← Back
Cape Cod
32-14 204 STREET
QUEENS · BIN 4134432
💬 Discuss this project
1950Year Built
1.5Stories
A0Building Class
R3XZoning
1,131 sfGross Floor Area
1Units
0 Open ViolationsFDNY Report ↗
Cape Cod · 4,750 sf lot · 0.24 FAR built
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
THE OWNER OF 32-14, 204 S103/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ISEED CONSTRUCTION INC103/30/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SJ CONSTR DESIGN INCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ISEED CONSTRUCTION INC8336103/30/2026
Building Lifecycle
All (6)Filed (1)Permit Issued (1)Signed Off (1)Violation (2)Inspection (1)
07/30/2026
Signed off — Alteration
To resolve ECB Violation #39179898L. Thanks.
Q01378488-I1
07/29/2026
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
05/13/2026
Permit issued — General Construction
Q01378488-I1-GC
03/30/2026
Filed — Alteration
To resolve ECB Violation #39179898L. Thanks.
Q01378488-I1
03/10/2026
Violation issued (ECB, closed)
Construction
12/09/2004
Violation issued (ECB, closed)
Site Safety
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offSJ CONSTR DESIGN INC05/13/2026
1 project · most recent 01/26/2024
FiledStatusContractorScope
01/26/2024CompleteALL WAYS ELECTRIC CORP.W—
▾Field Inspections (DOB CAP) — 1
DateTypeResultReport
07/29/2026Pass-Final General Construction Non-Directive 14PassView ↗
▾Special Inspection Requirements (DOB NOW) — 8
DateRequirementInspectorRole
04/03/2026Fenestration areasYIPENG LUANenergy_progress
04/03/2026Fenestration and door U-factor and product ratingsYIPENG LUANenergy_progress
04/03/2026Air barrier - visual inspectionYIPENG LUANenergy_progress
04/03/2026Insulation placement and R valuesYIPENG LUANenergy_progress
04/03/2026Fenestration air leakageYIPENG LUANenergy_progress
03/25/2026Tenant Protection Plan ComplianceYIPENG LUANspecial
03/25/2026Energy Code Compliance InspectionsYIPENG LUANprogress
03/25/2026Fire-Resistant Penetrations and JointsYIPENG LUANspecial
▾Documents — 10 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/17/2026Q01378488-I1Request digital key ↗
▸Seals & Professional Certifications9
▸DOB NOWProgress Inspector Seal & Signature6
08/31/2026Q01378488-I1Open ↗
08/31/2026Q01378488-I1Open ↗
08/31/2026Q01378488-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature2
08/31/2026Q01378488-I1Open ↗
08/31/2026Q01378488-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/17/2026Q01378488-I1Open ↗