| Job | Address | Type | Status | Filed | Latest permit | On the job | Description |
|---|---|---|---|---|---|---|---|
| M01303314 ↗ | 5 EAST 42 STREET MANHATTAN | Alteration | Permit Issued | 10/16/2025 | 08/18/2026 | Owner East 43RD NYC LLC Contractor WCDNY INC Filer DVA Advisors | POPS area demolition and eventual restoration to its original state. |
| M01225674 ↗ | 1 WARDS ISLAND MANHATTAN | Alteration CO | Permit Issued | 09/09/2025 | 04/17/2026 | Owner NYC PARKS DEPARTMENT Contractor THE WHITING-TURNER CONTRA | Structural work associated with alteration of existing nature center. |
| M00723903 ↗ | 200 EAST 75TH STREET MANHATTAN | New Building | Permit Issued | 05/09/2022 | 03/19/2026 | Owner EJS GROUP Contractor TRITON CONSTRUCTION CO., | Underground piping in conjunction with New Building # M00723903. |
| B08051392 ↗ | 1215 FULTON STREET BROOKLYN | Alteration | Permit Issued | 02/02/2023 | 04/29/2025 | Contractor DEMAR MECHANICAL INC | Underground piping in conjunction with NB # 321597777. Application filed under 2014 code per BB 2021-007. |
| M00958930 ↗ | 77 WATER STREET MANHATTAN | Alteration | Permit Issued | 11/21/2023 | 01/18/2024 | Owner SAGE REALTY CORP Contractor ARCHSTONE BUILDERS LLC Filer MBE CODE & ZONING LLC | STRUCTURAL WORK. |
| X00687811 ↗ | 2401 3 AVENUE BRONX | Alteration | Permit Issued | 05/12/2022 | 12/27/2023 | Contractor ULTIMATE SAFETY ASS INC | Application for work to regrade site in an A-Zone in order to remove land from an area of Special Flood Hazard pursuant to RCNY 3606-02. |
| Person | Filings | Most recent |
|---|---|---|
| Rick Parisi | 9 | 08/06/2026 |
| ROBERT OSTERLOF | 3 | 04/11/2023 |
| Name | Jobs together | Most recent |
|---|---|---|
| GEA CONSULTING ENGINEERS | 2 | 04/08/2026 |
| ANCORA ENGINEERING, PLLC | 1 | 08/20/2026 |
| BEYER BLINDER BELLE | 1 | 04/08/2026 |
| COSENTINI ASSOCIATES | 1 | 01/05/2024 |
| DOUGLAS P. GONZALEZ | 1 | 01/05/2024 |
| Forst Consulting and Arch., PLLC | 1 | 08/20/2026 |
| GACE DPC | 1 | 04/08/2026 |
| Guth DeConzo Consulting Engineers | 1 | 08/20/2026 |
| IMEG Consulting Corp. | 1 | 08/20/2026 |
| MRCE | 1 | 04/08/2026 |
| SILMAN | 1 | 08/20/2026 |
| Name | Jobs together | Most recent |
|---|---|---|
| DEMAR MECHANICAL INC | 2 | 04/08/2026 |
| TRITON CONSTRUCTION CO., | 2 | 04/08/2026 |
| ARCHSTONE BUILDERS LLC | 1 | 01/05/2024 |
| ARMON MECHANICAL INC | 1 | 04/08/2026 |
| ASPRO PLUMBING, INC | 1 | 08/20/2026 |
| BEN CONTRACTING GROUP COR | 1 | 06/08/2018 |
| DEMAR PLUMBING CORP | 1 | 10/29/2025 |
| EAST 43RD NYC LLC | 1 | 10/16/2025 |
| HUDSON MERIDIAN CONSTRUCT | 1 | 05/12/2022 |
| MAC FELDER INC | 1 | 01/05/2024 |
| PRIME MECHANICAL CONTRACT | 1 | 08/20/2026 |
| PRIME SPRINKLER CORP | 1 | 10/29/2025 |
| STAT FIRE SPRINKLER NYC C | 1 | 04/08/2026 |
| STRUCTURE TONE, LLC | 1 | 10/19/2023 |
| STUART N SCHWARTZ | 1 | 04/08/2026 |
| THE WHITING-TURNER CONTRA | 1 | 08/20/2026 |
| WCDNY INC | 1 | 10/16/2025 |
