| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M01390693 ↗ | 1585 BROADWAY MANHATTAN | Alteration | Permit Issued | 06/02/2026 | 09/29/2026 | Owner MORGAN STANLEY Contractor PRODUCTION CONTRACT. LLC | Removal of existing HVAC,WSHP, & equipment and distribution and replacement with same as per plans filed herewith. No change in use, egress… |
| M01390729 ↗ | 1585 BROADWAY MANHATTAN | Alteration | Permit Issued | 06/02/2026 | 06/09/2026 | Owner MORGAN STANLEY Contractor PAR FIRE PROTECTION LLC | All new Tenant space on ground level. Tenant Space of the building fed from overall building systems including Domestic Water Supply and San… |
| B00311232 ↗ | 66 NORTH 3 STREET BROOKLYN | Alteration | Signed-off | 02/17/2020 | 04/11/2024 | Contractor AGGRESSIVE FIRE PROT LLC Filer GILLMAN CONSULTING INC | Modification to sprinkler system and related piping as shown on drawings filed herewith. No change in use, egress or occupancy. |
| Q00947974 ↗ | 155-08 CROSS BAY BOULEVARD QUEENS | Alteration | Signed-off | 11/09/2023 | 11/17/2023 | Contractor VERICON CONSTRUCTION CO | Bank renovation (Capital One), work to include mechanical modification of relocation of existing air devices and associated branch duct rero… |
| X00921296 ↗ | 1941 WILLIAMSBRIDGE ROAD BRONX | Alteration | Signed-off | 09/20/2023 | 10/02/2023 | Owner CAPITAL ONE Contractor MACCARONE PLUMBING INC | BATHROOM RENOVATION (CAPITAL ONE), WORK TO INCLUDE PLUMBING MODIFICATIONS AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| X00921268 ↗ | 1941 WILLIAMSBRIDGE ROAD BRONX | Alteration | Signed-off | 09/20/2023 | 09/26/2023 | Owner CAPITAL ONE Contractor GREGOR INDUSTRIES INC | BATHROOM RENOVATION (CAPITAL ONE), WORK TO INCLUDE MECHANCAL MODIFICATIONS AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| Name | Projects together | Most recent |
|---|---|---|
| ANDREW ROBINSON | 1 | 05/11/2021 |
| Name | Projects together | Most recent |
|---|---|---|
| DANSON HEIGHTS SERVICE CO | 8 | 08/14/2020 |
| AMERICAN PLBG SOLUTIONS I | 2 | 09/30/2019 |
| ASHLAR MECHANICAL CORP | 2 | 05/11/2021 |
| DUO PLUMBING & HTG CORP. | 2 | 09/15/2023 |
| GREGOR INDUSTRIES INC | 2 | 09/20/2023 |
| SACHSE CONSTRUCTION AND | 2 | 02/17/2020 |
| SMITH-MCCORD, INC | 2 | 05/20/2020 |
| ABCO PEERLESS SPRINKLER C | 1 | 08/16/2022 |
| AGGRESSIVE FIRE PROT LLC | 1 | 11/09/2020 |
| BEDROCK PLBG. & HTG., INC | 1 | 11/06/2019 |
| BLACK SQUARE BUILDERS COR | 1 | 03/31/2020 |
| COYLE CONTRACTING CORP | 1 | 10/19/2021 |
| FLYTIGER P & H LTD | 1 | 12/20/2021 |
| FLYTIGER PLB & HTG LTD | 1 | 10/19/2021 |
| FOLOR INC | 1 | 08/16/2022 |
| HENG YIP CONSTRUCTION COR | 1 | 10/20/2022 |
| M&T PLBG AND HTG CO., INC | 1 | 02/26/2020 |
