← Back
BuildNYC
Office only, 2-6 stories
Genovese Family Life Center
89-30 161ST STREET · Jamaica · BIN 4208866
💬 Discuss this project
1949Year Built
4Stories
O2Building Class
C4-4DZoning
30,000 sfGross Floor Area
1Units
LL97 Covered2 Active Violations 1 unresolved · 1 paperwork only 3 likely answered 3 old, status unconfirmed ▸FDNY Report ↗
Office only, 2-6 stories · 10,500 sf lot · 2.86 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofSCO Genovese Restack29p · 3 filings · 20 docs
Floor 4SCO Genovese Restack66p · 9 filings · 20 docs
Floor 3SCO Genovese Restack66p · 9 filings · 20 docs
Floor 2SCO Genovese Restack66p · 9 filings · 20 docs
Floor 1SCO Genovese Restack66p · 9 filings · 20 docs
CellarSCO Genovese Restack, SCO Family of Services45p · 6 filings · 20 docs
Site & exteriorSCO Genovese RestackUnder Construction6p · 1 filing · 4 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
St Christopher Ottilie1203/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Spacesmith307/27/2026
MG Engineering711/28/2022
Urbantech Consulting Engineering107/12/2021
Jonathan B. Held AIA Architect105/08/2020
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Empire City Consultants2003/21/2026
JMV Consulting Engineering P103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
DB CollaborativeGeneral Contractor2207/08/2026
BK Plumbing & HeatingFire Protection207/08/2026
S.B.A. PlumbingPlumbing207/08/2026
Ascuatech ElectricalElectrical103/22/2026
Lippolis ElectricElectrical103/21/2026
V'S Creative DesignGeneral Contractor108/30/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
DNA Controlled Inspection554411/28/2022
Socotec Engineering4983407/14/2021
Building Lifecycle
All (128)Filed (12)Permit Issued (15)Signed Off (7)Violation (60)Inspection (4)Special Inspection (30)
08/27/2026
Permit issued — General Construction
Q01428399-I1-GC
07/27/2026
Filed — Alteration
filing herewith gen. construction work includes adding a cast in place concrete ramp and steps as per plans filed herewith. No change to use, egress or occupancy.
Q01428399-I1
07/09/2026
Special inspection requirement — Final
MARC GORDON
06/05/2026
Signed off — Alteration
Q00464029-I1
06/05/2026
Signed off — Alteration
MODIFICATION TO AN EXISTING MECHANICAL SYSTEM (BUILD OUT PHASE). NO CHANGE OF USE, EGRESS OR OCCUPANCY.
Q00517811-I1
04/07/2025
Violation issued (FDNY_NOV, closed)
12/01/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
05/01/2024
Signed off — Alteration
MODIFICATION TO AN EXISTING SPRINKLER SYSTEM (DEMO PHASE). NO CHANGE OF USE, EGRESS OR OCCUPANCY.
Q00464035-I1
04/17/2024
Violation issued (FDNY_NOV, closed)
04/10/2024
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
03/19/2024
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
11/03/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/03/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/20/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
05/03/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
01/11/2023
Special inspection requirement — Mechanical Systems
ALEXIS SCHLESSINGERMAN
01/11/2023
Special inspection requirement — Post-installed Anchors
ALEXIS SCHLESSINGERMAN
01/11/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
ALEXIS SCHLESSINGERMAN
01/11/2023
Special inspection requirement — Energy Code Compliance Inspections
ALEXIS SCHLESSINGERMAN
01/11/2023
Special inspection requirement — HVAC-R and service water heating equipment
ALEXIS SCHLESSINGERMAN
01/11/2023
Special inspection requirement — Maintenance information
ALEXIS SCHLESSINGERMAN
01/11/2023
Special inspection requirement — Duct leakage testing, insulation and design
ALEXIS SCHLESSINGERMAN
01/11/2023
Special inspection requirement — Electrical motors and elevators
ALEXIS SCHLESSINGERMAN
01/11/2023
Special inspection requirement — HVAC-R and service water heating system controls
ALEXIS SCHLESSINGERMAN
01/11/2023
Special inspection requirement — Final
ALEXIS SCHLESSINGERMAN
11/28/2022
Filed — Alteration
MODIFICATION TO AN EXISTING MECHANICAL SYSTEM (BUILD OUT PHASE). NO CHANGE OF USE, EGRESS OR OCCUPANCY.
