Roof9p · 3 filings · 20 docs
DMMechanical
Issued Permit Scope
Mechanical Systems
Renovation of 3rd floor apartment to include removal and installation of partitions, doors and finishes. No change to use, egress or occupancy is involved.
On file for this project
20 documents · 1 drawing sheet
RENOVATION OF EXISTING DUPLEX APARTMENT ON THE BASEMENT AND 1ST FLOOR TO INCLUDE REMOVAL AND INSTALLATION OF PARTITIONS, DOORS, CEILINGS AND FINISHES. NO CHANGE TO USE, EGRESS OR OCCUPANCY IS INVOLVED.
On file for this project
16 documents · 1 drawing sheet
RENOVATION OF EXISTING DUPLEX APARTMENT ON THE CELLAR, BASEMENT, 1ST FLOOR AND ROOF TO INCLUDE REMOVAL AND INSTALLATION OF HVAC SYSTEM. NO CHANGE TO USE, EGRESS OR OCCUPANCY IS INVOLVED.
On file for this project
5 documents · 2 drawing sheets
Floor 48p · 2 filings · 18 docs
ArchitecturePlumbing
Issued Permit Scope
General Construction · Plumbing
PROPOSED RESTORATION OF FRONT FACADE TO INCLUDE BRICK REPOINTING AND REPLACEMENT, REPAIRING STOOP AND FRONT DRIVEWAY, WINDOW REPLACEMENT S AND REPLACE PORTICO. NO CHANGE TO USE, EGRESS OR OCCUPANCY IS INVOLVED.
On file for this project
7 documents
GAS RE-PIPE TO (5) APARTMENTS FOR COOKING AND (1) RISER FOR HEAT AND HOT WATER. REGISTER GAS APPLIANCES AND REPLACE BOILER.
On file for this project
11 documents
Floor 323p · 3 filings · 20 docs
ArchitectureDMMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing
Renovation of 3rd floor apartment to include removal and installation of partitions, doors and finishes. No change to use, egress or occupancy is involved.
On file for this project
20 documents · 3 drawing sheets
PROPOSED RESTORATION OF FRONT FACADE TO INCLUDE BRICK REPOINTING AND REPLACEMENT, REPAIRING STOOP AND FRONT DRIVEWAY, WINDOW REPLACEMENT S AND REPLACE PORTICO. NO CHANGE TO USE, EGRESS OR OCCUPANCY IS INVOLVED.
On file for this project
7 documents
GAS RE-PIPE TO (5) APARTMENTS FOR COOKING AND (1) RISER FOR HEAT AND HOT WATER. REGISTER GAS APPLIANCES AND REPLACE BOILER.
On file for this project
11 documents
Floor 229p · 3 filings · 20 docs
ArchitecturePlumbingStructural
Issued Permit Scope
General Construction · Plumbing · Structural
PROPOSED RESTORATION OF FRONT FACADE TO INCLUDE BRICK REPOINTING AND REPLACEMENT, REPAIRING STOOP AND FRONT DRIVEWAY, WINDOW REPLACEMENT S AND REPLACE PORTICO. NO CHANGE TO USE, EGRESS OR OCCUPANCY IS INVOLVED.
On file for this project
7 documents
MODIFICATION OF INTERIOR BEARING WALL AND REPAIR TO EXTERIOR WINDOW OPENINGS.
On file for this project
12 documents · 3 drawing sheets
GAS RE-PIPE TO (5) APARTMENTS FOR COOKING AND (1) RISER FOR HEAT AND HOT WATER. REGISTER GAS APPLIANCES AND REPLACE BOILER.
On file for this project
11 documents
Floor 113p · 7 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
RELOCATION OF SPRINKLER RISER ON BASEMENT AND 1ST FLOORS. REMOVAL AND INSTALLATION OF SPRINKLER HEADS ON SUCH FLOORS AS WELL. REMOVAL OF SPRINKLR PIPING IN THE CELLAR. NO CHANGE TO USE, EGRESS OR OCCUPANCY IS INVOLVED.
On file for this project
15 documents
PROPOSED RESTORATION OF FRONT FACADE TO INCLUDE BRICK REPOINTING AND REPLACEMENT, REPAIRING STOOP AND FRONT DRIVEWAY, WINDOW REPLACEMENT S AND REPLACE PORTICO. NO CHANGE TO USE, EGRESS OR OCCUPANCY IS INVOLVED.
On file for this project
7 documents
MODIFICATION OF INTERIOR BEARING WALL AND REPAIR TO EXTERIOR WINDOW OPENINGS.