| MACCARONE PLUMBING INC | 1 | 09/20/2023 |
| PAR FIRE PROTECTION LLC | 1 | 06/02/2026 |
| PAR PLUMBING CO., INC | 1 | 06/02/2026 |
| PHILIP ANDREWS LLC | 1 | 12/09/2019 |
| PRODUCTION CONTRACT. LLC | 1 | 06/02/2026 |
| PSI PARTNERS, LLC | 1 | 11/09/2020 |
| QUALITY RENOVATION TEAM I | 1 | 01/07/2021 |
| SCHIMENTI CONSTRUCTION CO | 1 | 08/01/2023 |
| Name | Projects together | Most recent |
|---|---|---|
| SHEFA LAND CORP. | 4 | 05/11/2021 |
| WALGREENS | 4 | 09/30/2019 |
| THE SHOPS AT COLUMBUS CIRCLE | 3 | 09/20/2023 |
| CAPITAL ONE | 2 | 09/20/2023 |
| MORGAN STANLEY | 2 | 06/02/2026 |
| VORNADO REALTY TRUST | 2 | 11/06/2019 |
| 155 CROSSBAY REALTY CO, LLC | 1 | 11/09/2023 |
| SL GREEN REALTY CORP | 1 | 12/09/2019 |
| Name | Projects together | Most recent |
|---|---|---|
| GILLMAN CONSULTING INC | 3 | 09/20/2023 |
| OUTSOURCE CONSULTANTS, INC. | 3 | 11/09/2023 |
| A1 EXPEDITING SERVICE CORP. | 2 | 06/02/2026 |
| PEROTTO CONSULTING MGT | 2 | 08/16/2022 |
| BROOKBRIDGE CONSULTING | 1 | 05/11/2021 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M01390693 ↗ | 1585 BROADWAY MANHATTAN | Alteration | Permit Issued | 06/02/2026 | 09/29/2026 | Owner MORGAN STANLEY Contractor PRODUCTION CONTRACT. LLC | Removal of existing HVAC,WSHP, & equipment and distribution and replacement with same as per plans filed herewith. No change in use, egress… |
| M01390729 ↗ | 1585 BROADWAY MANHATTAN | Alteration | Permit Issued | 06/02/2026 | 06/09/2026 | Owner MORGAN STANLEY Contractor PAR FIRE PROTECTION LLC | All new Tenant space on ground level. Tenant Space of the building fed from overall building systems including Domestic Water Supply and San… |
| B00311232 ↗ | 66 NORTH 3 STREET BROOKLYN | Alteration | Signed-off | 02/17/2020 | 04/11/2024 | Contractor AGGRESSIVE FIRE PROT LLC Filer GILLMAN CONSULTING INC | Modification to sprinkler system and related piping as shown on drawings filed herewith. No change in use, egress or occupancy. |
| Q00947974 ↗ | 155-08 CROSS BAY BOULEVARD QUEENS | Alteration | Signed-off | 11/09/2023 | 11/17/2023 | Contractor VERICON CONSTRUCTION CO | Bank renovation (Capital One), work to include mechanical modification of relocation of existing air devices and associated branch duct rero… |
| X00921296 ↗ | 1941 WILLIAMSBRIDGE ROAD BRONX | Alteration | Signed-off | 09/20/2023 | 10/02/2023 | Owner CAPITAL ONE Contractor MACCARONE PLUMBING INC | BATHROOM RENOVATION (CAPITAL ONE), WORK TO INCLUDE PLUMBING MODIFICATIONS AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| X00921268 ↗ | 1941 WILLIAMSBRIDGE ROAD BRONX | Alteration | Signed-off | 09/20/2023 | 09/26/2023 | Owner CAPITAL ONE Contractor GREGOR