| Owner | Filings | Most Recent |
|---|---|---|
| JUDSON REALTY | 33 | 07/08/2026 |
| MYKITA SHOP NY | 6 | 07/08/2026 |
| GSL ENTERPRISES | 1 | 03/22/2026 |
| MYKITA SHOP MADISON AVENUE LLC | 1 | 03/22/2026 |
| INTERSYSTEMS | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| FRANK NIGRO ARCHITECT, P.C. | 3 | 06/28/2023 |
| MOTTOLA RINI ENGINEERS | 1 | 04/26/2021 |
| METHOD DESIGN ARCHITECTURE + URBANI | 1 | 05/19/2020 |
| JAMES P. STROKE, PE | 1 | 10/03/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| S M EXPEDITING | 8 | 03/21/2026 |
| DY EXPEDITING | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| D.P. & SON PAINTING INC | General Contractor | 6 | 07/08/2026 |
| WKR CONSTRUCTION, INC | General Contractor | 4 | 07/08/2026 |
| METROPOLITAN MECH CORP | General Contractor | 3 | 03/21/2026 |
| UPDATE SYSTEMS ELECTRICAL | Electrical | 2 | 03/22/2026 |
| SENAD MEHOVIC | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| FRANK NIGRO ARCHITECT PC | 3211 | 2 | 11/29/2022 |
| MOTTOLA RINI ENGINEERS, P | 3251 | 1 | 04/26/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | D.P. & SON PAINTING INC | 07/24/2024 |
| DOB NOW | Construction Fence | Signed-off | D.P. & SON PAINTING INC | 08/08/2023 |
| DOB NOW | General Construction | Signed-off | D.P. & SON PAINTING INC | 07/28/2023 |
| DOB NOW | General Construction | Signed-off | D.P. & SON PAINTING INC | 01/11/2023 |
| DOB NOW | Mechanical Systems | Signed-off | WKR CONSTRUCTION, INC | 05/03/2021 |
| DOB NOW | Construction Fence | Signed-off | WKR CONSTRUCTION, INC | 01/15/2021 |
| DOB NOW | Construction Fence | Signed-off | WKR CONSTRUCTION, INC | 09/01/2020 |
| DOB NOW | Mechanical Systems | Signed-off | METROPOLITAN MECH CORP | 10/24/2019 |
| BIS | OT | ISSUED | WKR CONSTRUCTION, INC | 09/17/2020 |
| BIS | OT | ISSUED | WKR CONSTRUCTION, INC | 04/08/2020 |
| BIS | OT | ISSUED | WKR CONSTRUCTION, INC | 03/20/2020 |
| BIS | OT | ISSUED | JAMES E FITZGERALD INC | 03/12/2020 |
| BIS | MH | ISSUED | JAMES E FITZGERALD INC | 03/12/2020 |
| BIS | PL | ISSUED | ACCURATE MECHANICAL INC | 10/11/2019 |
| BIS | MH | ISSUED | JAMES E FITZGERALD INC | 09/26/2019 |
| BIS | OT | ISSUED | JAMES E FITZGERALD INC | 09/26/2019 |
| BIS | MH | ISSUED | JAMES E FITZGERALD INC | 09/03/2019 |
| BIS | OT | ISSUED | JAMES E FITZGERALD INC | 09/03/2019 |
| BIS | MH | ISSUED | JUDSON REALTY, LLC | 02/08/2019 |
| BIS | — | ISSUED | FORLIANO CONSTRUCTION MAN | 12/19/2018 |
| BIS | OT | ISSUED | FORLIANO CONSTRUCTION MAN | 10/24/2018 |
| BIS | OT | ISSUED | FORLIANO CONSTRUCTION MAN | 10/19/2018 |
| BIS | OT | ISSUED | FORLIANO CONSTRUCTION MAN | 10/19/2018 |
| BIS | OT | ISSUED | BRIAN ILL DEVELOPMENT LLC | 06/26/2015 |
| BIS | EQ | ISSUED | COLGATE ENTERPRISE CORP | 05/15/2015 |
| BIS | OT | ISSUED | JUDSON REALTY, LLC | 04/14/2015 |
| BIS | OT | ISSUED | JUDSON REALTY, LLC | 03/24/2014 |
| BIS | OT | ISSUED | JUDSON REALTY, LLC | 04/11/2013 |
