← Back
BuildNYC
Elevator cooperative
870 5TH AVENUE
MANHATTAN · BIN 1041250
💬 Discuss this project
1949Year Built
20Stories
D4Building Class
R10Zoning
235,448 sfGross Floor Area
102Units
LL97 CoveredRent Stabilized182 Active Violations 171 unresolved · 11 paperwork only ▸FISP: SAFE
Elevator cooperative · Owner of record: 870 Fifth Ave · 17,750 sf lot · 13.26 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingEquipmentCivilGeneralOther
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofDouglas Elliman Property Management2p · 2 filings · 20 docs
PenthouseUnit PH, Unit PH9, Unit PHC19p · 2 filings · 20 docs
Floor 201p · 1 filing · 15 docs
Floor 19
Floor 18Unit 18A, Unit 18CUnder Construction14p · 2 filings · 20 docs
Floor 17Unit 17A2 filings · 9 docs
Floor 16
Floor 15Unit 15A17p · 3 filings · 20 docs
Floor 14Unit 14E22p · 5 filings · 20 docs
Floor 13Unit 14E34p · 5 filings · 20 docs
Floor 12
Floor 11Unit 11A, Unit 11DUnder Construction42p · 2 filings · 20 docs
Floor 10Unit 10H31p · 3 filings · 20 docs
Floor 9Unit 9B, Unit 9E8p · 2 filings · 20 docs
Floor 8Unit 8A, Unit 8B, Unit 8D20p · 3 filings · 20 docs
Floor 7Unit 7A12p · 1 filing · 20 docs
Floor 6Unit 6A1 filing · 8 docs
Floor 5
Floor 4Unit 4A, Unit 4E, Unit 4HUnder Construction40p · 4 filings · 20 docs
Floor 3Unit 3H15p · 1 filing · 20 docs
Floor 2
Floor 1Install split AC system for lobby area4p · 1 filing · 4 docs
Cellar870 5 Ave Owners CORP1 filing · 5 docs
Sub-BasementUnder Construction6p · 1 filing · 20 docs
Site & exteriorDouglas Elliman Property Management45p · 8 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
870 Fifth17603/22/2026
870 5th Avaenue4003/21/2026
870 Fifith Avenue803/21/2026
870 5 Ave Owners503/22/2026
870 5 AVE503/21/2026
Pres403/21/2026
▾Filing Representatives (Expediters)
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Homeline ConstructionGeneral Contractor1207/08/2026
Platinum Services NYScaffold1007/08/2026
Hatchet WorksGeneral Contractor807/08/2026
Wilfrido & Sons ConstructionGeneral Contractor707/08/2026
Freedom GSGeneral Contractor607/08/2026
Dartom ConstructionGeneral Contractor507/08/2026
Dartom Cabinetryspecialty_contractor404/09/2026
Garrity ContractingGeneral Contractor407/08/2026
Clark ConstructionGeneral Contractor409/01/2026
A.M.NPlumbing407/08/2026
FanukaGeneral Contractor308/13/2026
The Metro GroupGeneral Contractor303/21/2026
Donato PlumbingPlumbing308/26/2026
Demo ContractorsGeneral Contractor303/21/2026
Yates Exterior Restorationspecialty_contractor304/09/2026
Polyphase ElectricElectrical203/21/2026
Eric & NG ElectricalElectrical203/22/2026
Glendale Electl ContngElectrical203/22/2026
Everest ScaffoldingScaffold203/21/2026
Accurate MechanicalPlumbing210/06/2026
Central Construction ManagementGeneral Contractor204/09/2026
Lit GroupGeneral Contractor207/08/2026
Coppermine Construction *General Contractor208/08/2026
Riconda MaintenanceGeneral Contractor204/09/2026
Cottam Heating & Air Conditspecialty_contractor203/21/2026
Einsteins Plumbing & HeatingPlumbing107/08/2026
Hydrokinetic Plumbing & Heating IPlumbing107/08/2026
Orbit Plumbing & HeatingPlumbing107/08/2026
Pal-Mar Plumbing & HeatingPlumbing107/05/2026
P.S.I. MechanicalPlumbing106/14/2026
Schimenti Construction CoPlumbing109/13/2026
S&H PlumbingPlumbing107/08/2026
