← Back
Elevator apt, fireproof without stores
97-11 HORACE HARDING EXPWY
QUEENS · BIN 4047334
💬 Discuss this project
1963Year Built
16Stories
D3Building Class
R6Zoning
235,000 sfGross Floor Area
232Units
LL97 CoveredRent Stabilized27 Open Violations ▸FISP: SWARMP
Elevator apt, fireproof without stores · 48,120 sf lot · 4.88 FAR built · Flood zone X
Locations of Work
Architecture
Floor 184p · 1 filing · 6 docs
Floor 174p · 1 filing · 6 docs
Floor 164p · 1 filing · 6 docs
Floor 154p · 1 filing · 6 docs
Floor 144p · 1 filing · 6 docs
Floor 134p · 1 filing · 6 docs
Floor 124p · 1 filing · 6 docs
Floor 114p · 1 filing · 6 docs
Floor 104p · 1 filing · 6 docs
Floor 94p · 1 filing · 6 docs
Floor 84p · 1 filing · 6 docs
Floor 74p · 1 filing · 6 docs
Floor 64p · 1 filing · 6 docs
Floor 54p · 1 filing · 6 docs
Floor 44p · 1 filing · 6 docs
Floor 34p · 1 filing · 6 docs
Floor 24p · 1 filing · 6 docs
Floor 1
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
LEFRAKORG507/08/2026
SINGAPORE LEASING LIMITED203/22/2026
LEFRAK CITY MAINTENANCE SERVICES803/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PAUL PERDEK, PROF. ENG. PLLC111/27/2023
SETH P. ROYE ARCHITECT PC110/11/2023
BAILEYS ENGINEERING PC103/09/2018
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
AE DESIGN SOLUTION403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ARSENAL SCAFFOLD INCGeneral Contractor407/08/2026
EMPIRE NY INSTALLATIONS INCGeneral Contractor303/21/2026
MILLENIUM RESTORATION CORPGeneral Contractor203/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
UNITED ENGINEERING OF NY9157203/28/2024
SETH P ROYE ARCHITECT PC8554110/11/2023
TROLYDIA TESTING & INSPEC4422110/11/2023
Building Lifecycle
All (101)Filed (5)Permit Issued (7)Signed Off (3)Facade (FISP) (12)Violation (60)Objection (2)Special Inspection (12)
05/06/2026
Violation issued (HPD, closed)
C
03/01/2026
Violation issued (HPD, closed)
C
03/01/2026
Violation issued (HPD, closed)
C
02/02/2026
Violation issued (HPD, closed)
C
02/02/2026
Violation issued (HPD, closed)
C
02/02/2026
Violation issued (HPD, closed)
C
01/27/2026
Violation issued (HPD, closed)
C
01/27/2026
Violation issued (HPD, closed)
C
12/25/2025
Violation issued (HPD, closed)
B
12/25/2025
Violation issued (HPD, closed)
C
11/28/2025
Violation issued (HPD, closed)
C
09/26/2025
Violation issued (HPD, closed)
A
09/14/2025
Violation issued (HPD, closed)
C
04/24/2025
Violation issued (HPD, closed)
A
04/24/2025
Violation issued (HPD, closed)
A
04/11/2025
Violation issued (HPD, closed)
B
04/11/2025
Violation issued (HPD, closed)
B
04/11/2025
Violation issued (HPD, closed)
B
04/10/2025
Violation issued (HPD, open)
C
02/22/2025
Violation issued (HPD, closed)
C
02/22/2025
Violation issued (HPD, closed)
C
01/28/2025
Violation issued (HPD, closed)
C
01/26/2025
Violation issued (HPD, open)
C
01/26/2025
Violation issued (HPD, closed)
C
01/26/2025
Violation issued (HPD, closed)
C
01/05/2025
Violation issued (HPD, closed)
C
01/05/2025
Violation issued (HPD, closed)
B
01/05/2025
Violation issued (HPD, closed)
C
01/05/2025
Violation issued (HPD, closed)
B
01/03/2025
Violation issued (HPD, open)
B
01/03/2025
Violation issued (HPD, closed)
C
01/03/2025
Violation issued (HPD, open)
B
01/03/2025
Violation issued (HPD, closed)
C
01/03/2025
Violation issued (HPD, closed)
C
01/03/2025
Violation issued (HPD, open)
C
12/24/2024
Violation issued (HPD, closed)
A
11/17/2024
Violation issued (HPD, closed)
C
11/17/2024
Violation issued (HPD, closed)
C
11/17/2024
Violation issued (HPD, closed)
B
11/17/2024
Violation issued (HPD, closed)
B
10/25/2024
Violation issued (HPD, closed)
B
10/25/2024
Violation issued (HPD, closed)
A
10/25/2024
Violation issued (HPD, closed)
B
09/09/2024
Violation issued (HPD, open)
C
09/09/2024
Violation issued (HPD, closed)
B
09/09/2024
Violation issued (HPD, closed)
B
09/09/2024
Violation issued (HPD, closed)
C
09/09/2024
Violation issued (HPD, closed)
B
08/21/2024
Violation issued (HPD, closed)
C
07/09/2024
Violation issued (HPD, closed)
C
07/09/2024
Violation issued (HPD, closed)
A
06/18/2024