Q00517811-P1
08/05/2022
Violation issued (FDNY_ORDER, closed)
08/02/2022
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
07/10/2022
Signed off — Alteration
SCOPE OF WORK INCLUDES INTERIOR FIT OUT FOR 4 FLOORS OF WORK AT 89-30 161ST STREET,JAMAICA, QUEENS. DEMOLITION INCLUDES CHOPPING AND LEVELING FOR SLAB PENETRATIONS FOR MEP SCOPE AND DEMOLITION OF EXISTING ENTRANCE DOORS FOR NEW DOORS. CONSTRUCTION WORK IN
Q00517692-I1
07/07/2022
Signed off — Alteration
MODIFICATION TO AN EXISTING OFFICE SPACE WITH REMOVAL OF PARTITIONS (DEMO PHASE). NO CHANGE OF USE, EGRESS OR OCCUPANCY,
Q00463904-I1
06/17/2022
Violation issued (FDNY_NOV, closed)
06/01/2022
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
04/21/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
WILLIAM FITZJOHN
04/21/2022
Special inspection requirement — Mechanical Systems
WILLIAM FITZJOHN
04/21/2022
Special inspection requirement — Post-installed Anchors
WILLIAM FITZJOHN
04/21/2022
Special inspection requirement — Energy Code Compliance Inspections
WILLIAM FITZJOHN
04/21/2022
Special inspection requirement — Final
WILLIAM FITZJOHN
04/21/2022
Special inspection requirement — Electrical motors and elevators
WILLIAM FITZJOHN
04/21/2022
Special inspection requirement — Duct leakage testing, insulation and design
WILLIAM FITZJOHN
04/21/2022
Special inspection requirement — HVAC-R and service water heating equipment
WILLIAM FITZJOHN
04/21/2022
Special inspection requirement — Maintenance information
WILLIAM FITZJOHN
04/21/2022
Special inspection requirement — HVAC-R and service water heating system controls
WILLIAM FITZJOHN
01/12/2022
Permit issued — Mechanical Systems
Q00517811-I1-MS
01/12/2022
Permit issued — General Construction
Q00517692-I1-GC
01/12/2022
Permit issued — General Construction
Q00463904-I1-GC
01/12/2022
Permit issued — Structural
Q00518524-I1-ST
01/12/2022
Permit issued — Mechanical Systems
Q00464029-I1-MS
12/08/2021
Signed off — Alteration
Q00464041-I1
12/08/2021
Signed off — Alteration
MODIFICATION TO AN EXISTING PLUMBING SYSTEM (BUILD OUT PHASE).
Q00518217-I1
09/01/2021
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
08/24/2021
Permit issued — General Construction
Q00517692-I1-GC
08/24/2021
Permit issued — Mechanical Systems
Q00517811-I1-MS
08/24/2021
Permit issued — Structural
Q00518524-I1-ST
08/20/2021
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
08/17/2021
Violation issued (FDNY_NOV, closed)
08/16/2021
Permit issued — Plumbing
Q00518217-I1-PL
08/13/2021
Permit issued — Sprinklers
Q00518240-I1-EW-SP
07/15/2021
Filed — Alteration
SCOPE OF WORK INCLUDES INTERIOR FIT OUT FOR 4 FLOORS OF WORK AT 89-30 161ST STREET,JAMAICA, QUEENS. DEMOLITION INCLUDES CHOPPING AND LEVELING FOR SLAB PENETRATIONS FOR MEP SCOPE AND DEMOLITION OF EXISTING ENTRANCE DOORS FOR NEW DOORS. CONSTRUCTION WORK IN
Q00517692-I1
07/14/2021
Filed — Alteration
MODIFICATION TO AN EXISTING MECHANICAL SYSTEM (BUILD OUT PHASE). NO CHANGE OF USE, EGRESS OR OCCUPANCY.
