← Back
Elevator cooperative
90-60 UNION TURNPIKE
QUEENS · BIN 4094962
💬 Discuss this project
1965Year Built
20Stories
D4Building Class
R3-2Zoning
295,340 sfGross Floor Area
241Units
LL97 CoveredRent Stabilized5 Open Violations ▸FISP: SWARMP
Elevator cooperative · Owner of record: FOREST VIEW CRESCENT, INC. · 106,575 sf lot · 2.77 FAR built · Flood zone X
Locations of Work
ArchitectureEquipment
Permit Issued — active, not yet Signed-off
Bulkhead1p · 1 filing · 10 docs
Floor 17Under Construction1p · 1 filing · 4 docs
Floor 16
Floor 151p · 1 filing · 3 docs
Floor 14
Floor 13
Floor 12
Floor 11
Floor 10Under Construction11p · 1 filing · 16 docs
Floor 9
Floor 8
Floor 7
Floor 6
Floor 5
Floor 4
Floor 3
Floor 2
Floor 1
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
RACHLIN MANAGEMENT1104/09/2026
FOREST PARK CRESENT INC1503/22/2026
OWNER OF 90-60 UNION TRNP203/22/2026
SAME103/21/2026
STEEL INDUSTRIES303/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
AK CONSULTING SERVICES203/21/2026
BOYD CONSULTING203/21/2026
KRV HOME IMPROVEMENT403/21/2026
AE DESIGN SOLUTION403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
PRC CONSTRUCTION LLCGeneral Contractor303/21/2026
PROTO RESTORATION SPECIALGeneral Contractor204/10/2026
DIAZ FRANCISCOElectrical103/21/2026
DIAZ, FRANCISCOElectrical103/21/2026
HIGH QUALITY ELEC.OF NYCElectrical103/22/2026
POTTINGER, PATRICKElectrical103/21/2026
STEVEN OLKHOVETSKYElectrical103/21/2026
COSIMO CURCIOElectrical103/21/2026
WILLIAMS DESIGNS & CONSTRGeneral Contractor107/08/2026
CURCIO COSIMOElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ANTONUCCI & ASSOCIATES, A2115208/19/2026
CITY-WIDE TESTING INC416204/21/2026
SONI ENGINEERING CONSULTI9819212/02/2025
SANDEEP GUNNALA ENGINEERI8482110/02/2025
SUNG HO SHIN ARCHITECT2997110/14/2024
Building Lifecycle
All (119)Filed (11)Permit Issued (9)Signed Off (3)Facade (FISP) (15)Violation (60)Objection (4)Special Inspection (17)
08/19/2026
Filed — Alteration
INSTALL NEW BALCONY ENCLOSURES
Q01264272-S1
08/18/2026
Permit issued — General Construction
Q01287026-I1-GC
07/28/2026
Signed off — Alteration
Installation of suspended scaffold for facade work or inspection.
Q01296124-I1
06/08/2026
Permit issued — General Construction
Q01384391-I1-GC
05/29/2026
Filed — Alteration
Q01384391-I1
05/08/2026
Objection raised — Other
05/08/2026
Objection raised — Other
04/21/2026
Filed — Alteration
INTER. RENOV.: REMOVAL OF NON-LOADBEARING PARTITIONS, FLR, CLG & WALL FINISHES & LIGHTS. INSTALL NEW NON-LOADBEARING PARTITIONS, FLR, CLG & WALL FINISHES. INSTALL REPLACEMENT LIGHTS. NO PROPOSED CHANGE TO USE, EGRESS OR OCCUPNCY. NO ENLGMT OR DEVELPMT.
Q01287026-I1
04/21/2026
Filed — Alteration
INTER. RENOV.: REMOVAL OF NON-LOADBEARING PARTITIONS, FLR, CLG & WALL FINISHES & LIGHTS. INSTALL NEW NON-LOADBEARING PARTITIONS, FLR, CLG & WALL FINISHES. INSTALL REPLACEMENT LIGHTS. NO PROPOSED CHANGE TO USE, EGRESS OR OCCUPNCY. NO ENLGMT OR DEVELPMT.
Q01287026-S1
04/08/2026
Permit issued — General Construction
Q01264272-I1-GC
04/08/2026
Special inspection requirement — Final
Dariusz Makara
01/06/2026
Permit issued — General Construction
Q01264272-I1-GC
12/02/2025
Filed — Alteration
Installation of suspended scaffold for facade work or inspection.
