| Owner | Filings | Most Recent |
|---|---|---|
| J & G CONSTRUCTION SVCS | 15 | 07/08/2026 |
| FINE TIMES MANAGEMENT | 4 | 07/08/2026 |
| 99 JORALEMON STREET | 13 | 03/22/2026 |
| SB CAPITAL HOLDINGS LLC | 4 | 03/22/2026 |
| GOTHAM GA CORP | 1 | 03/22/2026 |
| SUPERB PROPERTY MANAGEMEN | 3 | 03/22/2026 |
| 99 JORALEMON ST. LLC FINE | 1 | 03/22/2026 |
| 99 JORALEMON ST LLC TIMES | 1 | 03/22/2026 |
| 40 SHERMAN ASSOCIATES | 1 | 03/22/2026 |
| BEGAY REALTY AIWEINSTEIN | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/05/2018 | $21.9M | — | — → — | $718/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| ELEVATED ENGINEERING, PLLC | 3 | 04/25/2023 |
| RICHARD KOENIGSBERG | 1 | 01/20/2023 |
| MOHAMMAD AHEAD, PE | 1 | 09/09/2022 |
| JP ENGINEERING | 1 | 09/30/2021 |
| JOHN SCHIMENTI, P.C. ARCHITECT | 2 | 04/23/2021 |
| SYED ENGINEERING, P.C. | 1 | 04/15/2019 |
| SCHERER DESIGN GROUP | 1 | 04/13/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| CCM CONSULTING GROUP, INC. | 3 | 03/21/2026 |
| CONSTRUCTION PERMIT SERVICES | 1 | 03/21/2026 |
| MARY TERESA DIPAOLI | 2 | 03/21/2026 |
| PROACTIVE BUILDING SOLUTIONS | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| J & G CONSTRUCTION SVCS | General Contractor | 11 | 07/08/2026 |
| ALLIED TELECOM CORP | General Contractor | 4 | 07/08/2026 |
| OVERLAND CONTRACTING INC | General Contractor | 4 | 07/08/2026 |
| BYPASS MECHANICAL CORP | Plumbing | 2 | 07/08/2026 |
| GLENDALE ELECTL CONTNG IN | Electrical | 1 | 03/22/2026 |
| JC CONSULTING & MANAGEMENT | General Contractor | 1 | 07/08/2026 |
| DK BUILDERS INC | General Contractor | 1 | 07/08/2026 |
| JESUS CORPORAN | Electrical | 1 | 03/21/2026 |
| JOSHUA GUTTMAN | Electrical | 1 | 03/21/2026 |
| ZITO, ROCCO | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| KOENIGSBERG ENGINEERING, | 2247 | 1 | 01/20/2023 |
| S&S CONCRETE & SOIL TESTI | 1008 | 1 | 01/20/2023 |
| JOHN SCHIMENTI PC | 519 | 2 | 04/23/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Supported Scaffold | Permit Issued | J & G CONSTRUCTION SVCS | 08/22/2023 |
| DOB NOW | Sidewalk Shed | Permit Issued | J & G CONSTRUCTION SVCS | 05/31/2023 |
| DOB NOW | General Construction | Signed-off | DK BUILDERS INC | 02/01/2023 |
| DOB NOW | Antenna | Signed-off | OVERLAND CONTRACTING INC | 11/18/2022 |
| DOB NOW | Supported Scaffold | Permit Issued | J & G CONSTRUCTION SVCS | 09/12/2022 |
| DOB NOW | Sidewalk Shed | Permit Issued | J & G CONSTRUCTION SVCS | 06/27/2022 |
| DOB NOW | General Construction | Permit Issued | JC CONSULTING & MANAGEME* | 10/15/2021 |
| DOB NOW | Plumbing | Signed-off | BYPASS MECHANICAL CORP | 07/01/2021 |
| DOB NOW | Sidewalk Shed | Permit Issued | J & G CONSTRUCTION SVCS | 06/28/2021 |
| DOB NOW | Plumbing | Signed-off | BYPASS MECHANICAL CORP | 02/09/2021 |
| DOB NOW | Antenna | Signed-off | OVERLAND CONTRACTING INC | 10/06/2020 |
| DOB NOW | Sidewalk Shed | Permit Issued | J & G CONSTRUCTION SVCS | 06/08/2020 |
| DOB NOW | Sidewalk Shed | Permit Issued | J & G CONSTRUCTION SVCS | 04/16/2019 |
| DOB NOW | Antenna | Signed-off | ALLIED TELECOM CORP | 03/11/2019 |
| DOB NOW | Antenna | Signed-off | ALLIED TELECOM CORP | 08/30/2018 |
| BIS | OT | ISSUED | GOTHAM GC CORP | 12/03/2020 |
| BIS | PL | ISSUED | BYPASS MECHANICAL CORP | 03/13/2019 |
| BIS | OT | ISSUED | GOTHAM GC CORP | 03/08/2019 |
| BIS | OT | ISSUED | SUPERB PROPERTY MNG'T | 04/03/2018 |
| BIS | EQ | ISSUED | ATCO RESTORATION INC | 10/17/2016 |
| BIS | OT | ISSUED | BECHTEL INFRASTRUCTURE AN | 06/06/2016 |
| BIS | OT | ISSUED | BECHTEL INFRASTRUCTURE AN | 08/04/2015 |
| BIS | EQ | ISSUED | ATCO RESTORATION INC | 04/01/2015 |
| BIS | OT | ISSUED | ODYSSIA GLOBAL COMM. CORP | 02/18/2015 |
| BIS | OT | ISSUED | ODYSSIA GLOBAL COMM. CORP | 03/06/2014 |
| BIS | OT | ISSUED | NET COM DEVELOPMENT INC | 05/24/2011 |
| BIS | OT | ISSUED | SBA COMM CORP | 10/04/2004 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/23/2021 | Signed-off | BYPASS MECHANICAL CORP | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/13/2022 | Permit Issued | ZEV ELECTRIC CORP. | — |
| 02/08/2021 | Complete | GLENDALE ELECTL CONTNG IN | General Wiring |
| 04/14/2019 | Permit Issued | RICHARD NEU | — |
| 04/01/2019 | Complete | GLENDALE ELECTL CONTNG IN | General Wiring |
| 01/02/2019 | Permit Issued | FRIED ELECTRIC CO. | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/09/2022 | Permit Issued | J & G CONSTRUCTION SVCS | Scaffold |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/11/2023 | Tenant Protection Plan Compliance | GLEN LANGER | special |
| 12/13/2022 | Post-installed Anchors | RICHARD KOENIGSBERG | special |
| 12/13/2022 | Structural Stability – Alterations of existing buildings | RICHARD KOENIGSBERG | special |
| 12/13/2022 | Masonry | RICHARD KOENIGSBERG | special |
| 12/12/2022 | Final | RICHARD KOENIGSBERG | progress |
| 04/23/2021 | Fire-Resistant Penetrations and Joints | John Schimenti | special |
| 04/23/2021 | Energy Code Compliance Inspections | John Schimenti | progress |