Q00517811-I1
07/14/2021
Filed — Alteration
MODIFICATION TO AN EXISTING PLUMBING SYSTEM (BUILD OUT PHASE).
Q00518217-I1
Latest 60 of 128 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedV'S Creative Design08/27/2026
DOB NOWMechanical SystemsSigned-offDB Collaborative01/12/2022
DOB NOWGeneral ConstructionSigned-offDB Collaborative01/12/2022
DOB NOWGeneral ConstructionSigned-offDB Collaborative01/12/2022
DOB NOWStructuralPermit IssuedDB Collaborative01/12/2022
DOB NOWMechanical SystemsSigned-offDB Collaborative01/12/2022
DOB NOWGeneral ConstructionSigned-offDB Collaborative08/24/2021
DOB NOWMechanical SystemsSigned-offDB Collaborative08/24/2021
DOB NOWStructuralPermit IssuedDB Collaborative08/24/2021
DOB NOWPlumbingSigned-offS.B.A. Plumbing08/16/2021
DOB NOWSprinklersPermit IssuedBK Plumbing & Heating08/13/2021
DOB NOWSprinklersSigned-offBK Plumbing & Heating05/10/2021
DOB NOWPlumbingSigned-offS.B.A. Plumbing04/16/2021
DOB NOWMechanical SystemsSigned-offDB Collaborative02/23/2021
DOB NOWGeneral ConstructionSigned-offDB Collaborative02/22/2021
BISMHISSUEDDB Collaborative07/10/2019
BISOTISSUEDDB Collaborative07/10/2019
BISFSISSUEDJack Piccinni06/25/2014
BISOTISSUEDBartel Construction Co05/09/2014
BISPLISSUEDJ. Caiazzo Plumbing & Heating04/05/2012
BISOTISSUEDBartel Construction Co03/20/2012
BISOTISSUEDFoschi Construction10/30/2008
BISOTISSUEDFoschi Construction07/09/2008
BISEQISSUEDMetro Contracting NY07/08/2008
BISPLISSUEDAngelo Andrew06/02/2006
BISSPISSUEDEmdi09/13/2005
BIS—ISSUEDSt Christopher Ottilie03/17/2005
BISSPISSUEDManhattan Automatic Sprinkler Co06/28/1991
BISPLISSUEDBypass Mechanical04/26/1991
BISOTISSUEDGordon Construction04/16/1991
BISOTRE-ISSUEDGordon Construction04/16/1991
BISOTRE-ISSUEDGordon Construction01/09/1991
BISOTISSUEDGordon Construction01/09/1991
BISOTISSUEDThe Noonan Group05/07/1990
BISEQISSUEDYork Scaffolding02/28/1990
4 projects · most recent 12/06/2021
General Wiring Lighting
FiledStatusContractorScope
12/06/2021Permit IssuedAscuatech ElectricalGeneral Wiring
05/06/2021Permit IssuedLmec ElectricGeneral Wiring, Lighting
06/26/2019CompleteLmec ElectricGeneral Wiring, Lighting
06/26/2019CompleteLmec Electric—
1 project · most recent 07/12/2021
Steel Wood
FiledStatusContractorScope
07/12/2021Permit IssuedDB CollaborativeSteel, Wood
▾Field Inspections (DOB CAP) — 4
DateTypeResultReport
04/10/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
03/19/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
09/01/2021Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
08/20/2021Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 33
DateRequirementInspectorRole
07/09/2026FinalMARC GORDONprogress
01/11/2023Mechanical SystemsALEXIS SCHLESSINGERMANspecial
01/11/2023Post-installed AnchorsALEXIS SCHLESSINGERMANspecial
01/11/2023Fire-Resistant Penetrations and JointsALEXIS SCHLESSINGERMANspecial
01/11/2023Energy Code Compliance InspectionsALEXIS SCHLESSINGERMANprogress
01/11/2023HVAC-R and service water heating equipmentALEXIS SCHLESSINGERMANenergy_progress
01/11/2023Maintenance informationALEXIS SCHLESSINGERMANenergy_progress
01/11/2023Duct leakage testing, insulation and designALEXIS SCHLESSINGERMANenergy_progress
01/11/2023Electrical motors and elevatorsALEXIS SCHLESSINGERMANenergy_progress
