| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/29/2024 | Complete | BROOKYLN SOLARWORKS, LLC | — |
| 03/11/2021 | Complete | DENMAR ELECTRIC CORP | General Wiring |
| Owner | Filings | Most Recent |
|---|---|---|
| 60-81 MYRTLE AVENUE | 24 | 07/08/2026 |
| ALDA BUILDING COMPANY | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/17/2019 | $1.4M | — | — → — | $424/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| NY BUILDING ASSOCIATES INC | 1 | 04/10/2024 |
| HAMANN ENGINEERING, PLLC | 4 | 01/06/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| BROOKLYN SOLARWORKS | 1 | 03/21/2026 |
| BIG ORANGE EXPEDITING | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| EURO HVAC INC | General Contractor | 3 | 03/21/2026 |
| DENMAR ELECTRIC CORP | Electrical | 1 | 03/22/2026 |
| BROOKLYN SOLARWORKS LLC | General Contractor | 1 | 07/08/2026 |
| NEW YORK PARK PLBG&HTG CO | Plumbing | 1 | 07/08/2026 |
| SO PLUMBING & HEATING INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| NKM ENGINEERING PLLC | 6244 | 1 | 04/10/2024 |
| HAMANN ENGINEERING, PLLC | 4949 | 4 | 01/06/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | BROOKLYN SOLARWORKS LLC | 04/11/2024 |
| DOB NOW | Plumbing | Signed-off | NEW YORK PARK PLBG&HTG CO | 01/24/2022 |
| DOB NOW | Mechanical Systems | Permit Issued | EURO HVAC INC | 09/28/2020 |
| DOB NOW | Plumbing | Signed-off | NICHOLAS SUIDA | 07/21/2020 |
| BIS | OT | ISSUED | ALDA BUILDING COMPANY LLC | 02/10/2020 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/28/2024 | Fire-Resistant Penetrations and Joints | NARESH MAHANGU | special |
| 03/28/2024 | Structural Stability – Alterations of existing buildings | NARESH MAHANGU | special |
| 03/28/2024 | Energy Code Compliance Inspections | NARESH MAHANGU | progress |
| 03/28/2024 | Final | NARESH MAHANGU | progress |
| 03/28/2024 | Air barrier - visual inspection | NARESH MAHANGU | energy_progress |
| 01/11/2021 | Fire-Resistant Penetrations and Joints | CARL HAMANN | special |
| 01/06/2021 | Fire-Resistant Penetrations and Joints | CARL HAMANN | special |
| 08/10/2020 | HVAC insulation and sealing | CARL HAMANN | energy_progress |
| 08/10/2020 | HVAC and service water heating equipment | CARL HAMANN | energy_progress |
| 08/10/2020 | Maintenance information | CARL HAMANN | energy_progress |
| 08/10/2020 | HVAC and service water heating system controls | CARL HAMANN | energy_progress |
| 08/10/2020 | Shutoff dampers | CARL HAMANN | energy_progress |
| 07/22/2020 | Final | CARL HAMANN | progress |
| 07/22/2020 | Mechanical Systems | CARL HAMANN | special |