Simple Choice Plumbing and HTPlumbing107/08/2026
Smart Plumbing & HeatingPlumbing107/08/2026
Top Dog Plumbing & HeatingPlumbing107/08/2026
WaterfirePlumbing107/08/2026
Wawel Plumbing and HeatingPlumbing107/08/2026
K & G Electric CoElectrical103/21/2026
Bobtek ElectricalElectrical103/21/2026
Moskowitz StuartElectrical103/21/2026
Madison ElectricElectrical103/21/2026
R-2 ElectricElectrical103/22/2026
M & R Electrical Contg and RepElectrical103/21/2026
Spectrum ElectricElectrical103/21/2026
Matros Automated ElectricalElectrical103/21/2026
Tactical ElectricElectrical103/22/2026
The Metro Group ElectricElectrical103/22/2026
TM Select ElectricElectrical103/22/2026
Defalco Associates, LLC/Electrical103/21/2026
Xela ElectricalElectrical103/22/2026
B & H Restorationspecialty_contractor107/08/2026
Creative Concepts First IGeneral Contractor107/08/2026
Daa Construction GroupGeneral Contractor104/09/2026
John Petrocelli ConstructionGeneral Contractor104/09/2026
PH Custom Home ImprovemenGeneral Contractor104/09/2026
Renovation PartnersGeneral Contractor107/08/2026
Sage Construction ServiceGeneral Contractor104/09/2026
Yates Restoration GroupGeneral Contractor104/09/2026
Andamio ScaffoldingScaffold107/08/2026
Aqueduct MechanicalPlumbing107/08/2026
Demar MechanicalPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Jack Green Associates422707/23/2026
Assure Professional Engineering6962803/27/2026
Eugene Khananov Architect2816311/24/2025
GM Huang Architecture PLL1398211/17/2025
Crosscheck Inspection Services544310/07/2025
Davis Architecture Studio8513407/08/2025
C.M. Testing Laboratory1352407/08/2025
O'Rourke Engineering5873306/05/2025
Cowley Engineering186402/25/2025
Project Tactical Solution5859501/28/2025
Integrity Consulting Service666401/13/2025
Robert Schultz2457112/06/2024
Bazini Engineering1808108/15/2023
Constant and Brown Engineering7565603/15/2023
RHL Engineering712211/11/2022
D'Antonio Consulting Engineering931110/20/2022
Enthink Engineers6247108/16/2022
Berg and Forster Architects3118108/04/2022
Richard Kreshtool Architects2867207/21/2022
Catalpa Special Inspectio2004104/29/2022
CES Engineering1277203/24/2022
Michael Zenreich Architects1724211/08/2021
Robert F. Germain Jr. PE5100103/04/2020
Abraham Bloch Architect3674112/13/2019
Building Lifecycle
All (300)Filed (54)Permit Issued (49)Signed Off (15)Facade (FISP) (3)Violation (44)Inspection (25)Objection (80)Special Inspection (30)
10/16/2026
Filed — Alteration
Filing for Non-structural Demolition; Removal & disposal of interior apartment unit. No change in use, egress or occupancy.
M01147526-P2
10/05/2026
Permit issued — Plumbing
M01232154-S1-PL
09/11/2026
Permit issued — Plumbing
M01421113-S1-PL
08/31/2026
Permit issued — General Construction
M00944762-I1-GC
08/12/2026
Permit issued — General Construction
M01147526-I1-GC
08/12/2026
Permit issued — Plumbing
M01147526-S2-PL
08/10/2026
Signed off — Alteration
REPLACEMENT OF ONE (1) PTAC UNIT AT EXISTING SLEEVE IN FACADE, AND ONE (1) PTAC UNIT AT NEW FACADE OPENING ARE REAR.
M01023482-I1
08/07/2026
Permit issued — General Construction
M01421113-I1-GC
08/05/2026
Permit issued — Mechanical Systems
M01421113-S2-MS
08/03/2026
Objection resolved — Addressed
07/28/2026
Objection raised — Scope
07/23/2026
Filed — Alteration
file plumbing work as per plans.