01/11/2023HVAC-R and service water heating system controlsALEXIS SCHLESSINGERMANenergy_progress
01/11/2023FinalALEXIS SCHLESSINGERMANprogress
04/21/2022Fire-Resistant Penetrations and JointsWILLIAM FITZJOHNspecial
04/21/2022Mechanical SystemsWILLIAM FITZJOHNspecial
04/21/2022Post-installed AnchorsWILLIAM FITZJOHNspecial
04/21/2022Energy Code Compliance InspectionsWILLIAM FITZJOHNprogress
04/21/2022FinalWILLIAM FITZJOHNprogress
04/21/2022Electrical motors and elevatorsWILLIAM FITZJOHNenergy_progress
04/21/2022Duct leakage testing, insulation and designWILLIAM FITZJOHNenergy_progress
04/21/2022HVAC-R and service water heating equipmentWILLIAM FITZJOHNenergy_progress
04/21/2022Maintenance informationWILLIAM FITZJOHNenergy_progress
04/21/2022HVAC-R and service water heating system controlsWILLIAM FITZJOHNenergy_progress
05/11/2021FinalWILLIAM FITZJOHNprogress
05/11/2021Fire-Resistant Penetrations and JointsWILLIAM FITZJOHNspecial
05/07/2021FinalWILLIAM FITZJOHNprogress
05/07/2021Structural Stability – Alterations of existing buildingsALEXIS SCHLESSINGERMANspecial
Latest 25 of 33.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
SCO Genovese RestackOfficeCellar, Floors 1–4, Roof
Project Q00517692 Alteration · LOC Issued · 07/15/2021
Project Q00518240 Alteration · Permit Entire · 07/14/2021
Project Q00518524 Alteration · Permit Entire · 07/12/2021
SCO Family of ServicesEducationCellar
Project Q00335248 Alteration · QA Failed · 05/08/2020
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 181 on file (BIS + DOB NOW)
▸Plans & Drawings12
▸DOB NOWPlans/Sketch7
08/27/2026Q00518524-I1Request digital key ↗
08/27/2026Q00518217-I1Request digital key ↗
08/27/2026Q00518240-I1Request digital key ↗
Showing 3 of 7 on file for this type
▸DOB NOWPlans/Sketch - Boiler Equipment1
08/28/2026Q00335248-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Mechanical Systems1
08/27/2026Q00464029-I1Request digital key ↗
▸DOB NOWPlans/Sketch - General Construction1
08/27/2026Q00463904-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sprinkler1
08/27/2026Q00464035-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing1
08/27/2026Q00464041-I1Request digital key ↗
▸Applications & Permits22
▸BISWORK PERMIT APPLICATION11
07/29/2019421730265Open ↗
07/29/2019421730265Open ↗
07/26/2019421731326Open ↗
Showing 3 of 11 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION11
07/16/2019421730265Open ↗
07/16/2019421730265Open ↗
07/16/2019421731326Open ↗
Showing 3 of 11 on file for this type
▸Seals & Professional Certifications63
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION17
07/18/2019421730265Open ↗
07/18/2019421730265Open ↗
07/18/2019421731326Open ↗
Showing 3 of 17 on file for this type
▸DOB NOWProgress Inspector Seal & Signature14
08/31/2026Q00517811-P1Open ↗
08/31/2026Q00517811-P1Open ↗
08/31/2026Q00517811-P1Open ↗
Showing 3 of 14 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature12
08/28/2026Q00335248-I1Open ↗
08/27/2026Q00464041-I1Open ↗
08/27/2026Q00518217-I1Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature8
08/31/2026Q00517811-P1Open ↗
08/31/2026Q00517811-P1Open ↗
08/31/2026Q00517811-P1Open ↗
Showing 3 of 8 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST6
07/16/2019421730265Open ↗
