| Firm | Filings | Most Recent |
|---|---|---|
| CORTNEY WALLESTON ARCHITECT, PC | 2 | 01/26/2024 |
| HAMANN ENGINEERING, PLLC | 1 | 11/30/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| BIG ORANGE EXPEDITING | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ROCK STAR RENOVATION LLC | General Contractor | 3 | 03/21/2026 |
| TOMCHRIS CONTRACTING CORP | General Contractor | 2 | 03/21/2026 |
| BIG CITY ELECL SOLUTIONS | Electrical | 1 | 03/22/2026 |
| TMS PLBG & HEATING CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CORTNEY WALLESTON ARCHITE | 3881 | 1 | 01/26/2024 |
| HAMANN ENGINEERING, PLLC | 4949 | 1 | 11/30/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | TMS PLBG & HEATING CORP | 07/03/2024 |
| DOB NOW | General Construction | Signed-off | ROCK STAR RENOVATION LLC | 03/29/2024 |
| DOB NOW | General Construction | Signed-off | TOMCHRIS CONTRACTING CORP | 01/17/2024 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/09/2024 | Permit Issued | BIG CITY ELECL SOLUTIONS | General Wiring |
| 01/08/2024 | Permit Issued | TM SELECT ELECTRIC CORP | General Wiring |
| 08/24/2020 | Complete | WILLDAN ELECTRICAL OF NY | — |
| 10/14/2019 | Complete | WILLDAN ELECTRICAL OF NY | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/16/2024 | Fire-Resistant Penetrations and Joints | Cortney Walleston | special |
| 01/16/2024 | Final | Cortney Walleston | progress |
| 01/16/2024 | Interior lighting power | Cortney Walleston | energy_progress |
| 01/16/2024 | Lighting controls | Cortney Walleston | energy_progress |
| 11/29/2023 | Tenant Protection Plan Compliance | CARL HAMANN | special |
| 11/28/2023 | Final | CARL HAMANN | progress |