On file for this project
12 documents · 2 drawing sheets
Latest 3 of 7 filings on this floor.
Cellar34p · 5 filings · 20 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers
RELOCATION OF SPRINKLER RISER ON BASEMENT AND 1ST FLOORS. REMOVAL AND INSTALLATION OF SPRINKLER HEADS ON SUCH FLOORS AS WELL. REMOVAL OF SPRINKLR PIPING IN THE CELLAR. NO CHANGE TO USE, EGRESS OR OCCUPANCY IS INVOLVED.
On file for this project
15 documents · 4 drawing sheets
RENOVATION OF EXISTING DUPLEX APARTMENT ON THE CELLAR, BASEMENT AND 1ST FLOOR TO INCLUDE REMOVAL AND INSTALLATION OF PLUMBING FIXTURES. NO CHANGE TO USE, EGRESS OR OCCUPANCY IS INVOLVED.
On file for this project
20 documents · 2 drawing sheets
RENOVATION OF EXISTING DUPLEX APARTMENT ON THE BASEMENT AND 1ST FLOOR TO INCLUDE REMOVAL AND INSTALLATION OF PARTITIONS, DOORS, CEILINGS AND FINISHES. NO CHANGE TO USE, EGRESS OR OCCUPANCY IS INVOLVED.
On file for this project
16 documents · 4 drawing sheets
Latest 3 of 5 filings on this floor.
Basement2p · 2 filings · 20 docs
DMStructural
REMOVAL AND REPLACEMENT OF WALL IN REAR YARD; NEW GRADE BEAM SUPPORT FOR EXISTING STAIR STRINGER AT REAR YARD
On file for this project
14 documents · 1 drawing sheet
RENOVATION OF EXISTING DUPLEX APARTMENT ON THE BASEMENT AND 1ST FLOOR TO INCLUDE REMOVAL AND INSTALLATION OF PARTITIONS, DOORS, CEILINGS AND FINISHES. NO CHANGE TO USE, EGRESS OR OCCUPANCY IS INVOLVED.
On file for this project
16 documents · 1 drawing sheet
Sub-Basement13p · 7 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
RELOCATION OF SPRINKLER RISER ON BASEMENT AND 1ST FLOORS. REMOVAL AND INSTALLATION OF SPRINKLER HEADS ON SUCH FLOORS AS WELL. REMOVAL OF SPRINKLR PIPING IN THE CELLAR. NO CHANGE TO USE, EGRESS OR OCCUPANCY IS INVOLVED.
On file for this project
15 documents
PROPOSED RESTORATION OF FRONT FACADE TO INCLUDE BRICK REPOINTING AND REPLACEMENT, REPAIRING STOOP AND FRONT DRIVEWAY, WINDOW REPLACEMENT S AND REPLACE PORTICO. NO CHANGE TO USE, EGRESS OR OCCUPANCY IS INVOLVED.
On file for this project
7 documents
MODIFICATION OF INTERIOR BEARING WALL AND REPAIR TO EXTERIOR WINDOW OPENINGS.
On file for this project
12 documents
Latest 3 of 7 filings on this floor.
Site & exterior22p · 5 filings · 20 docs
ArchitectureElectricalEquipmentGeneralMechanicalPlumbingStructural
Issued Permit Scope
Construction Fence · Foundation · Plumbing · Sidewalk Shed · Supported Scaffold
REMOVAL AND REPLACEMENT OF WALL IN REAR YARD; NEW GRADE BEAM SUPPORT FOR EXISTING STAIR STRINGER AT REAR YARD
On file for this project
14 documents · 7 drawing sheets
INSTALLATION OF CONSTRUCTION PLYWOOD FENCE AS PER PLANS.CONSTRUCTION FENCE SHALL COMPLY WITH CHAPTER # 33 OF THE 2022 CODE. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents · 6 drawing sheets
INSTALLATION OF 300PSF SIDEWALK SHED AND PIPE SCAFFOLDING AS PER PLANS, ALL EQUIPMENT SHALL COMPLY WITH CHAPTER # 33 OF THE NYC CODE 2022, NO CHANGES IN USE EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
On file for this project
2 documents · 6 drawing sheets
Latest 3 of 5 filings on this floor.
Filed — no permit issued11p · 2 filings · 17 docs
ArchitectureGeneralStructural
Support of Excavation work in backyard for underpinning work.
On file for this project
14 documents · 8 drawing sheets
UNDERPINNING OF EXISTING RETAINING WALL IN REAR YARD
On file for this project
3 documents · 4 drawing sheets