Over six families without stores
957 WOODYCREST AVENUE
BRONX · BIN 2003187
💬 Discuss this project
1924Year Built
5Stories
C1Building Class
R7-1Zoning
60,600 sfGross Floor Area
52Units
LL97 CoveredRent Stabilized76 Active Violations 74 unresolved · 2 paperwork only ▸FISP: No Report FiledFDNY Report ↗
Over six families without stores · Owner of record: HP 950-957 Woodycrest Ave Housing Develo Pment Fund · 11,555 sf lot · 5.24 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingEquipmentGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofLimited exterior masonry repairs facade repair1p · 1 filing · 10 docs
Floor 515p · 1 filing · 20 docs
Floor 413p · 1 filing · 20 docs
Floor 313p · 1 filing · 20 docs
Floor 213p · 1 filing · 20 docs
Floor 114p · 1 filing · 20 docs
Site & exteriorHeavy duty sidewalk shed installation21p · 4 filings · 20 docs
Filed — no permit issuedInstallation of heavy duty sidewalk shed8p · 2 filings · 15 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
J Wasser & Co1207/08/2026
963 Woodycrest Ave503/21/2026
HP 950-957 Woodycrest Ave Housing Develo Pment Fund203/22/2026
957 Woodycrest DS203/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
07/12/2019$9.3M—957 WOODYCREST DS LLC → ICER OF WOODYCREST AVE LLC$153/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Kma Designs106/02/2025
Bangash Associates112/18/2024
Ashraf207/30/2024
Syed Engineering512/22/2022
Mohammad Ahead, PE109/13/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Architect203/21/2026
Arsenal Building Consultants203/21/2026
Express Filing803/21/2026
Kma Designs603/21/2026
Sheikh Expediting203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
J & G Construction ServicesScaffold708/26/2026
Lime Stone BuildersGeneral Contractor207/08/2026
J & G Construction ServicesGeneral Contractor104/09/2026
JRS Contracting USAGeneral Contractor103/21/2026
J G Construction ServicesPlumbing104/09/2026
All Empire BuildingScaffold107/08/2026
Clean Tech MechanicalPlumbing107/08/2026
BHB ConstructionGeneral Contractor103/21/2026
Abatement SolutionsGeneral Contractor208/12/2015
Ameri RestorationGeneral Contractor105/04/2012
Pat Sementa P & HPlumbing207/31/2014
Tri-Circle EnterprisesGeneral Contractor107/17/2009
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Mohammad Ahead - Professi9286106/02/2025
Bangash Associates8488112/18/2024
Syed Engineering7054212/22/2022
Arc-HI-Tech Associates6963110/10/2021
Sia Inspections7306205/31/2021
Building Lifecycle
02/20/2029
Facade inspection report due (FISP Cycle 9, sub-cycle C)
The filing window opened 02/21/2027. No Cycle 9 filing on record yet
11/10/2026
Permit expired, never signed off — Sidewalk Shed
The city's record still shows this permit as issued, with no sign-off on its filing
X01087576-I1-SH
08/14/2026
§ 27-2005 HMC: PROPERLY REPAIR OR REPLACE THE BROKEN OR DEFECTIVE UPPER WINDOW SASH BALANCE 1ST WINDOW FROM SOUTH AT WEST WALL IN THE 4th ROOM FROM…
HPD violation · open
08/14/2026
§ 27-2005 ADM CODE PROPERLY REPAIR WITH SIMILAR MATERIAL THE BROKEN OR DEFECTIVE WOOD SUB FLOOR IN THE KITCHEN LOCATED AT APT 10A, 2nd STORY, 1st…
HPD violation · open
08/12/2026
Permit renewed — Sidewalk Shed
Renewed without changes
X01087576-I1-SH
276 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSidewalk ShedPermit IssuedJ & G Construction Services08/12/2026