INDUSTRIES INC | BATHROOM RENOVATION (CAPITAL ONE), WORK TO INCLUDE MECHANCAL MODIFICATIONS AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| M00890050 ↗ | 100 WEST 125 STREET MANHATTAN | Alteration | Signed-off | 08/01/2023 | 08/08/2023 | Contractor SCHIMENTI CONSTRUCTION CO | APPLICATION FILED FOR MECHANICAL MODIFICATIONS/ADDITIONS ON THE 1ST FLOOR & 2ND FLOOR FOR STORE (H&M) AS PER PLANS FILED HEREWITH. NO CHANGE… |
| M00863467 ↗ | 500 WEST 33 STREET MANHATTAN | Alteration | Signed-off | 05/11/2023 | 07/19/2023 | Contractor WARD PIPING COMPANY INC Filer GILLMAN CONSULTING INC | INSTALL NEW SPRINKLER HEADS AND RELATED PIPING FOR RU212 AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| M00863464 ↗ | 500 WEST 33 STREET MANHATTAN | Alteration | Signed-off | 05/11/2023 | 06/01/2023 | Contractor DUO PLUMBING & HTG CORP. Filer GILLMAN CONSULTING INC | REMOVE AND INSTALL NEW PLUMBING FIXTURES AND RELATED PIPING FOR RU 212 AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRES OR OCCU… |
| M00863462 ↗ | 500 WEST 33 STREET MANHATTAN | Alteration | Signed-off | 05/11/2023 | 05/31/2023 | Contractor STEADFAST DEVELOPMENT AND Filer GILLMAN CONSULTING INC | MODIFICATION TO EXISTING HVAC DUCTWORK AND RELATED PIPING FOR RU 212 AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUP… |
| M00787957 ↗ | 611 5 AVENUE MANHATTAN | Alteration | Signed-off | 08/16/2022 | 08/29/2022 | Contractor ABCO-PEERLESS SPRKLR CORP Filer PEROTTO CONSULTING MGT | #8607 - Sprinkler modifications in LV space. No change in egress, use, or occupancy. |
| M00787921 ↗ | 611 5 AVENUE MANHATTAN | Alteration | Signed-off | 08/16/2022 | 08/19/2022 | Contractor FOLOR INC Filer PEROTTO CONSULTING MGT | #8607 - Ductwork and Lighting modifications in existing retail space. No change in egress, use or occupancy. |
| B00364886 ↗ | 402 CLERMONT AVENUE BROOKLYN | Alteration | Signed-off | 09/03/2020 | 12/03/2021 | Contractor FLYTIGER P & H LTD | INSTALL PLUMBING FIXTURES. WORK FILED IN CONJUNCTION WITH CONVERSION FROM TWO TO ONE-FAMILY RESIDENCE (DOB ALT1# 321990182) |
| B00365366 ↗ | 402 CLERMONT AVENUE BROOKLYN | Alteration | Signed-off | 09/03/2020 | 11/23/2021 | Contractor FLYTIGER PLB & HTG LTD | INSTALL NEW SPRINKLER SYSTEM. FILED IN CONJUNCTION WITH ALT-1 DOB# 321990182. |
| B00611319 ↗ | 519 ROCKAWAY AVENUE | Alteration | Signed-off | 10/19/2021 | 11/15/2021 | Contractor COYLE CONTRACTING CORP | Modification to existing HVAC system as per plans filed herewith. No change in use, egress or occupancy under this application. |