M01421113-S1
07/22/2026
Filed — Alteration
file plumbing work as per plans.
M01421113-I1
07/22/2026
Filed — Alteration
file plumbing work as per plans.
M01421113-S2
07/22/2026
Special inspection requirement — HVAC-R and service water heating equipment
LAWRENCE GREEN
07/22/2026
Special inspection requirement — HVAC-R and service water heating system controls
LAWRENCE GREEN
07/15/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
LAWRENCE GREEN
07/15/2026
Special inspection requirement — Energy Code Compliance Inspections
LAWRENCE GREEN
07/15/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
LAWRENCE GREEN
07/08/2026
Filed — Alteration
REPLACE MECHANICAL EQUIPMENT AT ROOF LEVEL
M01329046-P1
07/08/2026
Signed off — Alteration
REPLACEMENT OF ONE (1) PTAC UNIT AT EXISTING SLEEVE IN FACADE, AND ONE (1) PTAC UNIT AT NEW FACADE OPENING ARE REAR.
M01023482-S2
07/02/2026
Objection resolved — Addressed
06/30/2026
Objection resolved — Addressed
06/30/2026
Objection resolved — Addressed
06/26/2026
Signed off — Alteration
REPLACEMENT OF ONE (1) PTAC UNIT AT EXISTING SLEEVE IN FACADE, AND ONE (1) PTAC UNIT AT NEW FACADE OPENING ARE REAR.
M01023482-S1
06/26/2026
Objection raised — Admin
06/26/2026
Special inspection requirement — Final
06/26/2026
Special inspection requirement — Heating Systems
06/26/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
06/26/2026
Special inspection requirement — Mechanical Systems
06/26/2026
Special inspection requirement — Exhaust and Vent Systems in Plenums and Ducts
06/26/2026
Special inspection requirement — Tenant Protection Plan Compliance
06/26/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
LAWRENCE GREEN
06/25/2026
Objection raised — Fire_Protection
06/25/2026
Objection raised — Fire_Protection
06/23/2026
Filed — Alteration
Work to be performed at existing terrace/greenhouse as per plans.
M01223447-P1
06/23/2026
Special inspection requirement — Mechanical Systems
LAWRENCE GREEN
06/23/2026
Special inspection requirement — Final
LAWRENCE GREEN
06/22/2026
Filed — Alteration
Mechanical work to be performed in existing unit #1A-1B on the basement level. Initial general construction &subsequent plumbing application to be filed. All in accordance with submitted plans. No changes to use, egress or occupancy under this application
M00944762-P3
06/22/2026
Filed — Alteration
Mechanical work to be performed in existing unit #1A-1B on the basement level. Initial general construction &subsequent plumbing application to be filed. All in accordance with submitted plans. No changes to use, egress or occupancy under this application
M00944762-P1
06/15/2026
Signed off — Alteration
Interior work at existing apt # 8A on the 8th floor. Work include non-structural demolition, minor partitions work and associated finishes all as per plans submitted. No change of use, egress or occupancy.
M01258630-I1
05/21/2026
Permit issued — General Construction
M01023482-S2-GC
05/21/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
05/18/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
05/12/2026
Special inspection requirement — Final
GUNJAN KHANDWALA
05/12/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
GUNJAN KHANDWALA
05/12/2026
Special inspection requirement — Mechanical Systems
GUNJAN KHANDWALA
05/07/2026
Signed off — Alteration
Plumbing work in conjunction with interior renovation at apartment 4A. No change in use, egress, or occupancy.
M01048104-S2
05/07/2026
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
05/07/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
05/07/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
LAWRENCE GREEN
05/05/2026
Signed off — Alteration
Interior work at existing apt # 8A on the 8th floor. Work include non-structural demolition, minor partitions work and associated finishes all as per plans submitted. No change of use, egress or occupancy.
