← Back
Elevator cooperative
112-50 NORTHERN BOULEVARD
QUEENS · BIN 4431568
💬 Discuss this project
1953Year Built
6Stories
D4Building Class
R6Zoning
290,000 sfGross Floor Area
301Units
LL97 CoveredRent Stabilized88 Open Violations ▸FISP: SAFEFDNY Report ↗
Elevator cooperative · Owner of record: DORIE MILLER HOUSING CO INC · 147,105 sf lot · 1.97 FAR built · Flood zone X
Locations of Work
ArchitectureEquipment
Roof2p · 2 filings · 14 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
METRO MANAGEMENT DEVELOPMENT407/08/2026
XINOS CONSTRUCTION404/09/2026
DORIE MILLER HOUSING1003/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
HOFFMANN ARCHITECTS, INC.202/27/2025
CRIBSTONE ENGINEERING PLLC108/07/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JM ZONING, LLC.403/21/2026
XINOS CONSTRUCTION203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
XINOS CONSTRUCTION CORPGeneral Contractor304/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
DNA CONTROLLED INSPECTION554102/27/2025
SOCOTEC ENGINEERING4983108/21/2024
Building Lifecycle
All (38)Filed (4)Permit Issued (4)Signed Off (3)Facade (FISP) (9)Violation (10)Special Inspection (8)
12/01/2025
Signed off — Alteration
Q01094738-I1
11/28/2025
Permit issued — Suspended Scaffold
Q01094738-I1-SC
11/18/2025
Signed off — Alteration
PROPOSED INSTALLATION OF A TEMPORARY SIDEWALK SHED AS PER PLANS SUBMITTED. WORK SHALL COMPLY WITH 2022 BUILDING CODS, CHAPTER 33. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Q01091232-I1
04/15/2025
Cycle 9 facade report signed — SAFE
03/21/2025
Signed off — Alteration
Q01073308-I1
02/27/2025
Filed — Alteration
Q01073308-P1
02/27/2025
Special inspection requirement — Final
Juan Kuriyama
02/27/2025
Special inspection requirement — Post-installed Anchors
ALEXIS SCHLESSINGERMAN
02/27/2025
Special inspection requirement — Masonry
ALEXIS SCHLESSINGERMAN
02/27/2025
Special inspection requirement — Tenant Protection Plan Compliance
ALEXIS SCHLESSINGERMAN
02/19/2025
Cycle 9 facade report submitted
02/10/2025
Cycle 9 facade inspection completed
02/05/2025
Special inspection requirement — Tenant Protection Plan Compliance
01/31/2025
Special inspection requirement — Masonry
WILLIAM FITZJOHN
01/31/2025
Special inspection requirement — Post-installed Anchors
WILLIAM FITZJOHN
01/31/2025
Special inspection requirement — Final
Juan Kuriyama
09/06/2024
Permit issued — General Construction
Q01073308-I1-GC
08/28/2024
Permit issued — Suspended Scaffold
Q01094738-I1-SC
08/21/2024
Filed — Alteration
Q01094738-I1
08/21/2024
Filed — Alteration
Q01073308-I1
08/08/2024
Permit issued — Sidewalk Shed
Q01091232-I1-SH
08/07/2024
Filed — Alteration
PROPOSED INSTALLATION OF A TEMPORARY SIDEWALK SHED AS PER PLANS SUBMITTED. WORK SHALL COMPLY WITH 2022 BUILDING CODS, CHAPTER 33. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Q01091232-I1
02/21/2023
Cycle 9 facade report submitted
02/20/2023
Cycle 9 facade report signed — SWARMP
02/17/2023
Cycle 9 facade inspection completed
03/10/2022
Violation issued (HPD, closed)
I
03/10/2022
Violation issued (HPD, closed)
A
04/20/2021
Violation issued (HPD, closed)
I
04/20/2021
Violation issued (HPD, closed)
A
02/15/2020
Cycle 8 facade report signed — SWARMP
02/12/2020
Cycle 8 facade inspection completed
11/26/2019
Cycle 8 facade report submitted
11/06/2019
Violation issued (HPD, closed)
I
02/19/2019
Violation issued (ECB, closed)
Local Law
10/26/2018
Violation issued (HPD, closed)
I
07/31/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
12/11/2017
Violation issued (HPD, closed)
I
11/30/2016
Violation issued (HPD, closed)
I
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSuspended ScaffoldSigned-offXINOS CONSTRUCTION CORP11/28/2025
DOB NOWGeneral ConstructionSigned-offXINOS CONSTRUCTION CORP09/06/2024
DOB NOWSuspended ScaffoldSigned-offXINOS CONSTRUCTION CORP08/28/2024
DOB NOWSidewalk ShedSigned-offXINOS CONSTRUCTION CORP08/08/2024
1 project · most recent 09/18/2024
FiledStatusContractorScope
09/18/2024Permit IssuedTOWER ELECTRIC INC.—
▾Special Inspection Requirements (DOB NOW) — 8
DateRequirementInspectorRole
02/27/2025FinalJuan Kuriyamaprogress
02/27/2025Post-installed AnchorsALEXIS SCHLESSINGERMANspecial
02/27/2025MasonryALEXIS SCHLESSINGERMANspecial
02/27/2025Tenant Protection Plan ComplianceALEXIS SCHLESSINGERMANspecial
02/05/2025Tenant Protection Plan Compliance—special
01/31/2025MasonryWILLIAM FITZJOHNspecial
01/31/2025Post-installed AnchorsWILLIAM FITZJOHNspecial
01/31/2025FinalJuan Kuriyamaprogress
▾Documents — 16 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/21/2026Q01091232-I1Request digital key ↗
08/21/2026Q01094738-I1Request digital key ↗
08/20/2026Q01073308-P1Request digital key ↗
Showing 3 of 4 on file for this type
▸Seals & Professional Certifications8
▸DOB NOWSpecial Inspector Seal & Signature3
08/27/2026Q01073308-P1Open ↗
08/23/2026Q01073308-I1Open ↗
08/23/2026Q01073308-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/20/2026Q01073308-P1Open ↗
08/20/2026Q01073308-I1Open ↗
08/13/2026Q01091232-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
08/27/2026Q01073308-P1Open ↗
08/23/2026Q01073308-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/20/2026Q01073308-P1Open ↗
08/20/2026Q01073308-I1Open ↗
▸Other Documents2
▸DOB NOWCalculations1
08/13/2026Q01094738-I1Open ↗
▸DOB NOWManufacturer's Specifications1
08/13/2026Q01094738-I1Open ↗