| M00314089 ↗ | 159 5 AVENUE MANHATTAN | Alteration | Signed-off | 02/26/2020 | 04/22/2021 | Owner SHEFA LAND CORP. Contractor M&T PLBG AND HTG CO., INC Filer RIZZO GROUP | Modifications to the existing plumbing system on the cellar, 1st and 2nd floors as per plans. No change to use, egress or occupancy. |
| M00314105 ↗ | 159 5 AVENUE MANHATTAN | Alteration | Signed-off | 02/26/2020 | 04/21/2021 | Owner SHEFA LAND CORP. Contractor ASHLAR MECHANICAL CORP Filer BROOKBRIDGE CONSULTING | Modifications to the existing sprinkler system on the cellar, 1st and 2nd floors as per plans. No change to use, egress or occupancy. |
| M00314109 ↗ | 159 5 AVENUE MANHATTAN | Alteration | Signed-off | 02/26/2020 | 04/21/2021 | Owner SHEFA LAND CORP. Contractor ASHLAR MECHANICAL CORP Filer RIZZO GROUP | Modifications to the existing standpipe system on the 1st floor as per plans. No change to use, egress or occupancy. |
| Q00391647 ↗ | 37-02 82 STREET QUEENS | Alteration | Signed-off | 01/06/2021 | 01/12/2021 | Contractor GREGOR INDUSTRIES INC | Mechanical work for existing Capital One Bank Tenant Improvement. No change in use, egress, or occupancy. |
| X00371381 ↗ | 4191 WHITE PLAINS ROAD BRONX | Alteration | Signed-off | 07/20/2020 | 01/07/2021 | Contractor DUO PLUMBING & HTG CORP. Filer BURNHAM NATIONWIDE INC | Plumbing work pertaining to commercial build out. |
| M00313629 ↗ | 159 5 AVENUE MANHATTAN | Alteration | Signed-off | 02/26/2020 | 12/11/2020 | Owner SHEFA LAND CORP. Contractor SHAWMUT WOODWORKING & SUPPLY Filer RIZZO GROUP | Modifications to the existing HVAC system on the cellar, 1st and 2nd floors as per plans. No change to use, egress or occupancy. |
| B00364840 ↗ | 402 CLERMONT AVENUE BROOKLYN | Alteration | Signed-off | 09/03/2020 | 11/23/2020 | Contractor HENG YIP CONSTRUCTION COR | MECHANICAL WORK FILED IN CONJUNCTION WITH CONVERSION FROM A TWO TO ONE-FAMILY RESIDENCE (ALT-I # 321990182). INSTALL HVAC SYSTEM. |
| B00384271 ↗ | 1532 86 STREET BROOKLYN | Alteration | Signed-off | 08/14/2020 | 08/18/2020 | Contractor DANSON HEIGHTS SERVICE CO | filing application for direct replacement of 3 rooftop units. No change in use egress or occupancy. |
| B00311298 ↗ | 66 NORTH 3 STREET BROOKLYN | Alteration | Signed-off | 02/17/2020 | 07/10/2020 | Contractor SACHSE CONSTRUCTION AND | Modification to HVAC ductwork and related piping as shown on drawings filed herewith. No change in use, egress or occupancy. |
| B00361980 ↗ | 355 KNICKERBOCKER AVENUE BROOKLYN | Alteration | Signed-off | 07/06/2020 | 07/09/2020 | Contractor DANSON HEIGHTS SERVICE CO | HEREBY FILING FOR THE INSTALLATION OF ROOFTOP UNITS. NO CHANGE TO USE EGRESS OR OCCUPANCY. |
| M00361985 ↗ | 1 WHITEHALL STREET MANHATTAN | Alteration | Signed-off | 07/06/2020 | 07/09/2020 | Contractor DANSON HEIGHTS SERVICE CO | INSTALLATION OF HVAC UNITS. NO CHANGE TO USE EGRESS OR OCCUPANCY. |