M01258630-S1
05/05/2026
Permit issued — General Construction
M01048104-S2-GC-CX
05/01/2026
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
05/01/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
04/29/2026
Violation issued (HPD, closed)
A
04/29/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
04/27/2026
Objection resolved — Addressed
04/24/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
04/24/2026
Objection resolved — Resolved
Latest 60 of 300 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedAccurate Mechanical10/05/2026
DOB NOWPlumbingPermit IssuedPipeworks NYC09/11/2026
DOB NOWGeneral ConstructionPermit IssuedClark Construction08/31/2026
DOB NOWGeneral ConstructionPermit IssuedFanuka08/12/2026
DOB NOWPlumbingPermit IssuedDonato Plumbing08/12/2026
DOB NOWGeneral ConstructionPermit IssuedCoppermine Construction *08/07/2026
DOB NOWMechanical SystemsPermit IssuedCoppermine Construction *08/05/2026
DOB NOWGeneral ConstructionSigned-offB & H Restoration05/21/2026
DOB NOWGeneral ConstructionSigned-offHomeline Construction05/05/2026
DOB NOWPlumbingPermit IssuedPal-Mar Plumbing & Heating03/23/2026
DOB NOWPlumbingPermit IssuedDonato Plumbing03/20/2026
DOB NOWGeneral ConstructionPermit IssuedLit Group03/19/2026
DOB NOWGeneral ConstructionPermit IssuedDaa Construction Group03/04/2026
DOB NOWMechanical SystemsPermit IssuedLit Group02/06/2026
DOB NOWPlumbingPermit IssuedP.S.I. Mechanical01/25/2026
DOB NOWGeneral ConstructionSigned-offDartom Cabinetry01/09/2026
DOB NOWSuspended ScaffoldPermit IssuedCentral Construction Management12/19/2025
DOB NOWSupported ScaffoldSigned-offPlatinum Services NY11/03/2025
DOB NOWMechanical SystemsPermit IssuedClark Construction10/29/2025
DOB NOWPlumbingSigned-offSmart Plumbing & Heating10/28/2025
DOB NOWPlumbingPermit IssuedWawel Plumbing and Heating10/28/2025
DOB NOWMechanical SystemsPermit IssuedFreedom GS10/27/2025
DOB NOWGeneral ConstructionPermit IssuedFreedom GS10/27/2025
DOB NOWGeneral ConstructionPermit IssuedFreedom GS10/27/2025
DOB NOWStructuralSigned-offYates Exterior Restoration10/24/2025
DOB NOWStructuralSigned-offCentral Construction Management10/23/2025
DOB NOWMechanical SystemsPermit IssuedFreedom GS10/21/2025
DOB NOWGeneral ConstructionPermit IssuedFreedom GS10/17/2025
DOB NOWGeneral ConstructionSigned-offRenovation Partners10/14/2025
DOB NOWGeneral ConstructionPermit IssuedSage Construction Service10/14/2025
DOB NOWPlumbingPermit IssuedAnthony Disabato10/09/2025
DOB NOWGeneral ConstructionPermit IssuedClark Construction09/30/2025
DOB NOWPlumbingPermit IssuedAqueduct Mechanical09/17/2025
DOB NOWGeneral ConstructionPermit IssuedJohn Petrocelli Construction08/28/2025
DOB NOWMechanical SystemsSigned-offFanuka08/28/2025
DOB NOWPlumbingSigned-offSimple Choice Plumbing and HT08/04/2025
DOB NOWPlumbingPermit IssuedDonato Plumbing07/22/2025
DOB NOWGeneral ConstructionSigned-offPH Custom Home Improvemen07/17/2025
DOB NOWGeneral ConstructionPermit IssuedFanuka07/17/2025
DOB NOWMechanical SystemsSigned-offCottam Heating Air Cond04/14/2025
+ 60 more permits on file
9 projects · most recent 10/16/2026
Heating and Air Conditioning Systems Air Conditioning Systems Ventilation Systems Others
FiledStatusContractorScopeMake / Model / Capacity
10/16/2026Permit IssuedFanukaOthers
Other
Islandaire EZ07 7,000 BTU · Ptac ×1
EZ09 9,300 BTU · Ptac ×1
EZ12 11,800 BTU · Ptac ×1
EZ15 14,300 BTU · Ptac ×1