Q01296124-P1
12/01/2025
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
nayan soni
12/01/2025
Special inspection requirement — Post-installed Anchors
nayan soni
11/07/2025
Permit issued — Suspended Scaffold
Q01296124-I1-SC
11/05/2025
Objection raised — Admin
11/05/2025
Objection resolved — Addressed
10/21/2025
Special inspection requirement — Fire-Resistance Rated Construction
ELIAS RASABI
10/21/2025
Special inspection requirement — Tenant Protection Plan Compliance
ELIAS RASABI
10/16/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
ELIAS RASABI
10/16/2025
Special inspection requirement — Lighting controls
ELIAS RASABI
10/16/2025
Special inspection requirement — Lighting in dwelling units
ELIAS RASABI
10/16/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
ELIAS RASABI
10/16/2025
Special inspection requirement — Energy Code Compliance Inspections
ELIAS RASABI
10/14/2025
Filed — Alteration
Installation of suspended scaffold for facade work or inspection.
Q01296124-I1
10/02/2025
Filed — Alteration
INSTALL NEW BALCONY ENCLOSURES
Q01264272-I1
09/29/2025
Permit issued — Sidewalk Shed
Q01291374-I1-SH
09/28/2025
Filed — Alteration
INSTALLATION OF NEW SIDEWALK SHED AT 90-50 UNION TURNPIKE QUEENS AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
Q01291374-I1
09/15/2025
Special inspection requirement — Energy Code Compliance Inspections
ELIAS RASABI
09/15/2025
Special inspection requirement — Final
ELIAS RASABI
09/15/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
ELIAS RASABI
09/12/2025
Signed off — Alteration
Q01147175-I1
09/12/2025
Signed off — Alteration
Q01148539-I1
08/21/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Robert Antonucci
08/21/2025
Special inspection requirement — Final
Robert Antonucci
08/21/2025
Special inspection requirement — Masonry
Robert Antonucci
08/21/2025
Special inspection requirement — Tenant Protection Plan Compliance
Sandeep Gunnala
06/12/2025
Violation issued (HPD, closed)
A
02/07/2025
Permit issued — General Construction
Q01148539-I1-GC
01/27/2025
Permit issued — General Construction
Q01147175-I1-GC
01/16/2025
Filed — Alteration
Q01148539-I1
12/30/2024
Filed — Alteration
Q01147175-I1
12/01/2024
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
10/22/2024
Permit issued — General Construction
Q01123307-I1-GC
10/14/2024
Filed — Alteration
Q01123307-I1
03/29/2023
Violation issued (HPD, closed)
A
12/01/2022
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
10/17/2022
Cycle 9 facade report signed — SWARMP
08/25/2022
Cycle 9 facade report submitted
08/10/2022
Cycle 9 facade inspection completed
03/09/2021
Violation issued (HPD, open)
C
04/27/2020
Violation issued (ECB, closed)
Unknown
11/08/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
11/08/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/05/2019
Cycle 8 facade report submitted
02/03/2019
Cycle 8 facade report signed — SAFE
01/16/2019
Cycle 8 facade inspection completed
04/06/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
04/06/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
Latest 60 of 119 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedNot Applicable08/18/2026
DOB NOWGeneral ConstructionPermit IssuedNot Applicable06/08/2026
DOB NOWGeneral ConstructionPermit IssuedPROTO RESTORATION SPECIAL04/08/2026
DOB NOWGeneral ConstructionPermit IssuedPROTO RESTORATION SPECIAL01/06/2026
DOB NOWSuspended ScaffoldSigned-offPROTO RESTORATION CONSTRU11/07/2025
DOB NOWSidewalk ShedPermit IssuedPRC CONSTRUCTION LLC09/29/2025
DOB NOWGeneral ConstructionSigned-offNot Applicable02/07/2025
DOB NOWGeneral ConstructionSigned-offNot Applicable01/27/2025
DOB NOWGeneral ConstructionPermit IssuedWILLIAMS DESIGNS & CONSTR10/22/2024
BISOTISSUEDPROTO RESTORATION CONSTRUCTION03/28/2018
BISOTISSUEDPROTO RESTORATION CONSTRUCTION06/21/2017
BISEQISSUEDG & M EQUIPMENT LEASING L05/11/2017
BISOTISSUEDC C CONTROLLED COMBUSTION09/21/2015
