| Owner | Filings | Most Recent |
|---|---|---|
| Paramount Group | 1,061 | 10/21/2026 |
| 900 Third Ave | 110 | 03/22/2026 |
| Aafo 1301 Properties Owner | 17 | 03/21/2026 |
| Heitman Properties | 11 | 03/21/2026 |
| Agent for Owner 900 Third Avenue | 5 | 03/21/2026 |
| SL Green Realty | 3 | 03/21/2026 |
| For 900 3rd Ave LP Owner | 3 | 03/21/2026 |
| For Progress Partnership | 3 | 03/21/2026 |
| JMB Properties | 3 | 03/21/2026 |
| JMB Properties Co Aaf Progress | 3 | 03/21/2026 |
| JMB Properties As Agents for Pro | 2 | 03/21/2026 |
| 909 Third Company | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Robert Derector Associates | 94 | 10/19/2026 |
| Loffredo Brooks Architects | 9 | 10/17/2026 |
| TPG Architecture | 11 | 10/01/2026 |
| Ashraf | 2 | 05/06/2026 |
| Office of James Ruderman | 7 | 02/09/2026 |
| Elizabeth Marr | 3 | 01/15/2026 |
| Active Design Group Engineering | 2 | 12/11/2025 |
| Walter P Moore | 1 | 08/21/2025 |
| Vincent J. Liotta P.E | 1 | 08/30/2024 |
| WPM NY Engineers | 2 | 05/15/2024 |
| Stonefield Engineering & Design | 1 | 08/21/2023 |
| The Switzer Group | 2 | 08/18/2023 |
| Michele CYR | 1 | 12/07/2021 |
| French & Parrello Associates | 1 | 10/21/2019 |
| Gensler | 1 | 02/26/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| Codegreen | 58 | 03/21/2026 |
| Metropolis Group | 12 | 03/21/2026 |
| Milrose Consultants | 68 | 03/21/2026 |
| Rizzo Group | 12 | 03/21/2026 |
| AK Consulting Services | 2 | 03/21/2026 |
| EA Design Group | 6 | 03/21/2026 |
| Project Expediters | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Gannon Contracting | General Contractor | 39 | 10/21/2026 |
| A.G.S. Improvements | General Contractor | 13 | 07/08/2026 |
| John Gallin & Son | General Contractor | 10 | 07/08/2026 |
| Par Fire Protection | Fire Protection | 9 | 07/08/2026 |
| Par Plumbing Co | Plumbing | 9 | 07/08/2026 |
| Phase 3 Interiors | General Contractor | 8 | 07/08/2026 |
| A&A Plumbing | Plumbing | 8 | 10/21/2026 |
| JT Magen & Company | General Contractor | 7 | 08/05/2026 |
| Plumbing Works | Plumbing | 5 | 03/22/2026 |
| James E Fitzgerald | General Contractor | 5 | 07/08/2026 |
| Geoffrey A. Lagas & Associates | Plumbing | 5 | 07/08/2026 |
| Icon Interiors | General Contractor | 5 | 07/08/2026 |
| Full Capacity Fire | Fire Protection | 4 | 07/08/2026 |
| Henick-Lane Service | General Contractor | 4 | 04/09/2026 |
| Soh Par Sprinkler | Fire Protection | 3 | 09/16/2026 |
| Sirina Fire Protection | Fire Protection | 3 | 07/08/2026 |
| Clune Construction Co | General Contractor | 3 | 03/21/2026 |
| Lawrence J. Levine | Fire Protection | 2 | 03/21/2026 |
| Call Electric Co | Electrical | 2 | 03/21/2026 |
| Omara Organization | General Contractor | 2 | 03/21/2026 |
| Par Plumbing Co | specialty_contractor | 2 | 03/21/2026 |
| Abco-Peerless Sprinkler | Fire Protection | 2 | 07/08/2026 |
| Bluewater Plumbing & Heating | Plumbing | 2 | 07/08/2026 |
| C.M.S. Electrical Services | Electrical | 2 | 03/21/2026 |
| Kleinknecht Electric Co | Electrical | 2 | 03/22/2026 |
| Difazio Electric NY | Electrical | 2 | 03/22/2026 |
| Preferred Sprinkler and Mechanical | Fire Protection | 2 | 07/08/2026 |
| BNF Contractors | General Contractor | 2 | 03/21/2026 |
| BK Construction Services | Scaffold | 1 | 04/09/2026 |
| Platinum Services NY | Scaffold | 1 | 07/08/2026 |
| Rennon Construction | Scaffold | 1 | 07/08/2026 |
| Star-Delta Electric | Electrical | 1 | 03/21/2026 |
| Zwicker Electric Co | Electrical | 1 | 03/21/2026 |
| Ashland Plumbing | Plumbing | 1 | 07/08/2026 |
| Abco-Peerless Sprinkler | Fire Protection | 1 | 03/21/2026 |
| Five Borough NYC | Fire Protection | 1 | 07/08/2026 |
| Plumbing Works | Fire Protection | 1 | 07/08/2026 |
| Preferred Mechanical | Plumbing | 1 | 07/08/2026 |