| B00257669 ↗ | 154A DIAMOND STREET BROOKLYN | Alteration | Signed-off | 11/27/2019 | 07/06/2020 | Contractor QUALITY RENOVATION TEAM I | INSTALLATION OF NEW MECHANICAL SYSTEM IN CONJUNCTION WITH RENOVATION OF 2 FAMILY. RELATED GENERAL CONSTRUCTION, PLUMBING AND STRUCTURAL FILE… |
| B00337475 ↗ | 165 JORALEMON STREET BROOKLYN | Alteration | Signed-off | 05/29/2020 | 06/11/2020 | Contractor STRUCTURECRAFT CONTRACTIN | Relocation of (3) condensing units and related piping from the cellar to the Roof. |
| B00333530 ↗ | 679 VAN SINDEREN AVENUE BROOKLYN | Alteration | Signed-off | 05/20/2020 | 06/08/2020 | Contractor SMITH-MCCORD, INC | INSTALLATION OF DUCTWORK IN CONJUNCTION WITH TENANT BUILD OUT. NO CHANGE IN USE EGRESS OR OCCUPANCY. |
| M00226009 ↗ | 715 LEXINGTON AVENUE MANHATTAN | Alteration | Signed-off | 11/06/2019 | 05/11/2020 | Owner VORNADO REALTY TRUST Contractor SACHSE CONSTRUCTION AND Filer GILLMAN CONSULTING INC | Modification to existing HVAC system as shown on drawings filed herewith. No change in use, egress or occupancy. |
| B00188596 ↗ | 26 3 PLACE BROOKLYN | Alteration | Signed-off | 07/10/2019 | 03/23/2020 | Contractor BLACK SQUARE BUILDERS COR | filing for mechanical work for CONVERTING FROM TWO DWELING UNITS TO A SINGLE FAMILY RESIDENCE. |
| B00295247 ↗ | 384 MOTHER GASTON BLVD BROOKLYN | Alteration | Signed-off | 02/10/2020 | 02/11/2020 | Contractor SMITH-MCCORD, INC | DIRECT REPLACMENT OF ROOF TOP HVAC UNITS. NO CHANGE TO USE, OCCUPANCY OR EGRESS. |
| M00225960 ↗ | 715 LEXINGTON AVENUE MANHATTAN | Alteration | Signed-off | 11/06/2019 | 01/31/2020 | Owner VORNADO REALTY TRUST Contractor BEDROCK PLBG. & HTG., INC Filer GILLMAN CONSULTING INC | Remove and install new plumbing fixtures as shown on drawings filed herewith. No change in use, egress or occupancy. |
| M00263176 ↗ | 115 SPRING STREET MANHATTAN | Alteration | Signed-off | 12/09/2019 | 01/07/2020 | Owner SL GREEN REALTY CORP Contractor PHILIP ANDREWS LLC | mechanical modifications taking place on the cellar floor as per plans filed herewith. no change in use, egress or occupancy. |
| Q00201429 ↗ | 93-20 ASTORIA BOULEVARD QUEENS | Alteration | Signed-off | 08/05/2019 | 12/16/2019 | Owner WALGREENS Contractor AMERICAN PLBG SOLUTIONS I Filer JAM CONSULTANTS, INC. | REPLACEMENT OF ROOF TOP UNITS ON EXISTING DUNNAGE AND PIPING |
| Q00201223 ↗ | 119-02 ROCKAWAY BOULEVARD QUEENS | Alteration | Signed-off | 08/05/2019 | 12/13/2019 | Owner WALGREENS Contractor AMERICAN PLBG SOLUTIONS I Filer JAM CONSULTANTS, INC. | REPLACEMENT OF ROOFTOP UNITS ON EXISTING DUNNAGE AND PIPING. |
