| Owner | Filings | Most Recent |
|---|---|---|
| PLATINUM SERVICES NY | 2 | 08/29/2026 |
| BROWN HARRIS STEVENS | 25 | 07/08/2026 |
| BROWN HARRIS STEVENS RESIDENTIAL MA | 16 | 04/09/2026 |
| AM&G WATERPROOFING | 5 | 03/22/2026 |
| SPRING SCAFFOLDING LLC | 5 | 03/22/2026 |
| 920 FIFTH AVENUE | 39 | 03/22/2026 |
| TO OWNER 920 FIFTH AVE | 3 | 03/22/2026 |
| DEBAER | 2 | 03/22/2026 |
| 920 5TH AVENUE | 26 | 03/21/2026 |
| 920 5 AVE | 10 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| BLACK SHEEP ENGINEERING GROUP | 3 | 07/30/2026 |
| ALWAYS FAST SERVICES CORP | 1 | 03/20/2026 |
| ERROL MCINTOSH, R.A., P.C. | 4 | 03/04/2026 |
| KAM CHIU CONSULTING ENGINEER, P.C. | 4 | 03/03/2026 |
| MARK GETTYS ARCHITECT, P.L.L.C. | 2 | 01/22/2026 |
| HANINGTON ENGINEERING CONSULTANTS | 2 | 01/21/2026 |
| HANINGTON ENGINEERING CONSUL, LLC | 2 | 01/20/2026 |
| BHH ARCHITECTS | 7 | 09/10/2025 |
| CES ENGINEERING LLC | 1 | 01/02/2025 |
| IDS/R ARCHITECTURE | 1 | 12/19/2024 |
| WISS, JANNEY, ELSTNER ASSOCIATES | 1 | 02/06/2024 |
| GLICKMAN SCHLESINGER ARCHITECTS | 2 | 11/21/2023 |
| ARPAD BAKSA ARCHITECT, P.C. | 1 | 07/10/2023 |
| IP GROUP | 1 | 07/13/2020 |
| DOOLING & COMPANY ARCHITECTS | 1 | 10/08/2019 |
| BAILEYS ENGINEERING PC | 2 | 12/17/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| WILLIAM VITACCO ASSOCIATES | 18 | 03/21/2026 |
| BURNHAM NATIONWIDE INC | 2 | 03/21/2026 |
| NAGAN EX CONSULTANTS | 10 | 03/21/2026 |
| J CALLAHAN CONSULTING | 10 | 03/21/2026 |
| JACK JAFFA & ASSOCIATES | 2 | 03/21/2026 |
| LMS-ACE SERVICES | 1 | 03/21/2026 |
| JAM CONSULTANTS, INC. | 1 | 03/21/2026 |
| AE DESIGN SOLUTION | 6 | 03/21/2026 |
| DVA Advisors | 1 | 03/21/2026 |
| NY EXPEDITERS | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| DSA BUILDERS INC | General Contractor | 7 | 07/08/2026 |
| EVEREST SCAFFOLDING INC | General Contractor | 3 | 07/08/2026 |
| CS BRIDGE CORP | General Contractor | 3 | 07/31/2026 |
| WARREN OSTROFF | Electrical | 3 | 03/21/2026 |
| INTER RENOVATION INC | General Contractor | 3 | 03/21/2026 |
| RUCKERCORP INC | General Contractor | 3 | 07/08/2026 |
| REIS EY, INC | General Contractor | 3 | 09/09/2026 |
| SPRING SCAFFOLDING LLC | General Contractor | 3 | 03/21/2026 |
| LICO CONTRACTING INC | General Contractor | 2 | 07/08/2026 |
| ACCURATE MECHANICAL INC | Plumbing | 2 | 07/08/2026 |
| FRANKIE PLBG & HTG L.L.C | Plumbing | 2 | 07/16/2026 |
| FRED SMITH P&H CO INC | Plumbing | 2 | 07/08/2026 |
| PRACTICAL PLBG & HTG INC | Plumbing | 2 | 07/08/2026 |
| FIOCCHI GROUP LLC | General Contractor | 2 | 08/26/2026 |
| WARREN OSTROFF ELEC., INC | Electrical | 2 | 03/22/2026 |
| FREEDOM GS INC | General Contractor | 1 | 04/08/2026 |
| HI-TECH WIRING ELECL SVCS | Electrical | 1 | 03/22/2026 |
| KONTOROUHAS, VASILIOS | Electrical | 1 | 03/21/2026 |
| LEONARD KRITZ | Electrical | 1 | 03/21/2026 |
| POLYPHASE ELECTRIC INC. | Electrical | 1 | 03/22/2026 |
| TOUGH STALLION LLC | Electrical | 1 | 03/21/2026 |
| BIRNBAUM, ALAN | Electrical | 1 | 03/21/2026 |