| L&K Partners | General Contractor | 1 | 07/08/2026 |
| Grushinsky Pipng & Heating | Fire Protection | 1 | 07/08/2026 |
| Osman | General Contractor | 1 | 07/08/2026 |
| Lab Plumbing & Heating Co | Plumbing | 1 | 07/08/2026 |
| Robert B. Samuels | Electrical | 1 | 03/21/2026 |
| Platinum General Services | General Contractor | 1 | 07/08/2026 |
| Tectonic Builders | General Contractor | 1 | 07/08/2026 |
| Five Borough NYC | Plumbing | 1 | 03/22/2026 |
| Adco Electrical | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Alan Margolin & Associates | 423 | 85 | 10/19/2026 |
| MEP Inspections | 1102 | 15 | 09/16/2026 |
| AK Engineering | 678 | 4 | 07/29/2026 |
| Metric Consulting and Ins | 1803 | 2 | 12/11/2025 |
| AK Consulting Services, I | 6198 | 1 | 10/01/2024 |
| Vincent J. Liotta P. E | 1974 | 1 | 08/30/2024 |
| RI Consulting Services | 8904 | 1 | 06/07/2024 |
| PSI Agency | 254 | 4 | 10/26/2023 |
| Joseph Martines PE | 1428 | 1 | 10/21/2019 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | A&A Plumbing | 10/20/2026 |
| DOB NOW | General Construction | Permit Issued | Gannon Contracting | 10/20/2026 |
| DOB NOW | Plumbing | Permit Issued | A&A Plumbing | 10/07/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Gannon Contracting | 10/06/2026 |
| DOB NOW | General Construction | Permit Issued | Gannon Contracting | 10/06/2026 |
| DOB NOW | Sprinklers | Signed-off | Soh Par Sprinkler | 09/15/2026 |
| DOB NOW | General Construction | Permit Issued | JT Magen & Company | 08/04/2026 |
| DOB NOW | General Construction | Permit Issued | Gannon Contracting | 07/01/2026 |
| DOB NOW | Structural | Permit Issued | Gannon Contracting | 07/01/2026 |
| DOB NOW | Mechanical Systems | Signed-off | Gannon Contracting | 06/11/2026 |
| DOB NOW | General Construction | Permit Issued | Gannon Contracting | 06/11/2026 |
| DOB NOW | Structural | Permit Issued | Gannon Contracting | 06/11/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | Platinum Services NY | 05/07/2026 |
| DOB NOW | General Construction | Permit Issued | Phase 3 Interiors | 03/30/2026 |
| DOB NOW | Plumbing | Permit Issued | Par Plumbing Co | 01/29/2026 |
| DOB NOW | Sprinklers | Signed-off | Lawrence J. Levine | 01/26/2026 |
| DOB NOW | Plumbing | Signed-off | Ashland Plumbing | 12/23/2025 |
| DOB NOW | Mechanical Systems | Signed-off | JT Magen & Company | 12/18/2025 |
| DOB NOW | Structural | Signed-off | JT Magen & Company | 12/18/2025 |
| DOB NOW | General Construction | Signed-off | JT Magen & Company | 12/17/2025 |
| DOB NOW | Structural | Permit Issued | Gannon Contracting | 12/09/2025 |
| DOB NOW | Standpipe | Permit Issued | Preferred Sprinkler and Mechanical | 12/02/2025 |
| DOB NOW | Sprinklers | Permit Issued | Preferred Sprinkler and Mechanical | 12/02/2025 |
| DOB NOW | Structural | Signed-off | JT Magen & Company | 11/07/2025 |
| DOB NOW | Mechanical Systems | Signed-off | JT Magen & Company | 11/07/2025 |
| DOB NOW | General Construction | Signed-off | JT Magen & Company | 11/06/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | Henick-Lane Service | 10/29/2025 |
| DOB NOW | General Construction | Permit Issued | Gannon Contracting | 09/11/2025 |
| DOB NOW | General Construction | Signed-off | Gannon Contracting | 09/11/2025 |
| DOB NOW | Plumbing | Signed-off | Geoffrey A. Lagas & Associates | 08/19/2025 |
| DOB NOW | Sprinklers | Signed-off | Full Capacity Fire | 08/14/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Gannon Contracting | 07/28/2025 |
| DOB NOW | General Construction | Signed-off | Gannon Contracting | 07/25/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Gannon Contracting | 07/11/2025 |
| DOB NOW | Plumbing | Signed-off | A&A Plumbing | 07/09/2025 |
