← Back
Three families
50 CHEEVER PLACE
BROOKLYN · BIN 3003719
💬 Discuss this project
1899Year Built
3Stories
C0Building Class
R6Zoning
3,192 sfGross Floor Area
3Units
0 Open Violations
Three families · 1,667 sf lot · 1.91 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbing
Permit Issued — active, not yet Signed-off
Floor 3Under Construction6p · 1 filing · 8 docs
Floor 2Under Construction4p · 1 filing · 8 docs
Floor 1Under Construction5p · 1 filing · 8 docs
Sub-BasementUnder Construction4p · 1 filing · 8 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
50 CHEEVER PLACE MANAGEMENT209/24/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ANTHONY BONSIGNORE, RA205/14/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
PLUMBING NYC INCPlumbing109/24/2026
Building Lifecycle
All (49)Filed (2)Permit Issued (1)Violation (13)Objection (22)Special Inspection (11)
09/23/2026
Permit issued — Plumbing
B01400478-S1-PL
09/11/2026
Objection resolved — Addressed
08/05/2026
Objection resolved — Addressed
08/05/2026
Objection resolved — Addressed
08/05/2026
Objection resolved — Addressed
08/05/2026
Objection resolved — Addressed
08/05/2026
Objection resolved — Addressed
07/29/2026
Objection resolved — Resolved
06/02/2026
Objection raised — Other
06/02/2026
Objection resolved — Resolved
06/02/2026
Objection raised — Cost
06/02/2026
Objection resolved — Addressed
06/02/2026
Objection raised — Scope
06/02/2026
Objection raised — Other
06/02/2026
Objection resolved — Resolved
06/02/2026
Objection raised — Scope
06/02/2026
Objection resolved — Resolved
05/29/2026
Objection raised — Energy
05/29/2026
Objection raised — Inspections
05/29/2026
Objection raised — Scope
05/29/2026
Objection raised — Admin
05/29/2026
Objection raised — Admin
05/29/2026
Objection raised — Scope
05/14/2026
Filed — Alteration
INTERIOR RENOVATION WORK ON THE BASEMENT,1ST,2ND & ERD FLOORS, NEW DUCTLESS A/C UNITS WITH ELECT HEAT PUMPS, REPLACE KITCHENS AND BATHS ALL AS PER PLANS FILED
B01400478-S1
05/14/2026
Filed — Alteration
INTERIOR RENOVATION WORK ON THE BASEMENT,1ST,2ND & ERD FLOORS, NEW DUCTLESS A/C UNITS WITH ELECT HEAT PUMPS, REPLACE KITCHENS AND BATHS ALL AS PER PLANS FILED
B01400478-I1
05/11/2026
Special inspection requirement — Mechanical Systems
05/11/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
05/11/2026
Special inspection requirement — Final
05/11/2026
Special inspection requirement — Energy Code Compliance Inspections
05/11/2026
Special inspection requirement — Air barrier - visual inspection
05/11/2026
Special inspection requirement — HVAC-R and service water heating system controls
05/11/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
05/11/2026
Special inspection requirement — Insulation placement and R values
05/11/2026
Special inspection requirement — HVAC-R and service water heating equipment
05/11/2026
Special inspection requirement — Interior lighting power
05/11/2026
Special inspection requirement — Lighting in dwelling units
11/20/2025
Violation issued (HPD, closed)
I
06/09/2025
Violation issued (HPD, closed)
A
04/09/2024
Violation issued (HPD, closed)
A
03/21/2023
Violation issued (HPD, closed)
A
11/14/2022
Violation issued (HPD, closed)
I
02/23/2022
Violation issued (HPD, closed)
A
02/23/2022
Violation issued (HPD, closed)
I
04/07/2021
Violation issued (HPD, closed)
A
10/29/2019
Violation issued (HPD, closed)
I
10/16/2018
Violation issued (HPD, closed)
I
11/20/2017
Violation issued (HPD, closed)
I
11/04/2016
Violation issued (HPD, closed)
I
10/08/2015
Violation issued (HPD, closed)
I
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedPLUMBING NYC INC09/23/2026
BISOTISSUEDH.L. GENERAL CONTRACTORS12/19/2002
1 project · most recent 05/14/2026
Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
05/14/2026——Air Conditioning Systems
Cooling
Tosot TWH24AG25D6D0 2 tons · Condensing Unit ×2
1 project · most recent 05/14/2026
Gas Water/Sanitary
FiledStatusContractorScope
05/14/2026Permit IssuedPLUMBING WORKS NYC INCGas, Water/Sanitary
1 project · most recent 06/12/2026
General Wiring
FiledStatusContractorScope
06/12/2026Permit IssuedPLAZA ELEC'L CONTR'S. INCGeneral Wiring
▾Special Inspection Requirements (DOB NOW) — 11
DateRequirementInspectorRole
05/11/2026Mechanical Systems—special
05/11/2026Fire-Resistant Penetrations and Joints—special
05/11/2026Final—progress
05/11/2026Energy Code Compliance Inspections—progress
05/11/2026Air barrier - visual inspection—energy_progress
05/11/2026HVAC-R and service water heating system controls—energy_progress
05/11/2026HVAC-R and service water piping design and insulation—energy_progress
05/11/2026Insulation placement and R values—energy_progress
05/11/2026HVAC-R and service water heating equipment—energy_progress
05/11/2026Interior lighting power—energy_progress
05/11/2026Lighting in dwelling units—energy_progress
▾Documents — 8 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/15/2026B01400478-S1Request digital key ↗
08/15/2026B01400478-I1Request digital key ↗
▸Applications & Permits2
▸DOB NOWLPC Approval/Permit2
08/15/2026B01400478-S1Open ↗
08/15/2026B01400478-I1Open ↗
▸Seals & Professional Certifications2
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/17/2026B01400478-S1Open ↗
08/17/2026B01400478-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/15/2026B01400478-S1Open ↗
08/15/2026B01400478-I1Open ↗