| PLATINUM SERVICES NY LLC | General Contractor | 1 | 04/09/2026 |
| DONATO PLUMBING, INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| MILROSE CONSULTANTS LLC | 2003 | 7 | 03/04/2026 |
| HOWARD L ZIMMERMAN ARCHIT | 1712 | 3 | 01/22/2026 |
| CROSSCHECK INSPECTION SER | 544 | 2 | 01/02/2025 |
| RYAN SPECIAL ENGINEERING | 2018 | 1 | 02/06/2024 |
| BEASLEY CHIN & HUNDERMAN | 1238 | 1 | 02/06/2024 |
| GLICKMAN SCHLESINGER ARCH | 6768 | 2 | 11/21/2023 |
| DOMANI INSPECTION SERVICE | 843 | 1 | 07/10/2023 |
| IP GROUP | 2542 | 1 | 07/13/2020 |
| INTEGRITY CONSULTING SERV | 666 | 1 | 10/15/2019 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | REIS EY, INC | 09/08/2026 |
| DOB NOW | General Construction | Permit Issued | REIS EY, INC | 09/02/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | CS BRIDGE CORP | 07/30/2026 |
| DOB NOW | Plumbing | Permit Issued | FRANKIE PLBG & HTG L.L.C | 07/15/2026 |
| DOB NOW | General Construction | Permit Issued | FIOCCHI GROUP LLC | 07/14/2026 |
| DOB NOW | General Construction | Permit Issued | FIOCCHI GROUP LLC | 06/09/2026 |
| DOB NOW | General Construction | Permit Issued | DSA BUILDERS INC | 06/09/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | DSA BUILDERS INC | 06/08/2026 |
| DOB NOW | Structural | Permit Issued | DSA BUILDERS INC | 06/05/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | CS BRIDGE CORP | 04/08/2026 |
| DOB NOW | Supported Scaffold | Permit Issued | CS BRIDGE CORP | 04/08/2026 |
| DOB NOW | Supported Scaffold | Signed-off | PLATINUM SERVICES NY LLC | 03/23/2026 |
| DOB NOW | Plumbing | Permit Issued | DONATO PLUMBING, INC | 01/15/2026 |
| DOB NOW | Suspended Scaffold | Signed-off | VERTICAL ACCESS LLC | 11/25/2025 |
| DOB NOW | Plumbing | Permit Issued | FRANKIE PLBG & HTG L.L.C | 07/11/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | DSA BUILDERS | 07/01/2025 |
| DOB NOW | Structural | Permit Issued | DSA BUILDERS | 07/01/2025 |
| DOB NOW | General Construction | Permit Issued | DSA BUILDERS | 07/01/2025 |
| DOB NOW | General Construction | Permit Issued | LICO CONTRACTING INC | 05/28/2025 |
| DOB NOW | General Construction | Permit Issued | REIS EY, INC | 05/22/2025 |
| DOB NOW | General Construction | Signed-off | RUCKERCORP INC | 04/23/2025 |
| DOB NOW | Plumbing | Signed-off | PRACTICAL PLBG & HTG INC | 03/18/2025 |
| DOB NOW | Plumbing | Permit Issued | ANTHONY DISABATO | 02/18/2025 |
| DOB NOW | General Construction | Permit Issued | FREEDOM GS | 01/24/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | KAY WATERPROOFING CORP. | 06/12/2024 |
| DOB NOW | General Construction | Signed-off | RUCKERCORP INC | 04/22/2024 |
| DOB NOW | Structural | Signed-off | INTER RENOVATION INC | 03/13/2024 |
| DOB NOW | General Construction | Signed-off | RUCKERCORP INC | 03/06/2024 |
| DOB NOW | Plumbing | Signed-off | PRACTICAL PLBG & HTG INC | 03/04/2024 |
| DOB NOW | Plumbing | Permit Issued | ANTHONY DISABATO | 05/07/2023 |
| DOB NOW | Plumbing | Signed-off | FRED SMITH P&H CO INC | 07/14/2021 |