| DOB NOW | Sprinklers | Signed-off | Full Capacity Fire | 07/09/2025 |
| DOB NOW | General Construction | Signed-off | Icon Interiors | 06/24/2025 |
| DOB NOW | Plumbing | Signed-off | A&A Plumbing | 06/23/2025 |
| DOB NOW | Sprinklers | Signed-off | Five Borough NYC | 06/20/2025 |
| DOB NOW | Standpipe | Permit Issued | Full Capacity Fire | 06/18/2025 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 10/19/2026 | — | — | Air Conditioning Systems | Cooling United Cool Air VZWL15G4ATBC 4,200 CFM ×1 |
| 05/15/2026 | Signed-off | JT Magen & Company | Air Conditioning Systems, Ventilation Systems | |
| 09/16/2025 | Permit Issued | Henick-Lane Service | Air Conditioning Systems | Cooling United Cool Air VZWL35G4ATBC-A 14,000 CFM · Wshp ×16 |
| 08/24/2023 | Signed-off | Gannon Contracting | Associated Ducts and Piping, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/16/2026 | — | — | 23 heads |
| 10/01/2026 | — | — | — |
| 09/08/2026 | Permit Issued | Preferred Sprinkler and Mechanical | 2,364 heads |
| 09/08/2026 | Signed-off | Par Fire Protection | 626 heads |
| 07/29/2026 | Signed-off | Soh Par Sprinkler | 11 heads |
| 11/05/2025 | Permit Issued | Preferred Sprinkler and Mechanical | 7 outlets |
| 07/22/2025 | Signed-off | Full Capacity Fire | 129 heads |
| 06/10/2025 | Permit Issued | Full Capacity Fire | 1 outlets |
| 04/15/2025 | Signed-off | Full Capacity Fire | 592 heads |
| 10/10/2024 | Signed-off | Grushinsky Pipng & Heating | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/16/2026 | Permit Issued | A&A Plumbing | Water/Sanitary |
| 10/16/2026 | — | — | — |
| 10/01/2026 | Permit Issued | A&A Plumbing | Water/Sanitary |
| 09/08/2026 | — | — | — |
| 07/29/2026 | Signed-off | Par Plumbing Co | Water/Sanitary |
| 04/02/2026 | Signed-off | Ashland Plumbing | Water/Sanitary |
| 12/11/2025 | Permit Issued | Par Plumbing Co | Water/Sanitary |
| 11/05/2025 | — | — | — |
| 07/22/2025 | — | — | — |
| 04/15/2025 | Signed-off | A&A Plumbing | Water/Sanitary |
| 10/10/2024 | Signed-off | A&A Plumbing | Water/Sanitary |
| 02/23/2022 | Signed-off | Geoffrey A. Lagas & Associates | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/10/2026 | Complete | Usis Electric | — |
| 05/11/2026 | Permit Issued | Kleinknecht Electric Co | General Wiring |
| 06/23/2025 | Permit Issued | Campbell & Dawes Ltd Electric | General Wiring |
| 05/02/2025 | Complete | Matros Automated Electrical | General Wiring |
| 04/16/2025 | Permit Issued | Kleinknecht Electric Co | General Wiring |
| 01/10/2025 | Complete | Allstate Electrical Cont | General Wiring |
| 11/05/2024 | Permit Issued | Amsterdam Electric | — |
| 05/17/2024 | Permit Issued | High Quality Electric of | — |
| 10/20/2023 | Complete | T. Dirusso Electrical Cont | General Wiring |
| 08/21/2023 | Complete | H. & L. Electric | General Wiring |
| 06/16/2023 | Complete | P.E. Stone | General Wiring |
| 04/07/2023 | Complete | Kleinknecht Electric Co | General Wiring |
| 07/21/2022 | Permit Issued | Nead Electric | General Wiring |
| 07/08/2022 | Complete | Nead Electric | General Wiring |
| 05/10/2021 | Permit Issued | Difazio Electric NY | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/09/2026 | Permit Issued | Gannon Contracting | Steel |
| 12/11/2025 | Signed-off | JT Magen & Company | Steel, Concrete |
| 11/24/2025 | Permit Issued | Gannon Contracting | Steel |
| 10/31/2025 | Signed-off | JT Magen & Company | Steel |