Signed off — Alteration
Facade Restoration
Q00992501-I1
06/11/2024
Signed off — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Q00951144-I1
05/03/2024
Violation issued (HPD, closed)
A
04/17/2024
Permit issued — Suspended Scaffold
Q00992501-P1-SC
04/17/2024
Objection resolved — Addressed
04/17/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
VIVEK PATEL
04/17/2024
Special inspection requirement — Post-installed Anchors
VIVEK PATEL
04/17/2024
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
VIVEK PATEL
04/16/2024
Objection raised — Other
Latest 60 of 101 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSuspended ScaffoldPermit IssuedMILLENIUM RESTORATION COR04/17/2024
DOB NOWSuspended ScaffoldSigned-offMILLENIUM RESTORATION COR01/22/2024
DOB NOWSidewalk ShedSigned-offEMPIRE NY INSTALLATIONS I11/28/2023
DOB NOWGeneral ConstructionPermit IssuedMILLENIUM RESTORATION CORP11/16/2023
DOB NOWSidewalk ShedSigned-offARSENAL SCAFFOLD INC06/11/2018
DOB NOWSidewalk ShedSigned-offARSENAL SCAFFOLD INC03/29/2018
DOB NOWSidewalk ShedSigned-offARSENAL SCAFFOLD INC03/12/2018
BISOTISSUEDJORICH CONSTRUCTION CO IN06/15/2018
BISPLISSUEDWEXLER PLUMBING LLC08/31/2017
BISOTISSUEDV.R.P. CONSULTING INC08/25/2017
BISPLISSUEDWEXLER PLUMBING LLC04/17/2017
BISOTISSUEDV.R.P. CONSULTING INC03/27/2017
BISPLISSUEDVELOCITY PLUMBING & HEAT02/08/2017
BISOTISSUEDTATAMS MANAGEMENT CORP02/01/2017
BISOTISSUEDRICONDA MAINTENANCE INC09/13/2016
BISOTISSUEDRICONDA MAINTENANCE INC07/05/2016
BISEQISSUEDEVEREST SCAFFOLDING INC05/13/2016
BISOTISSUEDRICONDA MAINTENANCE INC05/17/2013
BISEQISSUEDEVEREST SCAFFOLDING INC04/29/2013
BISOTISSUEDSEA BRIGHT SOLAR LLC08/16/2011
3 projects · most recent 10/18/2024
FiledStatusContractorScope
10/18/2024Permit IssuedHYLAN DATACOM & ELECL LLC1 meters, 1 new_meters
11/28/2023Permit IssuedMEGA ELEC'L CONTR'G, INC—
03/08/2018CompleteNASH ELECTRIC SERVICES IN—
▾Special Inspection Requirements (DOB NOW) — 12
DateRequirementInspectorRole
04/17/2024Structural Stability – Alterations of existing buildingsVIVEK PATELspecial
04/17/2024Post-installed AnchorsVIVEK PATELspecial
04/17/2024Alternative Materials - OTCR Buildings Bulletin NumberVIVEK PATELspecial
03/28/2024Post-installed AnchorsVIVEK PATELspecial
03/28/2024Alternative Materials - OTCR Buildings Bulletin NumberVIVEK PATELspecial
03/28/2024Structural Stability – Alterations of existing buildingsVIVEK PATELspecial
08/14/2023Tenant Protection Plan ComplianceEDWARD TOROSSIANspecial
07/11/2023Fire-Resistant Penetrations and JointsSeth Royespecial
07/11/2023MasonrySeth Royespecial
07/11/2023Energy Code Compliance InspectionsSeth Royeprogress
07/11/2023FinalSeth Royeprogress
03/05/2018FinalPAUL BAILEYprogress
▾Documents — 230 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch5
08/29/2026Q00024429-I1Request digital key ↗
08/24/2026Q00902735-I1Request digital key ↗
08/23/2026Q00951144-I1Request digital key ↗
Showing 3 of 5 on file for this type
▸Applications & Permits38
▸BISPLAN / WORK APPROVAL APPLICATION20
02/08/2018440392460Open ↗
01/30/2018440428413Open ↗
10/06/2017440428413Open ↗
Showing 3 of 20 on file for this type
▸BISWORK PERMIT APPLICATION15
06/21/2018421423891Open ↗
08/31/2017440428413Open ↗
08/24/2017440428413Open ↗
Showing 3 of 15 on file for this type
▸BISNon-Directive 14 Construction Sign Off Including Sign Applications3
12/28/2017440392460Open ↗
12/28/2017440428413Open ↗
12/28/2017440376497Open ↗
▸Seals & Professional Certifications58
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION23
07/02/2018421423891Open ↗
06/21/2018421423891Open ↗
12/28/2017440392460Open ↗
Showing 3 of 23 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature8
09/02/2026Q00902735-I1Open ↗
09/02/2026Q00902735-I1Open ↗
08/28/2026Q00992501-I1Open ↗
Showing 3 of 8 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT7
08/24/2017440428413Open ↗
03/24/2017440392460Open ↗
01/30/2017440376497Open ↗
Showing 3 of 7 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION5
08/24/2017440428413Open ↗
03/24/2017440392460Open ↗
01/30/2017440376497Open ↗