07/16/2019421731326Open ↗
07/16/2019421730265Open ↗
Showing 3 of 6 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT3
07/16/2019421730265Open ↗
07/16/2019421731326Open ↗
07/16/2019421730265Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM3
03/06/2012420540640Open ↗
07/02/2008410132574Open ↗
03/26/2008410089489Open ↗
▸Trade Schedules & Equipment9
▸BISSCHEDULE B - PLUMBING3
03/06/2012420540640Open ↗
10/09/2008410177534Open ↗
10/09/2008410177534Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE2
07/16/2019421730265Open ↗
07/16/2019421731326Open ↗
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT2
02/02/2015420911632Open ↗
01/16/2014420911632Open ↗
▸BISSELF-CERT PLUMBING NOTICE1
04/26/2012420540640Open ↗
▸BISSPRINKLER SYSTEMS1
03/11/2021421731326Open ↗
▸Environmental & Asbestos18
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form5
08/27/2026Q00518217-I1Open ↗
08/27/2026Q00518240-I1Open ↗
08/25/2026Q00517811-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report4
08/27/2026Q00464041-I1Open ↗
08/13/2026Q00464029-I1Open ↗
08/13/2026Q00463904-I1Open ↗
Showing 3 of 4 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER3
10/29/2013420911632Open ↗
07/02/2008410132574Open ↗
03/26/2008410089489Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)3
07/16/2019421730265Open ↗
07/16/2019421730265Open ↗
07/16/2019421731326Open ↗
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'3
03/06/2012420540640Open ↗
10/09/2008410177534Open ↗
10/09/2008410177525Open ↗
▸Energy Compliance7
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS3
07/18/2019421730265Open ↗
07/16/2019421730265Open ↗
10/29/2013420911632Open ↗
▸BISAS-BUILT ENERGY ANALYSIS2
04/17/2015420911632Open ↗
06/18/2012420540640Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
03/11/2021421731326Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
08/25/2026Q00517811-I1Open ↗
▸Inspections & Test Reports2
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)1
03/11/2021421731326Open ↗
▸BISPOST-INSTALLED ANCHORS1
03/11/2021421731326Open ↗
▸Approvals, Objections & Sign-offs21
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter12
08/28/2026Q00335248-I1Open ↗
08/27/2026Q00464041-I1Open ↗
08/27/2026Q00518240-I1Open ↗
Showing 3 of 12 on file for this type
▸BISADMINISTRATIVE OBJECTIONS4
10/09/2008410177534Open ↗
10/09/2008410177525Open ↗
07/07/2008410132574Open ↗
Showing 3 of 4 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST3
07/29/2021421731326Open ↗
04/25/2015420911632Open ↗
06/18/2012420540640Open ↗
▸BISMaster Plumber Seal Temporary Approval Letter1
04/26/2012420540640Open ↗
▸BISFINAL1
03/11/2021421731326Open ↗
▸Cost, Insurance & Ownership12
▸BISCOST AFFIDAVIT11
07/16/2019421730265Open ↗
07/16/2019421731326Open ↗
07/16/2019421730265Open ↗
Showing 3 of 11 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW31
07/29/2021421731326Open ↗
▸Filing & Intake Forms12
▸BISEFILING COVER SHEET10
07/16/2019421730265Open ↗
07/16/2019421730265Open ↗
07/16/2019421731326Open ↗
Showing 3 of 10 on file for this type
▸BISADDITIONAL INFORMATION2
06/04/2020421730265Open ↗
06/04/2020421731326Open ↗
▸Other Documents3
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION3
07/16/2019421730265Open ↗
07/16/2019421730265Open ↗
07/16/2019421731326Open ↗