07/23/2026Permit IssuedCoppermine Construction *Heating and Air Conditioning Systems
Heat / Cool
Islandaire EZPD12L2 12,000 BTU · Ptac ×3
EZ07L2MX 7,000 BTU · Ptac ×1
EZPD09L2 9,500 BTU · Ptac ×1
Ice Air 8RSAN17-W03 16,600 BTU · Ptac ×1
07/08/2026——Air Conditioning Systems, Ventilation Systems
Cooling
Task TGU-153RT-HTW-KW 12 tons · Heat Pump Outdoor ×2
TYU-RT-HTW-KW 4 tons · Heat Pump Outdoor ×2
Ventilation
Task 70 TGU-153RT-HTW-KW 12 tons · Doas ×2
TYU-033RT-HTW-KW 4 tons · Doas ×2
06/23/2026——Heating and Air Conditioning Systems
Heat / Cool
Mitsubishi Electric MITSUBISHI MODEL # MXZ-SM48NAMHZ2 48,000 BTU · Vrf Outdoor ×2
06/22/2026Permit IssuedClark ConstructionAir Conditioning Systems
Cooling
Above Air Above Aire- Model: N0 VCU-C-030-X. 30,000 BTU · Condensing Unit ×4
03/27/2026Signed-offB & H RestorationAir Conditioning Systems, Ventilation Systems
Cooling
Islandaire EZPD12B9FBS47AA 12,000 BTU · Ptac ×1
EZPD16A9GBS47AA 16,000 BTU · Ptac ×1
Friedrich Friedrich Wallmaster WET12A33A 12,000 BTU · Ptac ×1
Ventilation
11/24/2025Permit IssuedLit GroupHeating and Air Conditioning Systems
Heat / Cool
Ice Air 8RSMK16/8RSMK13 20,000 BTU · Ptac ×4
10/07/2025Permit IssuedDaa Construction GroupHeating and Air Conditioning Systems
Heat / Cool
Islandaire EZ42091233CS46AA 12,290 BTU · Ptac ×5
07/08/2025Permit IssuedFreedom GSAir Conditioning Systems
Cooling
Carrier FMC5Z2400AL 810 CFM · Fan Coil Indoor ×8
FMC5Z1800AL 575 CFM · Fan Coil Indoor ×4
National Comfort NCP5244000A-D1 23,600 BTU · Condensing Unit ×8
NCP5184000A-D1 18,600 BTU · Condensing Unit ×4
14 projects · most recent 10/16/2026
Water/Sanitary Gas
FiledStatusContractorScope
10/16/2026Permit IssuedDonato PlumbingGas, Water/Sanitary
07/23/2026Permit IssuedPipeworks NYCGas, Water/Sanitary
06/22/2026Permit IssuedDonato PlumbingWater/Sanitary
11/17/2025Permit IssuedWawel Plumbing and HeatingWater/Sanitary
10/07/2025Permit IssuedPal-Mar Plumbing & HeatingGas, Water/Sanitary
07/29/2025Signed-offSmart Plumbing & HeatingWater/Sanitary
07/08/2025Permit IssuedAccurate MechanicalGas, Water/Sanitary
06/20/2025Permit IssuedAqueduct MechanicalGas, Water/Sanitary
12/12/2022——Water/Sanitary
11/18/2022Permit IssuedA.M.NWater/Sanitary
11/12/2022——Water/Sanitary
10/20/2022Permit IssuedDemar MechanicalGas, Water/Sanitary
08/09/2022——Water/Sanitary
03/24/2022Signed-offHydrokinetic Plumbing & Heating IGas, Water/Sanitary
25 projects · most recent 10/07/2026
General Wiring Lighting
FiledStatusContractorScope
10/07/2026Permit IssuedEco Electrical ServcsGeneral Wiring, Lighting
06/26/2026Permit IssuedKepler Electrical ContGeneral Wiring
05/28/2026CompleteCobra Electrical NYCGeneral Wiring
04/08/2026Permit IssuedMacintosh ElectricGeneral Wiring
03/23/2026Permit IssuedOhr Chodosh Electrical Cont IGeneral Wiring
03/03/2026Permit IssuedGanly ElectricalGeneral Wiring
02/24/2026Permit IssuedK & G Electric CoGeneral Wiring
02/06/2026CompleteJ.G.C. ElectricGeneral Wiring
11/15/2025CompleteEastern Electrical ConstructionGeneral Wiring
10/17/2025Permit IssuedApollo Electric—
09/25/2025CompleteGlendale Electl ContngGeneral Wiring
09/10/2025Permit IssuedArma ElectricGeneral Wiring
09/08/2025CompleteA.L. ElectricalGeneral Wiring
08/06/2025Permit IssuedTM Select ElectricGeneral Wiring
08/01/2025CompleteP & Z ElectricGeneral Wiring
2 projects · most recent 07/08/2025
Masonry
FiledStatusContractorScope