| Name | Jobs together | Most recent |
|---|---|---|
| BOP WEST 31ST STREET LLC | 1 | 10/19/2023 |
| CLIPPER EQUITY | 1 | 06/08/2018 |
| EJS GROUP | 1 | 04/08/2026 |
| East 43RD NYC LLC | 1 | 10/16/2025 |
| NYC PARKS DEPARTMENT | 1 | 08/20/2026 |
| SAGE REALTY CORP | 1 | 01/05/2024 |
| Name | Jobs together | Most recent |
|---|---|---|
| WILLIAM VITACCO ASSOCIATES | 5 | 08/20/2026 |
| DVA Advisors | 2 | 10/29/2025 |
| JM ZONING, LLC. | 1 | 06/08/2018 |
| MBE CODE & ZONING LLC | 1 | 01/05/2024 |
| Job | Address | Type | Status | Filed | Latest permit | On the job | Description |
|---|---|---|---|---|---|---|---|
| M01303314 ↗ | 5 EAST 42 STREET MANHATTAN | Alteration | Permit Issued | 10/16/2025 | 08/18/2026 | Owner East 43RD NYC LLC Contractor WCDNY INC Filer DVA Advisors | POPS area demolition and eventual restoration to its original state. |
| M01225674 ↗ | 1 WARDS ISLAND MANHATTAN | Alteration CO | Permit Issued | 09/09/2025 | 04/17/2026 | Owner NYC PARKS DEPARTMENT Contractor THE WHITING-TURNER CONTRA | Structural work associated with alteration of existing nature center. |
| M00723903 ↗ | 200 EAST 75TH STREET MANHATTAN | New Building | Permit Issued | 05/09/2022 | 03/19/2026 | Owner EJS GROUP Contractor TRITON CONSTRUCTION CO., | Underground piping in conjunction with New Building # M00723903. |
| B08051392 ↗ | 1215 FULTON STREET BROOKLYN | Alteration | Permit Issued | 02/02/2023 | 04/29/2025 | Contractor DEMAR MECHANICAL INC | Underground piping in conjunction with NB # 321597777. Application filed under 2014 code per BB 2021-007. |
| M00958930 ↗ | 77 WATER STREET MANHATTAN | Alteration | Permit Issued | 11/21/2023 | 01/18/2024 | Owner SAGE REALTY CORP Contractor ARCHSTONE BUILDERS LLC Filer MBE CODE & ZONING LLC | STRUCTURAL WORK. |
| X00687811 ↗ | 2401 3 AVENUE BRONX | Alteration | Permit Issued | 05/12/2022 | 12/27/2023 | Contractor ULTIMATE SAFETY ASS INC | Application for work to regrade site in an A-Zone in order to remove land from an area of Special Flood Hazard pursuant to RCNY 3606-02. |
| M00836316 ↗ | 666 5 AVENUE MANHATTAN | Alteration | Signed-off | 03/27/2023 | 06/07/2023 | Owner BOP WEST 31ST STREET LLC Contractor STRUCTURE TONE, LLC | Landscaping, planting, and associated work at 8th floor terraces. No change to egress, use, or occupancy. |
| B00007437 ↗ | 107 COLUMBIA HEIGHTS BROOKLYN | Alteration | Signed-off | 06/08/2018 | 03/19/2020 | Owner CLIPPER EQUITY Contractor BEN CONTRACTING GROUP COR Filer JM ZONING, LLC. | FILING CURB CUT IN CONJUNCTION WITH ALT1 # 321194710 |
| Building | Filings | Most Recent |
|---|---|---|
| 1 WARDS ISLAND ↗ | 2 | 08/06/2026 |
| 5 EAST 42 STREET ↗ | 1 | 10/15/2025 |
| 77 WATER STREET ↗ | 1 | 11/07/2023 |
| 666 5 AVENUE ↗ | 3 | 10/13/2023 |
| 1215 FULTON STREET ↗ | 1 | 04/11/2023 |
| 200 EAST 75TH STREET ↗ | 2 | 05/10/2022 |
| 2401 3 AVENUE ↗ | 1 | 02/25/2022 |
| 107 COLUMBIA HEIGHTS ↗ | 1 | 12/21/2017 |