BISOTISSUEDPCGNY CORP09/22/2014
BISPLISSUEDCOMMERICAL PLBG SVCES LLC07/03/2013
BISOTISSUEDPCGNY CORP09/28/2012
BISPLISSUEDENOBRAC PLUMBING, INC07/18/2012
BISOTISSUEDYATES REST GROUP LTD05/29/2012
BISOTISSUEDPCGNY CORP05/03/2012
BISOTISSUEDYATES REST GROUP LTD05/12/2011
BISEQISSUEDCS BRIDGE CORP04/26/2011
BISEQISSUEDSTEEL INSUSTRIES, INC02/28/2011
BISOTISSUEDYATES REST GROUP LTD06/23/2010
BISEQISSUEDCS BRIDGE CORP04/16/2010
BISEQISSUEDCOLGATE SCAFF & EQUIP CO03/02/2010
BISEQISSUEDCOLGATE SCAFF & EQUIP CO01/23/2010
BISEQISSUEDCOLGATE SCAFF & EQUIP CO01/13/2009
BISEQISSUEDCLARK & WILKINS INDUSTRIES, INC12/20/2001
BISEQISSUEDCLARK & WILKINS INDUSTRIES, INC11/01/2001
BISOTISSUEDMILLENIUM RESTORATION CORP04/13/2001
BISEQISSUEDCLARK & WILKINS INDUSTRIES, INC01/02/2001
BISPLISSUEDVARSITY PLG HGT GO INC04/09/1999
BISOTISSUEDAGGRESSIVE HEATING INC03/03/1999
1 project · most recent 04/21/2026
Gas Water/Sanitary
FiledStatusContractorScope
04/21/2026——Gas, Water/Sanitary
2 projects · most recent 11/03/2025
General Wiring
FiledStatusContractorScope
11/03/2025Permit IssuedHIGH QUALITY ELEC.OF NYC—
09/12/2022CompleteCROSS BROTHERS ELECTRICGeneral Wiring
1 project · most recent 09/28/2025
Sidewalk Shed
FiledStatusContractorScope
09/28/2025Permit IssuedPRC CONSTRUCTION LLCSidewalk Shed
1 project · most recent 12/02/2025
Suspended Scaffold
FiledStatusContractorScope
12/02/2025Signed-offPROTO RESTORATION CONSTRUSuspended Scaffold
1 project · most recent 12/02/2025
Suspended Scaffold (SC)
FiledStatusContractorScope
12/02/2025Signed-offPROTO RESTORATION CONSTRUSuspended Scaffold (SC)
▾Special Inspection Requirements (DOB NOW) — 17
DateRequirementInspectorRole
04/08/2026FinalDariusz Makaraprogress
12/01/2025Alternative Materials - OTCR Buildings Bulletin Numbernayan sonispecial
12/01/2025Post-installed Anchorsnayan sonispecial
10/21/2025Fire-Resistance Rated ConstructionELIAS RASABIprogress
10/21/2025Tenant Protection Plan ComplianceELIAS RASABIspecial
10/16/2025HVAC-R and service water piping design and insulationELIAS RASABIenergy_progress
10/16/2025Lighting controlsELIAS RASABIenergy_progress
10/16/2025Lighting in dwelling unitsELIAS RASABIenergy_progress
10/16/2025Fire-Resistant Penetrations and JointsELIAS RASABIspecial
10/16/2025Energy Code Compliance InspectionsELIAS RASABIprogress
09/15/2025Energy Code Compliance InspectionsELIAS RASABIprogress
09/15/2025FinalELIAS RASABIprogress
09/15/2025Fire-Resistant Penetrations and JointsELIAS RASABIspecial
08/21/2025Structural Stability – Alterations of existing buildingsRobert Antonuccispecial
08/21/2025FinalRobert Antonucciprogress
08/21/2025MasonryRobert Antonuccispecial
08/21/2025Tenant Protection Plan ComplianceSandeep Gunnalaspecial
▾Documents — 184 on file (BIS + DOB NOW)
▸Plans & Drawings11
▸DOB NOWPlans/Sketch11
08/21/2026Q01123307-I1Request digital key ↗
08/21/2026Q01147175-I1Request digital key ↗
08/21/2026Q01148539-I1Request digital key ↗
Showing 3 of 11 on file for this type
▸Applications & Permits26
▸BISWORK PERMIT APPLICATION14
06/29/2017421453153Open ↗
05/05/2017440403234Open ↗
09/17/2015440252637Open ↗
Showing 3 of 14 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION12
12/01/2018421453153Open ↗
12/13/2017421453153Open ↗
11/17/2017421453153Open ↗
Showing 3 of 12 on file for this type
▸Seals & Professional Certifications59
▸DOB NOWDPL-1: Design Professional Seal & Signature13
08/21/2026Q01123307-I1Open ↗
08/21/2026Q01147175-I1Open ↗
08/21/2026Q01148539-I1Open ↗
Showing 3 of 13 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION10
12/12/2018421453153Open ↗
12/01/2018421453153Open ↗
12/15/2017421453153Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWProgress Inspector Seal & Signature8
09/28/2026Q01264272-I1Open ↗
09/23/2026Q01287026-I1Open ↗
08/28/2026Q01287026-I1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature8
09/28/2026Q01264272-I1Open ↗
09/28/2026Q01264272-I1Open ↗
09/28/2026Q01264272-I1Open ↗