07/08/2025Permit IssuedAccurate MechanicalMasonry
03/15/2023Permit IssuedHomeline Construction1 scope_items
1 project · most recent 11/17/2025
Tenant Protection Plan 72 Hour
FiledStatusContractorScope
11/17/2025Permit IssuedWawel Plumbing and HeatingTenant Protection Plan 72 Hour
▾Field Inspections (DOB CAP) — 40
DateTypeResultReport
05/21/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
05/18/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
05/07/2026Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
05/07/2026Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
05/01/2026Certified Gas-Gas-Piping-RoughingCertifiedView ↗
05/01/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
04/29/2026Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
04/24/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
04/01/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
03/03/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/29/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
12/12/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
12/11/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
11/26/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
11/18/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
11/18/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
11/14/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
11/07/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
11/07/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
09/10/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
05/02/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
03/14/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
02/24/2025Fail-Final PL - Up to 3 Requested FloorsFailView ↗
12/27/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
08/28/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
Latest 25 of 40.
▾Special Inspection Requirements (DOB NOW) — 150
DateRequirementInspectorRole
07/22/2026HVAC-R and service water heating system controlsLAWRENCE GREENenergy_progress
07/22/2026HVAC-R and service water heating equipmentLAWRENCE GREENenergy_progress
07/15/2026Fire-Resistant Penetrations and JointsLAWRENCE GREENspecial
07/15/2026Fire-Resistant Penetrations and JointsLAWRENCE GREENspecial
07/15/2026Energy Code Compliance InspectionsLAWRENCE GREENprogress
06/26/2026Mechanical Systems—special
06/26/2026Exhaust and Vent Systems in Plenums and Ducts—special
06/26/2026Tenant Protection Plan Compliance—special
06/26/2026Final—progress
06/26/2026Heating Systems—special
06/26/2026Fire-Resistant Penetrations and Joints—special
06/26/2026Fire-Resistant Penetrations and JointsLAWRENCE GREENspecial
06/23/2026Mechanical SystemsLAWRENCE GREENspecial
06/23/2026FinalLAWRENCE GREENprogress
05/12/2026FinalGUNJAN KHANDWALAprogress
05/12/2026Mechanical SystemsGUNJAN KHANDWALAspecial
05/12/2026Structural Stability – Alterations of existing buildingsGUNJAN KHANDWALAspecial
05/07/2026Fire-Resistant Penetrations and JointsLAWRENCE GREENspecial
03/26/2026Structural Stability – Alterations of existing buildingsGUNJAN KHANDWALAspecial
03/26/2026FinalGUNJAN KHANDWALAprogress
03/26/2026Mechanical SystemsGUNJAN KHANDWALAspecial
12/05/2025FinalGeorge Huangprogress
12/05/2025Fire-Resistant Penetrations and JointsGeorge Huangspecial
11/13/2025FinalGeorge Huangprogress
11/13/2025Fire-Resistant Penetrations and JointsGeorge Huangspecial
Latest 25 of 150.
