| Owner | Filings | Most Recent |
|---|---|---|
| 964 DEAN ACQUISITION GROUP | 30 | 07/08/2026 |
| TOPLINE NYC CONTRACTING | 3 | 03/22/2026 |
| DEAN GRIECO HOLDING CORP | 3 | 03/22/2026 |
| 964 DEAN ST CORP | 3 | 03/22/2026 |
| D T DEAN ST REALTY | 5 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| FABRICA ARCHITECTURE STUDIO | 4 | 05/19/2025 |
| BO LEE ARCHITECT PC | 1 | 10/21/2024 |
| RONALD VARGO ARCHITECT | 16 | 07/03/2024 |
| SILMAN | 4 | 02/29/2024 |
| MOHAMMAD AHEAD, PE | 1 | 03/07/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| BIG ORANGE EXPEDITING | 36 | 03/21/2026 |
| ADVANCED BUILDERS SERVICES | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| INFINITI ESC PLUMBING COR | Plumbing | 8 | 07/08/2026 |
| PATRICIA CAESAR THOMAS | Electrical | 6 | 03/21/2026 |
| KAY PLUMBING INC | General Contractor | 5 | 03/22/2026 |
| TOPLINE NYC CONTRACTING | General Contractor | 3 | 03/21/2026 |
| EDMUND S. JOSEPH | General Contractor | 3 | 03/21/2026 |
| MKSSKR CONSULTING SERVICE | General Contractor | 3 | 03/21/2026 |
| TOMCHRIS CONTRACTING CORP | General Contractor | 2 | 03/21/2026 |
| RONALD VARGO | Electrical | 1 | 03/21/2026 |
| GREGG NY PLUMBING, INC | Plumbing | 1 | 03/22/2026 |
| CARY P O'BRIEN DESIGN LLC | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| RHL ENGINEERING, LLC | 712 | 4 | 05/19/2025 |
| RONALD VARGO ARCHITECT | 848 | 17 | 07/03/2024 |
| HAMANN ENGINEERING, PLLC | 4949 | 4 | 04/15/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | CARY P O'BRIEN DESIGN LLC | 11/12/2024 |
| DOB NOW | General Construction | Signed-off | EDMUND S. JOSEPH | 10/29/2024 |
| DOB NOW | Boiler Equipment | Signed-off | INFINITI ESC PLUMBING COR | 05/28/2024 |
| DOB NOW | Boiler Equipment | Signed-off | INFINITI ESC PLUMBING COR | 05/17/2024 |
| DOB NOW | Boiler Equipment | Signed-off | INFINITI ESC PLUMBING COR | 05/17/2024 |
| DOB NOW | Structural | Signed-off | TOMCHRIS CONTRACTING CORP | 05/14/2024 |
| DOB NOW | Mechanical Systems | Signed-off | MKSSKR CONSULTING SERVICE | 02/29/2024 |
| DOB NOW | Boiler Equipment | Signed-off | INFINITI ESC PLUMBING COR | 12/27/2023 |
| DOB NOW | Plumbing | Signed-off | INFINITI ESC PLUMBING COR | 12/08/2023 |
| DOB NOW | Plumbing | Signed-off | INFINITI ESC PLUMBING COR | 11/11/2022 |
| DOB NOW | Boiler Equipment | Signed-off | INFINITI ESC PLUMBING COR | 08/02/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | TOPLINE NYC CONTRACTING | 04/07/2022 |
| DOB NOW | Plumbing | Signed-off | INFINITI ESC PLUMBING COR | 11/12/2021 |
| BIS | SP | ISSUED | VILLAGE P & H NY INC | 02/29/2024 |
| BIS | — | ISSUED | EDMUND S. JOSEPH | 12/04/2023 |
| BIS | — | ISSUED | MICLAW CONTRACTING INC | 07/12/2022 |
| BIS | SP | ISSUED | VILLAGE P & H NY INC | 11/12/2021 |
| BIS | — | ISSUED | MICLAW CONTRACTING INC | 08/17/2021 |
| BIS | OT | ISSUED | WT BUILDERS LLC | 09/28/2015 |
| BIS | MH | ISSUED | DAVID JABLON | 02/15/2001 |
| BIS | PL | ISSUED | DAVID JABLON | 02/15/2001 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/10/2024 | Complete | PW & SONS ELECTRICAL CORP | General Wiring |
| 07/22/2024 | Complete | RICHARD NEU | General Wiring |
| 07/05/2022 | Complete | STAR ELEC'L CONTRACTORS C | — |
| 03/11/2022 | Complete | RICHARD NEU | — |
| 09/08/2021 | Complete | GOLDMAN ELECTRIC CORP. | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/31/2024 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| 12/14/2023 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 10/17/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/19/2021 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 11/19/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/19/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/29/2025 | Final | Carla Fuquene-Pena | progress |
| 05/29/2025 | Fire-Resistant Penetrations and Joints | Vincent Gentile | special |
| 05/29/2025 | Interior lighting power | Vincent Gentile | energy_progress |
| 12/03/2024 | Fire-Resistant Penetrations and Joints | Vincent Gentile | special |
| 12/03/2024 | Interior lighting power | Vincent Gentile | energy_progress |
| 10/21/2024 | Lighting controls | BO LEE | energy_progress |
| 10/21/2024 | Interior lighting power | BO LEE | energy_progress |
| 10/18/2024 | Final | BO LEE | progress |
| 10/16/2024 | Interior lighting power | Vincent Gentile | energy_progress |
| 10/16/2024 | Fire-Resistant Penetrations and Joints | Vincent Gentile | special |
| 06/15/2024 | Fire-Resistant Penetrations and Joints | Ronald Vargo | special |
| 06/15/2024 | Energy Code Compliance Inspections | Ronald Vargo | progress |
| 06/15/2024 | Fire-Resistance Rated Construction | Ronald Vargo | progress |
| 06/15/2024 | Maintenance information | Ronald Vargo | energy_progress |
| 05/08/2024 | Shutoff dampers | Ronald Vargo | energy_progress |
| 05/08/2024 | HVAC insulation and sealing | Ronald Vargo | energy_progress |
| 05/08/2024 | HVAC and service water heating system controls | Ronald Vargo | energy_progress |
| 05/08/2024 | HVAC and service water heating equipment | Ronald Vargo | energy_progress |
| 05/08/2024 | Fire-Resistant Penetrations and Joints | Ronald Vargo | special |
| 05/08/2024 | Heating Systems | Ronald Vargo | special |
| 05/08/2024 | Mechanical Systems | Ronald Vargo | special |
| 05/08/2024 | Final | Ronald Vargo | progress |
| 04/22/2024 | Heating Systems | CARL HAMANN | special |
| 04/22/2024 | Fire-Resistant Penetrations and Joints | Ronald Vargo | special |
| 04/09/2024 | Final | Ronald Vargo | progress |