| B00188609 ↗ | 26 3 PLACE BROOKLYN | Alteration | Signed-off | 07/10/2019 | 12/09/2019 | Contractor NICHOLAS SUIDA | PLUMBING WORK FILED FOR CONVERSION FROM TWO FAMILY TO 1 FAMILY RESIDENCE. GENERAL CONSTRUCTION WORK FILED UNDER APPLICATION #321594066 |
| S00201688 ↗ | 2655 RICHMOND AVENUE STATEN ISLAND | Alteration | Signed-off | 09/12/2019 | 10/10/2019 | Contractor THE BENMOORE CONSTRUCTION | SPACE #2492-TENANT WORK: CLAIRE'S: INTERIOR TENANT IMPROVEMENT. EXISTING HVAC UNIT TO REMAIN. MODIFY/EXTEND DUCTWORK TO MATCH NEW AIR DEV… |
| M00190412 ↗ | 205 EAST 31 STREET MANHATTAN | Alteration | Filed — no permit on record | 09/12/2019 | — | — | — |
| M00191178 ↗ | 205 EAST 31 STREET MANHATTAN | Alteration | Filed — no permit on record | 09/12/2019 | — | — | |
| M00207438 ↗ | 205 EAST 31 STREET MANHATTAN | Alteration | Filed — no permit on record | 09/12/2019 | — | — | — |
| Q00201719 ↗ | 82-67 BROADWAY QUEENS | Alteration | Signed-off | 08/12/2019 | 08/30/2019 | Owner WALGREENS Contractor DANSON HEIGHTS SERVICE CO Filer JAM CONSULTANTS, INC. | REPLACEMENT OF ROOFTOP UNITS ON EXISTING DUNNAGE AND PIPING. |
| Q00202018 ↗ | 33-55 34 AVENUE QUEENS | Alteration | Signed-off | 08/13/2019 | 08/30/2019 | Owner WALGREENS Contractor DANSON HEIGHTS SERVICE CO Filer JAM CONSULTANTS, INC. | REPLACEMENT OF ROOFTOP UNITS ON EXISTING DUNNAGE AND PIPING |
| Q00196275 ↗ | 149-28 14 AVENUE QUEENS | Alteration | Signed-off | 08/12/2019 | 08/15/2019 | Contractor DANSON HEIGHTS SERVICE CO | REPLACEMENT OF ROOF TOP UNITS ON EXISTING DUNNAGE AND PIPING. |
| Building | Filings | Most Recent |
|---|---|---|
| 1585 BROADWAY ↗ | 2 | 04/21/2026 |
| 155-08 CROSS BAY BOULEVARD ↗ | 1 | 10/13/2023 |
| 500 WEST 33 STREET ↗ | 5 | 09/13/2023 |
| 1941 WILLIAMSBRIDGE ROAD ↗ | 2 | 08/17/2023 |
| 611 5 AVENUE ↗ | 2 | 08/04/2022 |
| 402 CLERMONT AVENUE ↗ | 8 | 06/17/2022 |
| 154A DIAMOND STREET ↗ | 3 | 12/18/2020 |
| 37-02 82 STREET ↗ | 1 | 08/27/2020 |
| 66 NORTH 3 STREET ↗ | 4 | 08/11/2020 |
| 4191 WHITE PLAINS ROAD ↗ | 1 | 07/15/2020 |
| 159 5 AVENUE ↗ | 4 | 02/11/2020 |
| 119-02 ROCKAWAY BOULEVARD ↗ | 2 | 09/12/2019 |
| 715 LEXINGTON AVENUE ↗ | 3 | 09/11/2019 |
| 93-20 ASTORIA BOULEVARD ↗ | 2 | 09/11/2019 |
| 33-55 34 AVENUE ↗ | 2 | 08/21/2019 |
| 205 EAST 31 STREET ↗ | 3 | 07/10/2019 |
| 26 3 PLACE ↗ | 4 | — |
| 384 MOTHER GASTON BLVD ↗ | 1 | — |
| 679 VAN SINDEREN AVENUE ↗ | 1 | — |
| 165 JORALEMON STREET ↗ | 1 | — |
| 355 KNICKERBOCKER AVENUE ↗ | 1 | — |
| 1532 86 STREET ↗ | 1 | — |
| 519 ROCKAWAY AVENUE ↗ | 1 | — |
| 115 SPRING STREET ↗ | 1 | — |
| 1 WHITEHALL STREET ↗ | 1 | — |
| 100 WEST 125 STREET ↗ | 1 | — |
| 149-28 14 AVENUE ↗ | 1 | — |
| 82-67 BROADWAY ↗ | 1 | — |
| 2655 RICHMOND AVENUE ↗ | 1 | — |