Showing 3 of 5 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY4
08/24/2017440428413Open ↗
03/24/2017440392460Open ↗
05/11/2016440310842Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST4
04/13/2016421311565Open ↗
03/11/2016421299669Open ↗
10/10/2012420583434Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/13/2026Q00024429-I1Open ↗
08/13/2026Q00951144-I1Open ↗
08/13/2026Q00902735-I1Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM2
10/10/2012420583434Open ↗
Showing 1 of 2 on file for this type
▸DOB NOWProgress Inspector Seal & Signature2
09/02/2026Q00902735-I1Open ↗
08/25/2026Q00024429-I1Open ↗
▸Trade Schedules & Equipment5
▸BISSCHEDULE B - PLUMBING3
08/24/2017440428413Open ↗
03/24/2017440392460Open ↗
01/30/2017440376497Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE2
02/12/2018440392460Open ↗
02/01/2018440428413Open ↗
▸Safety & Tenant Protection7
▸BISTenant Protection Plan and Notes7
01/30/2017421423891Open ↗
01/24/2017421423891Open ↗
04/22/2016421311565Open ↗
Showing 3 of 7 on file for this type
▸Environmental & Asbestos8
▸BISASBESTOS: CERTIFICATION (DEP ACP5)5
08/24/2017440428413Open ↗
03/24/2017440392460Open ↗
01/30/2017440376497Open ↗
Showing 3 of 5 on file for this type
▸BISDEP ASBESTOS PROJECT COMPLETION FORM1
06/21/2018421423891Open ↗
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
08/17/2011420472223Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026Q00902735-I1Open ↗
▸Energy Compliance31
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS12
07/02/2018421423891Open ↗
06/21/2018421423891Open ↗
12/28/2017440392460Open ↗
Showing 3 of 12 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS11
07/02/2018421423891Open ↗
12/28/2017440392460Open ↗
12/28/2017440428413Open ↗
Showing 3 of 11 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
08/24/2017440428413Open ↗
03/24/2017440392460Open ↗
01/30/2017440376497Open ↗
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING1
05/11/2016440310842Open ↗
▸BISTR8: Energy Code Progress Inspections1
08/06/2012420472223Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
07/24/2012420472223Open ↗
▸BISSOLAR TAX ABATEMENT APPLICATION (PTA4)1
03/23/2012420472223Open ↗
▸BISTECHNICAL REPORT: ENERGY1
03/12/2012420472223Open ↗
▸Inspections & Test Reports6
▸BISTECHNICAL REPORT: RESPONSIBILITY6
08/24/2017440428413Open ↗
03/24/2017440392460Open ↗
01/30/2017440376497Open ↗
Showing 3 of 6 on file for this type
▸Approvals, Objections & Sign-offs19
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST15
07/03/2018421423891Open ↗
03/02/2018440392460Open ↗
02/13/2018440428413Open ↗
Showing 3 of 15 on file for this type
▸BISADMINISTRATIVE OBJECTIONS2
10/10/2012420583434Open ↗
Showing 1 of 2 on file for this type
▸BISUtility Company PV System Interconnection Acknowledgement Letter1
03/23/2012420472223Open ↗
▸BISCCD1-Construction Code Determination1
08/23/2013420583434Open ↗
▸Cost, Insurance & Ownership21
▸BISCOST AFFIDAVIT21
07/02/2018421423891Open ↗
12/28/2017440392460Open ↗
12/28/2017440376497Open ↗
Showing 3 of 21 on file for this type
▸Filing & Intake Forms23
▸BISBOROUGH INTAKE FORM8
03/02/2018440392460Open ↗
02/13/2018440428413Open ↗
02/08/2018440392460Open ↗
Showing 3 of 8 on file for this type
▸BISADDITIONAL INFORMATION5
11/17/2017440428413Open ↗
08/02/2016421311565Open ↗
07/06/2016421299669Open ↗
Showing 3 of 5 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET5
08/24/2017440428413Open ↗
03/24/2017440392460Open ↗
01/30/2017440376497Open ↗
Showing 3 of 5 on file for this type
▸BISEFILING COVER SHEET5
01/24/2017421423891Open ↗
04/13/2016421311565Open ↗
03/11/2016421299669Open ↗
Showing 3 of 5 on file for this type
▸Other Documents9
▸BISTax Abatement Miscellaneous4
05/07/2012420472223Open ↗
05/07/2012420472223Open ↗
04/27/2012420472223Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWCalculations2
08/13/2026Q00992501-I1Open ↗
08/13/2026Q00992501-P1Open ↗
▸DOB NOWManufacturer's Specifications2
08/13/2026Q00992501-I1Open ↗
08/13/2026Q00992501-P1Open ↗
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
04/26/2013440075507Open ↗