DOB NOWSupported ScaffoldPermit IssuedJ & G Construction Services06/09/2025
DOB NOWGeneral ConstructionPermit IssuedJ & G Construction Services01/30/2025
DOB NOWSidewalk ShedPermit IssuedJ & G Construction Services08/08/2024
DOB NOWSidewalk ShedSigned-offJ & G Construction Services10/13/2022
DOB NOWPlumbingSigned-offClean Tech Mechanical05/31/2022
DOB NOWGeneral ConstructionSigned-offLime Stone Builders05/19/2022
DOB NOWSidewalk ShedSigned-offJ & G Construction Services05/10/2022
DOB NOWGeneral ConstructionSigned-offLime Stone Builders12/16/2021
DOB NOWSidewalk ShedSigned-offAll Empire Building12/30/2019
BISOTISSUEDJRS Contracting USA02/26/2020
BISOTISSUEDAbatement Solutions08/12/2015
BISOTISSUEDAbatement Solutions08/12/2015
BISPLISSUEDPat Sementa P & H07/31/2014
BISBLISSUEDPat Sementa P & H07/31/2014
BISOTISSUEDAmeri Restoration05/04/2012
BISEQISSUEDB H & B Construction04/04/2012
BISOTISSUEDTri-Circle Enterprises07/17/2009
BISEQISSUEDJ & G General Contracting06/18/2009
BISFSISSUEDNational Grid Energy Management02/11/1998
4 projects · most recent 03/16/2022
General Wiring
FiledStatusContractorScope
03/16/2022CompleteIrwin Electr'l Contractors, IGeneral Wiring
03/22/2021Permit IssuedRichard Neu—
08/27/2020Permit IssuedDeltex Electrical Cont. IGeneral Wiring
12/26/2019CompleteRichard Neu—
3 projects · most recent 06/02/2025
Sidewalk Shed Scaffold
FiledStatusContractorScope
06/02/2025Permit IssuedJ & G Construction ServicesScaffold
07/30/2024Permit IssuedJ & G Construction ServicesSidewalk Shed
04/04/2021——Sidewalk Shed
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
01/03/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
08/05/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 31
DateRequirementInspectorRole
06/02/2025Post-installed AnchorsMOHAMMAD AHEADspecial
11/25/2024Tenant Protection Plan ComplianceFAZAL BANGASHspecial
11/25/2024FinalFAZAL BANGASHprogress
11/25/2024Structural Stability – Alterations of existing buildingsFAZAL BANGASHspecial
11/25/2024MasonryFAZAL BANGASHspecial
12/21/2022Fire-Resistant Penetrations and JointsRAFI HAMIDspecial
12/21/2022Energy Code Compliance InspectionsRAFI HAMIDprogress
01/05/2022Interior lighting powerRAFI HAMIDenergy_progress
01/05/2022Structural Stability – Alterations of existing buildingsSOFIA KAPELYANspecial
01/05/2022Energy Code Compliance InspectionsJeff Akermanprogress
01/05/2022FinalSOFIA KAPELYANprogress
01/05/2022Fire-Resistance Rated ConstructionJeff Akermanprogress
01/05/2022Fire-Resistant Penetrations and JointsSOFIA KAPELYANspecial
01/05/2022Lighting in dwelling unitsRAFI HAMIDenergy_progress
10/09/2021Energy Code Compliance InspectionsIGOR LISOVENKOprogress
10/09/2021FinalIGOR LISOVENKOprogress
09/29/2021Maintenance informationIGOR LISOVENKOenergy_progress
09/29/2021Concrete - Cast-In-PlaceIGOR LISOVENKOspecial
09/29/2021Air barrier - visual inspectionIGOR LISOVENKOenergy_progress
09/29/2021Structural Stability – Alterations of existing buildingsIGOR LISOVENKOspecial
09/29/2021Fire-Resistant Penetrations and JointsIGOR LISOVENKOspecial
09/29/2021MasonryIGOR LISOVENKOspecial
09/29/2021Fenestration air leakageIGOR LISOVENKOenergy_progress
07/20/2021Interior lighting powerRAFI HAMIDenergy_progress
07/20/2021Lighting in dwelling unitsRAFI HAMIDenergy_progress