▾Documents — 1,332 on file (BIS + DOB NOW)
▸Plans & Drawings98
▸DOB NOWPlans/Sketch89
09/06/2026M00000923-I1Request digital key ↗
09/04/2026M00480326-P1Request digital key ↗
09/04/2026M00480326-I1Request digital key ↗
Showing 3 of 89 on file for this type
▸DOB NOWPlans/Sketch - Plumbing4
09/05/2026M00255101-I1Request digital key ↗
09/02/2026M00422656-P2Request digital key ↗
09/02/2026M00422656-P1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - General Construction2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWPlans/Sketch - Structural2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWPlans/Sketch - Boiler Equipment1
09/05/2026M00270684-I1Request digital key ↗
▸Applications & Permits257
▸BISPLAN / WORK APPROVAL APPLICATION89
11/06/2025101666813Open ↗
06/30/2025103786789Open ↗
07/14/2021122787582Open ↗
Showing 3 of 89 on file for this type
▸DOB NOWLPC Approval/Permit87
10/18/2026M01147526-P2Open ↗
09/03/2026M00522677-I1Open ↗
09/03/2026M00522677-P1Open ↗
Showing 3 of 87 on file for this type
▸BISWORK PERMIT APPLICATION81
06/02/2021122787582Open ↗
06/02/2021122787582Open ↗
01/25/2021140985352Open ↗
Showing 3 of 81 on file for this type
▸Seals & Professional Certifications342
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION95
10/17/2019123800226Open ↗
09/20/2019140491698Open ↗
07/26/2019123713062Open ↗
Showing 3 of 95 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature95
10/18/2026M01147526-P2Open ↗
09/04/2026M00480326-P1Open ↗
09/04/2026M00480326-I1Open ↗
Showing 3 of 95 on file for this type
▸DOB NOWProgress Inspector Seal & Signature56
09/27/2026M01232154-S2Open ↗
09/26/2026M01023482-S2Open ↗
09/25/2026M00648571-S1Open ↗
Showing 3 of 56 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature56
09/27/2026M01232154-S2Open ↗
09/27/2026M01232154-S2Open ↗
09/27/2026M01232154-S2Open ↗
Showing 3 of 56 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST12
04/17/2019123660840Open ↗
Showing 1 of 12 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT10
01/06/2021140985352Open ↗
11/29/2019140878138Open ↗
04/17/2019123660840Open ↗
Showing 3 of 10 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY5
01/06/2021140985352Open ↗
11/29/2019140878138Open ↗
Showing 2 of 5 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION5
01/06/2021140985352Open ↗
11/29/2019140878138Open ↗
Showing 2 of 5 on file for this type
▸BISPC FULL REPORT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
05/21/2018140762645Open ↗
▸Trade Schedules & Equipment79
▸BISSELF-CERT PLUMBING NOTICE32
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 32 on file for this type
▸BISSCHEDULE B - PLUMBING23
06/21/2018140762645Open ↗
05/21/2018140762645Open ↗
Showing 2 of 23 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE20
04/17/2019123660840Open ↗
02/22/2018121827611Open ↗
01/24/2018123352950Open ↗
Showing 3 of 20 on file for this type
▸BISEQUIPMENT USE PERMITS2
12/03/2018123352950Open ↗
Showing 1 of 2 on file for this type
▸BISJAMAICA: DEP SEWER CONNECTION APPROVAL1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT1
12/03/2018123352950Open ↗
▸Safety & Tenant Protection18
▸BISTenant Protection Plan and Notes12
10/17/2019123800226Open ↗
07/26/2019123713062Open ↗
05/29/2019123782219Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWTenant Protection Plan5
09/02/2026M00422656-P2Open ↗
09/02/2026M00422656-P1Open ↗
Showing 2 of 5 on file for this type
▸BISTPP1: TENANT PROTECTION PLAN1
04/21/2021140985352Open ↗
▸Environmental & Asbestos124
▸DOB NOWDEP ACP-5: Asbestos Assessment Report76
10/18/2026M01147526-P2Open ↗
09/03/2026M00479684-P1Open ↗
09/03/2026M00479684-I1Open ↗
Showing 3 of 76 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)23
01/06/2021140985352Open ↗
12/10/2019123800226Open ↗
07/26/2019123713062Open ↗
Showing 3 of 23 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'13
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 13 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form7
08/26/2026M01048104-I1Open ↗
