Materials - OTCR Buildings Bulletin NumberLeo Leespecial
03/25/2025Post-installed AnchorsLeo Leespecial
11/06/2024Alternative Materials - OTCR Buildings Bulletin NumberLeo Leespecial
11/06/2024Post-installed AnchorsLeo Leespecial
06/10/2024Fire-Resistant Penetrations and JointsJOMO CHARLESspecial
06/10/2024Seismic Isolation SystemsALDO BRAVOspecial
05/09/2024Post-installed AnchorsJOMO CHARLESspecial
04/19/2024Energy Code Compliance InspectionsJOMO CHARLESprogress
04/17/2024Energy Code Compliance InspectionsJOMO CHARLESprogress
04/16/2024HVAC-R and service water piping design and insulationJOMO CHARLESenergy_progress
04/16/2024Sprinkler SystemsJOMO CHARLESspecial
04/16/2024Fire-Resistant Penetrations and JointsJOMO CHARLESspecial
04/16/2024Mechanical SystemsJOMO CHARLESspecial
04/16/2024FinalJOMO CHARLESprogress
04/16/2024HVAC-R and service water heating system controlsJOMO CHARLESenergy_progress
04/16/2024HVAC-R and service water heating equipmentJOMO CHARLESenergy_progress
04/16/2024Lighting controlsJOMO CHARLESenergy_progress
Latest 25 of 52.
▾Documents — 452 on file (BIS + DOB NOW)
▸Plans & Drawings36
▸DOB NOWPlans/Sketch32
09/02/2026M00663753-I1Request digital key ↗
09/02/2026M00663879-I1Request digital key ↗
09/02/2026M00663894-I1Request digital key ↗
Showing 3 of 32 on file for this type
▸DOB NOWPlans/Sketch - Sidewalk Shed2
09/05/2026M00206428-I1Request digital key ↗
09/05/2026M00230038-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Mechanical Systems1
09/04/2026M00438459-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing1
08/15/2026M00438396-I1Request digital key ↗
▸Applications & Permits81
▸BISPLAN / WORK APPROVAL APPLICATION45
02/07/2022122991432Open ↗
01/26/2022122991432Open ↗
01/24/2022122991432Open ↗
Showing 3 of 45 on file for this type
▸BISWORK PERMIT APPLICATION36
03/10/2021140988858Open ↗
03/20/2020123049352Open ↗
07/11/2019123049352Open ↗
Showing 3 of 36 on file for this type
▸Seals & Professional Certifications110
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION27
12/11/2019123049352Open ↗
12/11/2019123049352Open ↗
04/04/2018122991405Open ↗
Showing 3 of 27 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature25
09/05/2026M00206428-I1Open ↗
09/05/2026M00230038-I1Open ↗
09/04/2026M00438396-I1Open ↗
Showing 3 of 25 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature22
09/23/2026M01036463-S1Open ↗
09/23/2026M01036463-S1Open ↗
09/23/2026M01036463-S1Open ↗
Showing 3 of 22 on file for this type
▸DOB NOWProgress Inspector Seal & Signature14
09/23/2026M01036463-S1Open ↗
09/18/2026M00964686-I1Open ↗
09/18/2026M00964686-I1Open ↗
Showing 3 of 14 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST8
12/26/2013121816464Open ↗
11/05/2013121816464Open ↗
Showing 2 of 8 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT3
11/02/2016140571165Open ↗
12/30/2015140444856Open ↗
11/05/2013121816464Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION2
11/02/2016140571165Open ↗
12/30/2015140444856Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY2
11/02/2016140571165Open ↗
12/30/2015140444856Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
12/22/2020140988858Open ↗
▸Trade Schedules & Equipment23
▸BISSCHEDULE B - PLUMBING9
06/16/2020123049352Open ↗
06/16/2020123049352Open ↗
05/11/2020123049352Open ↗
Showing 3 of 9 on file for this type
▸BISSELF-CERT PLUMBING NOTICE4
07/12/2012120996271Open ↗
Showing 1 of 4 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE3
04/04/2018122991405Open ↗
11/13/2017123049352Open ↗
11/13/2017123049352Open ↗
▸BISEQUIPMENT USE PERMITS2
01/03/2014121816464Open ↗
08/21/2012120996271Open ↗
▸BISFA - FDNY APPROVAL : FD-FAA2
10/25/2022122991432Open ↗
02/02/2015121574386Open ↗
▸BISEQUIPMENT USE APPLICATION-PERMIT2
08/20/2012120996271Open ↗
01/03/2014121816464Open ↗
▸BISPLUMBING - SUPPORTING DOCUMENTATION1
07/12/2012120996271Open ↗