| 05/28/2024 | Permit Issued | A.G.S. Improvements | Steel |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/21/2025 | — | — | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/28/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/18/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/24/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/24/2026 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| 06/18/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/18/2026 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 04/15/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/09/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/11/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/25/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 01/07/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/06/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 01/05/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 12/15/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 12/11/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 12/11/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/01/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/23/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/20/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/20/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 10/14/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/10/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/07/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/02/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/27/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/09/2026 | Fire-Resistant Penetrations and Joints | Young Suh | special |
| 10/09/2026 | Sprinkler Systems | Young Suh | special |
| 10/09/2026 | Fire-Resistant Penetrations and Joints | Young Suh | special |
| 10/09/2026 | Post-installed Anchors | Young Suh | special |
| 10/09/2026 | Metering | Young Suh | energy_progress |
| 10/09/2026 | Mechanical Systems | Young Suh | special |
| 10/09/2026 | Interior lighting power | Young Suh | energy_progress |
| 10/09/2026 | Final | Frank Loffredo | progress |
| 10/09/2026 | Final | Young Suh | progress |
| 10/09/2026 | Energy Code Compliance Inspections | Young Suh | progress |
| 10/09/2026 | Maintenance information | Young Suh | energy_progress |
| 10/09/2026 | Post-installed Anchors | Young Suh | special |
| 10/09/2026 | Lighting controls | Young Suh | energy_progress |
| 09/21/2026 | Fire-Resistant Penetrations and Joints | Young Suh | special |
| 09/21/2026 | Final | Young Suh | progress |
| 09/21/2026 | Mechanical Systems | Young Suh | special |
| 09/21/2026 | Fire-Resistant Penetrations and Joints | Young Suh | special |
| 09/21/2026 | Post-installed Anchors | Young Suh | special |
| 09/21/2026 | Final | Thomas Hughes | progress |
| 09/21/2026 | Sprinkler Systems | Young Suh | special |
| 09/21/2026 | Energy Code Compliance Inspections | Young Suh | progress |
| 09/21/2026 | Sprayed fire-resistant materials | Young Suh | special |
| 09/17/2026 | Energy Code Compliance Inspections | Nicolas Crosetto | progress |
| 09/17/2026 | Mechanical Systems | Nicolas Crosetto | special |
| 09/17/2026 | Interior lighting power | Nicolas Crosetto | energy_progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Elecore Properties | Office | Floor 22 | Project M01462877 Project M01462889 Project M01462918 Project M01462926 |
| Kirkland & Ellis | Office | Floors 3, 4, 11, 19–21, 26–30, 33–36 | Project M01321430 Project M01317589 Project M01317816 Project M01317839 Project M01317857 Project M01317935 Project M01300814 Project M01300823 Project M01300829 Project M01302774 Project M01300651 Project M01300755 |
| Macro - Savills | Office | Floor 15 | Project M00910418 Project M00910419 Project M00910417 |
| Kensington Publishing | Office | Floor 26 | Project M00903990 Project M00903999 Project M00904003 |
| Nielsen | Office | Floor 18 | Project M00817351 Project M00817358 Project M00817337 |
| The Economist | Office | Floor 16 | Project M08051099 |
| HMSI | Office | Floor 17 | Project M00266858 Project M00266862 |