| Owner | Filings | Most Recent |
|---|---|---|
| TRI-STATE CONTRACTING OF* | 3 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| KENNY LEE ARCHITECT | 1 | 03/18/2025 |
| LONGTIN SOLUTIONS LLC | 4 | 12/06/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| KORMAN DESIGN & BUILD | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| AMC PLBG, HTG & CLNG, INC | Plumbing | 2 | 07/08/2026 |
| SENID PL & HTG CORP | Plumbing | 2 | 07/08/2026 |
| MICHAEL BAPTISTE | Electrical | 1 | 03/21/2026 |
| KINGDOM CONTRACTING LLC | General Contractor | 1 | 04/09/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| KORMAN DESIGN & BUILD | 2055 | 1 | 03/18/2025 |
| KORMAN DESIGN & BUILD | 8792 | 1 | 03/18/2025 |
| LONGTIN SOLUTIONS LLC | 8320 | 4 | 12/06/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | KINGDOM CONTRACTING LLC | 05/16/2025 |
| DOB NOW | Plumbing | Signed-off | SENID PL & HTG CORP | 08/17/2023 |
| DOB NOW | Boiler Equipment | Signed-off | SENID PL & HTG CORP | 07/11/2023 |
| DOB NOW | Boiler Equipment | Signed-off | AMC PLBG, HTG & CLNG, INC | 12/05/2022 |
| DOB NOW | Plumbing | Signed-off | AMC PLBG, HTG & CLNG, INC | 10/21/2022 |
| BIS | MH | ISSUED | NOBEL CONSTRUCTION CORP | 06/26/2014 |
| BIS | EQ | ISSUED | TRI-STATE CONTRACTING OF* | 03/20/2014 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/06/2023 | Signed-off | SENID PL & HTG CORP | Gas |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/05/2020 | Permit Issued | WILLDAN ELECTRICAL OF NY | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 10/21/2025 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 10/10/2025 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 12/27/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/21/2023 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| 11/15/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/02/2023 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 09/21/2023 | No Access-Final PL - Up to 3 Requested Floors | No Access | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/07/2023 | Fire-Resistant Penetrations and Joints | TIM TSAI | special |
| 12/07/2023 | Energy Code Compliance Inspections | TIM TSAI | progress |
| 12/07/2023 | HVAC-R and service water heating equipment | TIM TSAI | energy_progress |
| 12/07/2023 | HVAC-R and service water piping design and insulation | TIM TSAI | energy_progress |
| 12/07/2023 | HVAC-R and service water heating system controls | TIM TSAI | energy_progress |
| 10/02/2023 | Fire-Resistant Penetrations and Joints | TIM TSAI | special |
| 10/02/2023 | Heating Systems | TIM TSAI | special |