▸Safety & Tenant Protection3
▸BISSTREET TREE CHECKLIST2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWTenant Protection Plan1
09/05/2026M00206428-I1Open ↗
▸Environmental & Asbestos32
▸DOB NOWDEP ACP-5: Asbestos Assessment Report13
09/02/2026M00663753-I1Open ↗
09/02/2026M00663894-I1Open ↗
08/29/2026M08023634-I1Open ↗
Showing 3 of 13 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)9
01/06/2021140988858Open ↗
04/04/2018122991405Open ↗
04/04/2018122989622Open ↗
Showing 3 of 9 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER3
06/08/2012121102298Open ↗
Showing 1 of 3 on file for this type
▸Energy Compliance27
▸BISAS-BUILT ENERGY ANALYSIS6
07/13/2021140988858Open ↗
06/28/2021123049352Open ↗
07/27/2016140444856Open ↗
Showing 3 of 6 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS6
04/04/2018122991405Open ↗
04/04/2018122991405Open ↗
04/04/2018122991405Open ↗
Showing 3 of 6 on file for this type
▸BISTECHNICAL REPORT: ENERGY5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY4
07/13/2021140988858Open ↗
01/28/2021140988858Open ↗
12/22/2020140988858Open ↗
Showing 3 of 4 on file for this type
▸BISNYCECC ANALYSIS2
01/28/2021140988858Open ↗
12/30/2015140444856Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
12/30/2015140444856Open ↗
▸BISTR8: Energy Code Progress Inspections1
07/02/2013120772832Open ↗
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING1
11/02/2016140571165Open ↗
▸DOB NOWPreliminary Commissioning Report Certification1
08/13/2026M08023634-I1Open ↗
▸Inspections & Test Reports10
▸BISTECHNICAL REPORT: RESPONSIBILITY7
07/13/2021140988858Open ↗
06/28/2021123049352Open ↗
03/26/2021123049352Open ↗
Showing 3 of 7 on file for this type
▸BISINSPECTION REPORT - SUPPORTING DOCUMENTATION1
03/19/2018140571165Open ↗
▸BISHYDRAULIC FLOW CALCULATIONS1
01/23/2018123049352Open ↗
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER1
01/23/2018123049352Open ↗
▸Approvals, Objections & Sign-offs28
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST12
10/28/2022122991432Open ↗
03/03/2022122989622Open ↗
07/13/2021140988858Open ↗
Showing 3 of 12 on file for this type
▸BISADMINISTRATIVE OBJECTIONS12
03/26/2013121574386Open ↗
06/14/2012121096802Open ↗
06/08/2012121102298Open ↗
Showing 3 of 12 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION3
02/01/2013120739371Open ↗
09/06/2012120996271Open ↗
Showing 2 of 3 on file for this type
▸DOB NOWDEP Variance (V5) letter1
08/13/2026M00964686-I1Open ↗
▸Cost, Insurance & Ownership40
▸BISCOST AFFIDAVIT35
07/13/2021140988858Open ↗
06/28/2021123049352Open ↗
01/28/2021140988858Open ↗
Showing 3 of 35 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW32
10/27/2022122991432Open ↗
03/03/2022122989622Open ↗
▸BISINSURANCE: WORKERS' COMPENSATION1
10/27/2022122991432Open ↗
▸BISINSURANCE: DISABILITY1
10/27/2022122991432Open ↗
▸BISINSURANCE: LIABILITY1
10/27/2022122991432Open ↗
▸Filing & Intake Forms36
▸BISEFILING COVER SHEET21
04/04/2018122991405Open ↗
04/04/2018122991405Open ↗
04/04/2018122989622Open ↗
Showing 3 of 21 on file for this type
▸BISADDITIONAL INFORMATION9
02/23/2021140988858Open ↗
06/16/2020123049352Open ↗
06/16/2020123049352Open ↗
Showing 3 of 9 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET3
12/22/2020140988858Open ↗
11/02/2016140571165Open ↗
12/30/2015140444856Open ↗
▸BISBOROUGH INTAKE FORM3
06/14/2019123049352Open ↗
06/14/2019123049352Open ↗
03/19/2018140571165Open ↗
▸Other Documents26
▸DOB NOWManufacturer's Specifications10
08/17/2026M01082108-I1Open ↗
08/17/2026M01082108-P4Open ↗
08/17/2026M01082108-P5Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWCalculations10
08/17/2026M01082108-I1Open ↗
08/17/2026M01082108-P5Open ↗
08/17/2026M01082108-P3Open ↗
Showing 3 of 10 on file for this type
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION6
01/23/2018123049352Open ↗
06/08/2012121102298Open ↗
Showing 2 of 6 on file for this type