08/26/2026M01048104-S1Open ↗
08/26/2026M01048104-S2Open ↗
Showing 3 of 7 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸Energy Compliance71
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS39
12/10/2019123800226Open ↗
12/10/2019123800226Open ↗
10/17/2019123800226Open ↗
Showing 3 of 39 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS19
06/07/2021140878138Open ↗
01/26/2021123660840Open ↗
10/01/2020123800226Open ↗
Showing 3 of 19 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY4
10/09/2022122787582Open ↗
01/26/2021123660840Open ↗
01/21/2021140985352Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS3
01/06/2021140985352Open ↗
11/29/2019140878138Open ↗
Showing 2 of 3 on file for this type
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISNYCECC ANALYSIS1
11/29/2019140878138Open ↗
▸BISTECHNICAL REPORT: ENERGY1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISENERGY CODE 1ST REVIEW COMPLETE1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
10/09/2022122787582Open ↗
▸BISTR8: Energy Code Progress Inspections1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Inspections & Test Reports27
▸BISTECHNICAL REPORT: RESPONSIBILITY25
11/18/2025101666813Open ↗
11/18/2025101666813Open ↗
11/17/2025101666813Open ↗
Showing 3 of 25 on file for this type
▸BIS* FINAL INSPECTION DIRECTIVE 14 OF 19751
07/10/2025103786789Open ↗
▸BISDIR-14 ID OF RESPONSIBILITY (TR1)1
01/21/2021140985352Open ↗
▸Approvals, Objections & Sign-offs111
▸BISLANDMARKS APPROVAL46
01/06/2021140985352Open ↗
12/10/2019123800226Open ↗
11/29/2019140878138Open ↗
Showing 3 of 46 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST37
11/18/2025101666813Open ↗
07/15/2025103786789Open ↗
10/11/2022122787582Open ↗
Showing 3 of 37 on file for this type
▸BISADMINISTRATIVE OBJECTIONS14
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 14 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION8
01/26/2021123660840Open ↗
07/23/2019123782219Open ↗
07/23/2019123782219Open ↗
Showing 3 of 8 on file for this type
▸BISLANDMARKS SIGNOFF3
07/15/2025103786789Open ↗
10/11/2022122787582Open ↗
10/01/2020123800226Open ↗
▸BISLETTERS - APPROVED FABRICATION CERTIFICATIONS2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISSUPERSEDING LETTER1
06/02/2021122787582Open ↗
▸Cost, Insurance & Ownership85
▸BISCOST AFFIDAVIT77
01/26/2021123660840Open ↗
01/06/2021140985352Open ↗
10/01/2020123800226Open ↗
Showing 3 of 77 on file for this type
▸BISHIC LICENSE OR AFFIDAVIT6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW32
10/09/2022122787582Open ↗
06/07/2021140878138Open ↗
▸Filing & Intake Forms84
▸BISEFILING COVER SHEET34
10/17/2019123800226Open ↗
07/26/2019123713062Open ↗
05/29/2019123782219Open ↗
Showing 3 of 34 on file for this type
▸BISADDITIONAL INFORMATION28
01/11/2021123660840Open ↗
12/17/2019123660840Open ↗
08/21/2018140762645Open ↗
Showing 3 of 28 on file for this type
▸BISBOROUGH INTAKE FORM15
06/02/2021122787582Open ↗
02/10/2020123660840Open ↗
12/30/2019123660840Open ↗
Showing 3 of 15 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET7
01/06/2021140985352Open ↗
11/29/2019140878138Open ↗
05/21/2018140762645Open ↗
Showing 3 of 7 on file for this type
▸Other Documents36
▸DOB NOWProof of Historic Building17
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 17 on file for this type
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION9
01/26/2021123660840Open ↗
Showing 1 of 9 on file for this type
▸BISDepartment of Consumer Affairs (DCA) Form3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸DOB NOWCalculations2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWManufacturer's Specifications2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISINTERNAL (SECONDARY) BACKFLOW PREVENTION DEVICE TEST REPORT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BIS* VENT. SYS.-ENGINEER/INSTALLER 27-136,7791
11/17/2025101666813Open ↗
▸DOB NOWPro Cert Restriction Exception (LL158/17)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type