Showing 3 of 8 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST5
04/03/2017421453153Open ↗
05/03/2012420562368Open ↗
03/01/2011420327364Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT5
06/08/2017440410663Open ↗
05/05/2017440403234Open ↗
04/03/2017421453153Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM4
05/03/2012420562368Open ↗
03/01/2011420327364Open ↗
06/16/2010420202587Open ↗
Showing 3 of 4 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION3
06/08/2017440410663Open ↗
05/05/2017440403234Open ↗
09/17/2015440252637Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY3
06/08/2017440410663Open ↗
05/05/2017440403234Open ↗
09/17/2015440252637Open ↗
▸Trade Schedules & Equipment4
▸BISSCHEDULE B - PLUMBING2
11/23/2012420562368Open ↗
05/03/2012420562368Open ↗
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT1
09/17/2015440252637Open ↗
▸BISPLUMBING - SUPPORTING DOCUMENTATION1
07/10/2013420562368Open ↗
▸Safety & Tenant Protection4
▸BISTENANT PROTECTION PLAN AND NOTES4
06/08/2017440410663Open ↗
05/05/2017440403234Open ↗
04/03/2017421453153Open ↗
Showing 3 of 4 on file for this type
▸Environmental & Asbestos18
▸DOB NOWDEP ACP-5: Asbestos Assessment Report11
08/29/2026Q01287026-I1Open ↗
08/21/2026Q01123307-I1Open ↗
08/21/2026Q01147175-I1Open ↗
Showing 3 of 11 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)3
04/03/2017421453153Open ↗
03/28/2017421453153Open ↗
09/17/2015440252637Open ↗
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'2
05/03/2012420562368Open ↗
06/16/2010420202587Open ↗
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER2
03/01/2011420327364Open ↗
01/13/2009410213745Open ↗
▸Energy Compliance10
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS4
12/12/2018421453153Open ↗
04/03/2017421453153Open ↗
03/28/2017421453153Open ↗
Showing 3 of 4 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS2
12/12/2018421453153Open ↗
03/10/2017440252637Open ↗
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING1
05/05/2017440403234Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
09/17/2015440252637Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
09/17/2015440252637Open ↗
▸BISTECHNICAL REPORT: ENERGY1
05/03/2012420562368Open ↗
▸Inspections & Test Reports3
▸BISTECHNICAL REPORT: RESPONSIBILITY3
06/08/2017440410663Open ↗
05/05/2017440403234Open ↗
09/17/2015440252637Open ↗
▸Approvals, Objections & Sign-offs16
▸BISADMINISTRATIVE OBJECTIONS6
04/03/2017421453153Open ↗
03/28/2017421453153Open ↗
05/03/2012420562368Open ↗
Showing 3 of 6 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST6
01/15/2019421453153Open ↗
01/15/2019421453153Open ↗
01/02/2019421453153Open ↗
Showing 3 of 6 on file for this type
▸BISOIL TANK REMOVAL CERT : LETTER-FO2
03/10/2017440252637Open ↗
03/10/2017440252637Open ↗
▸BISLETTERS - APPRVD FAB CERT-INTENT1
03/10/2017440252637Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
08/14/2012420202587Open ↗
▸Cost, Insurance & Ownership11
▸BISCOST AFFIDAVIT11
01/12/2019421453153Open ↗
01/02/2019421453153Open ↗
12/12/2018421453153Open ↗
Showing 3 of 11 on file for this type
▸Filing & Intake Forms17
▸BISEFILING COVER SHEET6
11/17/2017421453153Open ↗
04/03/2017421453153Open ↗
05/03/2012420562368Open ↗
Showing 3 of 6 on file for this type
▸BISADDITIONAL INFORMATION5
12/01/2018421453153Open ↗
01/26/2017440252637Open ↗
01/24/2017440252637Open ↗
Showing 3 of 5 on file for this type
▸BISBOROUGH INTAKE FORM3
01/08/2019421453153Open ↗
08/28/2018421453153Open ↗
12/13/2017421453153Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET3
06/08/2017440410663Open ↗
05/05/2017440403234Open ↗
09/17/2015440252637Open ↗
▸Other Documents5
▸DOB NOWManufacturer's Specifications2
08/13/2026Q01296124-I1Open ↗
08/13/2026Q01296124-P1Open ↗
▸DOB NOWCalculations2
08/13/2026Q01296124-I1Open ↗
08/13/2026Q01296124-P1Open ↗
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
05/24/2010410213745Open ↗