| BIS | EQ | ISSUED | INTERSYSTEMS CORPORATION | 08/01/2012 |
| BIS | OT | ISSUED | JUDSON REALTY, LLC | 07/19/2012 |
| BIS | PL | ISSUED | A+ INSTALLATIONS CORP | 10/21/2011 |
| BIS | OT | ISSUED | MICHILLI INC | 09/23/2011 |
| BIS | MH | ISSUED | MICHILLI INC | 09/23/2011 |
| BIS | OT | ISSUED | MICHILLI INC | 09/23/2011 |
| BIS | MH | ISSUED | SMI CONSTRUCTION MANGEMENT | 05/07/2008 |
| BIS | PL | ISSUED | N.PAGANO P&H CONTR LTD | 10/02/2007 |
| BIS | MH | ISSUED | SMI CONSTRUCTION MANGEMENT | 09/11/2007 |
| BIS | OT | RE-ISSUED | SMI CONSTRUCTION MANGEMENT | 05/04/2007 |
| BIS | OT | RE-ISSUED | SMI CONSTRUCTION MANGEMENT | 05/04/2007 |
| BIS | OT | ISSUED | STEVE MARK INC | 01/12/2007 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/16/2021 | Complete | UPDATE SYSTEMS ELECTRICAL | General Wiring |
| 12/01/2020 | Permit Issued | E & M ELECTRICAL NY CORP | General Wiring |
| 02/12/2019 | Complete | ECNY ELEC'L CONTR'S, INC | General Wiring |
| 10/03/2018 | Complete | IDEAL ELEC & HVAC CO INC | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/07/2023 | Air barrier - visual inspection | FRANK NIGRO | energy_progress |
| 06/07/2023 | Fenestration and door U-factor and product ratings | FRANK NIGRO | energy_progress |
| 06/07/2023 | Insulation placement and R values | FRANK NIGRO | energy_progress |
| 06/07/2023 | Energy Code Compliance Inspections | FRANK NIGRO | progress |
| 06/06/2023 | Final | FRANK NIGRO | progress |
| 11/23/2022 | Metering | FRANK NIGRO | energy_progress |
| 11/23/2022 | Structural Stability – Alterations of existing buildings | FRANK NIGRO | special |
| 11/23/2022 | Fire-Resistant Penetrations and Joints | FRANK NIGRO | special |
| 11/23/2022 | Energy Code Compliance Inspections | FRANK NIGRO | progress |
| 11/23/2022 | Fire-Resistance Rated Construction | FRANK NIGRO | progress |
| 11/23/2022 | Interior lighting power | FRANK NIGRO | energy_progress |
| 11/23/2022 | Lighting controls | FRANK NIGRO | energy_progress |
| 10/04/2022 | Final | FRANK NIGRO | progress |
| 02/11/2021 | HVAC-R and service water heating system controls | Anthony Rini, III | energy_progress |
| 02/11/2021 | HVAC-R and service water heating equipment | Anthony Rini, III | energy_progress |
| 02/11/2021 | HVAC-R and service water piping design and insulation | Anthony Rini, III | energy_progress |
| 02/10/2021 | Energy Code Compliance Inspections | Anthony Rini, III | progress |
| 02/10/2021 | Final | Anthony Rini, III | progress |
| 02/10/2021 | Mechanical Systems | Anthony Rini, III | special |
| 05/12/2020 | Final | Demetrios Comodromos | progress |
| 10/02/2019 | HVAC insulation and sealing | FRANK NIGRO | energy_progress |
| 10/02/2019 | HVAC and service water heating equipment | FRANK NIGRO | energy_progress |
| 10/02/2019 | HVAC and service water heating system controls | FRANK NIGRO | energy_progress |
| 09/26/2019 | Mechanical Systems | FRANK NIGRO | special |
| 09/26/2019 | Final | FRANK NIGRO | progress |