| Owner | Filings | Most Recent |
|---|---|---|
| A D GENERAL CONTRACTORS | 13 | 07/08/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| VOLUME SPACE CONSULTING INC. | 1 | 12/05/2024 |
| STUDIO NYANDAK ARCHITECTURE AND ENG | 1 | 10/18/2024 |
| ERIN COWHEY ARCHITECT | 1 | 03/11/2024 |
| AM ARCHITECT'S STUDIO LLC | 2 | 06/21/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| S M EXPEDITING | 4 | 03/21/2026 |
| METROPOLIS GROUP INC | 2 | 03/21/2026 |
| GREEN STUDIO | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| A & D GENERAL CONTR INC | General Contractor | 12 | 07/08/2026 |
| CITIVIEW CONTRACTING CORP | General Contractor | 6 | 03/21/2026 |
| R. BARONE PLUMBING | Plumbing | 3 | 07/08/2026 |
| RICHARD NEU | Electrical | 1 | 03/21/2026 |
| LELIS, ARILSON | Electrical | 1 | 03/21/2026 |
| SERGIO GIANNACHI | Electrical | 1 | 03/21/2026 |
| NEU, RICHARD | Electrical | 1 | 03/21/2026 |
| RICHARD NEU | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| STUDIO NYANDAK ARCHITECTU | 8378 | 1 | 10/18/2024 |
| AM DESIGN STUDIO LLC | 4413 | 1 | 06/21/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Construction Fence | Permit Issued | A & D GENERAL CONTR INC | 06/11/2025 |
| DOB NOW | Supported Scaffold | Permit Issued | A & D GENERAL CONTR INC | 06/10/2025 |
| DOB NOW | Sidewalk Shed | Permit Issued | A & D GENERAL CONTR INC | 06/10/2025 |
| DOB NOW | Structural | Signed-off | CITIVIEW CONTRACTING CORP | 05/13/2025 |
| DOB NOW | Construction Fence | Permit Issued | A & D GENERAL CONTR INC | 12/06/2024 |
| DOB NOW | Supported Scaffold | Permit Issued | A & D GENERAL CONTR INC | 12/06/2024 |
| DOB NOW | Supported Scaffold | Permit Issued | A & D GENERAL CONTR INC | 12/06/2024 |
| DOB NOW | Plumbing | Permit Issued | R. BARONE PLUMBING | 08/12/2021 |
| DOB NOW | General Construction | Permit Issued | CITIVIEW CONTRACTING CORP | 07/26/2021 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/25/2025 | Permit Issued | RICHARD NEU | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/18/2024 | Signed-off | CITIVIEW CONTRACTING CORP | Masonry |
| Date | Type | Result | Report |
|---|---|---|---|
| 11/14/2025 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 05/29/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 05/29/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 10/28/2021 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 08/20/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/17/2024 | Structural Stability – Alterations of existing buildings | TENZIN NYANDAK | special |
| 10/17/2024 | Masonry | TENZIN NYANDAK | special |
| 10/17/2024 | Post-installed Anchors | TENZIN NYANDAK | special |
| 10/17/2024 | Structural Steel - Details | TENZIN NYANDAK | special |
| 10/17/2024 | Structural Steel - High Strength Bolting | TENZIN NYANDAK | special |
| 10/17/2024 | Structural Steel - Welding | TENZIN NYANDAK | special |
| 10/16/2024 | Final | TENZIN NYANDAK | progress |
| 03/08/2024 | Permanent certificate | — | energy_progress |
| 03/08/2024 | Fire-Resistant Penetrations and Joints | — | special |
| 03/08/2024 | Fire-Resistance Rated Construction | — | progress |
| 03/08/2024 | Fenestration areas | — | energy_progress |
| 03/08/2024 | Lighting in dwelling units | — | energy_progress |
| 03/08/2024 | Air barrier - visual inspection | — | energy_progress |
| 03/08/2024 | Insulation placement and R values | — | energy_progress |
| 03/08/2024 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 03/08/2024 | Maintenance information | — | energy_progress |
| 03/08/2024 | Fenestration air leakage | — | energy_progress |
| 02/22/2024 | Final | — | progress |
| 02/22/2024 | Mechanical Systems | — | special |