| DOB NOW | Plumbing | Signed-off | FRED SMITH P&H CO INC | 07/16/2020 |
| DOB NOW | Structural | Signed-off | LICO CONTRACTING INC | 02/04/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | EVEREST SCAFFOLDING INC | 10/11/2019 |
| DOB NOW | Supported Scaffold | Signed-off | SPRING SCAFFOLDING LLC | 12/17/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | EVEREST SCAFFOLDING INC | 09/12/2018 |
| BIS | MH | ISSUED | LICO CONTRACTING INC | 12/22/2020 |
| BIS | OT | ISSUED | LICO CONTRACTING INC | 12/22/2020 |
| BIS | OT | ISSUED | D REIS CONTRACTING CORP | 12/21/2020 |
| BIS | OT | ISSUED | D REIS CONTRACTING CORP | 12/17/2020 |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/20/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/06/2026 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 05/06/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/14/2025 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 11/13/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 11/13/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/22/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 07/22/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/09/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/26/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/03/2026 | Fire-Resistant Penetrations and Joints | Christopher Drutjons | special |
| 03/03/2026 | Fire-Resistance Rated Construction | Christopher Drutjons | progress |
| 03/03/2026 | Final | BAILEY HECK | progress |
| 03/03/2026 | Post-installed Anchors | Christopher Drutjons | special |
| 02/25/2026 | Mechanical Systems | Christopher Drutjons | special |
| 02/25/2026 | Fire-Resistant Penetrations and Joints | Christopher Drutjons | special |
| 02/25/2026 | Final | Christopher Drutjons | progress |
| 01/24/2026 | Tenant Protection Plan Compliance | — | special |
| 01/24/2026 | Fire-Resistant Penetrations and Joints | Jon Colatrella | special |
| 01/24/2026 | Final | Mark Gettys | progress |
| 01/24/2026 | Post-installed Anchors | Jon Colatrella | special |
| 01/09/2026 | Structural Steel - Details | Benjamin Plotnick | special |
| 01/09/2026 | Sprayed fire-resistant materials | Benjamin Plotnick | special |
| 01/09/2026 | Structural Steel - Welding | Benjamin Plotnick | special |
| 12/15/2025 | Tenant Protection Plan Compliance | Benjamin Plotnick | special |
| 12/15/2025 | Final | Benjamin Plotnick | progress |
| 12/15/2025 | Structural Stability – Alterations of existing buildings | Benjamin Plotnick | special |
| 12/08/2025 | Post-installed Anchors | — | special |
| 11/17/2025 | Tenant Protection Plan Compliance | — | special |
| 11/13/2025 | Fire-Resistant Penetrations and Joints | Jon Colatrella | special |
| 11/13/2025 | Post-installed Anchors | Jon Colatrella | special |
| 11/13/2025 | Final | Mark Gettys | progress |
| 09/04/2025 | Tenant Protection Plan Compliance | — | special |
| 09/04/2025 | Fire-Resistant Penetrations and Joints | Christopher Drutjons | special |
| 09/04/2025 | Mechanical Systems | Christopher Drutjons | special |