| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M00636541 ↗ | 790 8 AVENUE MANHATTAN | Alteration | Signed-off | 12/15/2021 | 04/01/2024 | Design SURFACE DESIGN Contractor ENTERPRISE ARCHITECTURAL* | FACADE RE-CLADDING AT MASS WALL AND COLUMNS AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY |
| M00721664 ↗ | 790 8 AVENUE MANHATTAN | Alteration | Filed — no permit on record | 05/02/2022 | — | — | |
| M00674652 ↗ | 150 WEST 79 STREET MANHATTAN | Alteration | Signed-off | 04/08/2022 | 04/28/2022 | Design ERIK SCHULTZ ARCHITECTURE Contractor EURO GROUP DESIGN GROUP Filer RIZZO GROUP | Architectural, structural and HVAC modifications to apartment 2B as per plans. No change to use, egress or occupancy. |
| Name | Projects together | Most recent |
|---|---|---|
| ERIK SCHULTZ ARCHITECTURE | 1 | 02/22/2023 |
| KIEFER & SCHUSTER ENGINEERING PLLC | 1 | 05/02/2022 |
| SURFACE DESIGN | 1 | 12/15/2021 |
| Name | Projects together | Most recent |
|---|---|---|
| EASI CAULKING INC | 1 | 12/15/2021 |
| ENTERPRISE ARCHITECTURAL* | 1 | 12/15/2021 |
| EURO GROUP DESIGN GROUP | 1 | 02/22/2023 |
| EXTERIOR CLADDING TEC LLC | 1 | 12/15/2021 |
| Name | Projects together | Most recent |
|---|---|---|
| RPH HOTELS 48TH STREET OWNER, LLC | 2 | 05/02/2022 |
| Name | Projects together | Most recent |
|---|---|---|
| MUNICIPAL BUILDING CONSULTANTS | 2 | 05/02/2022 |
| RIZZO GROUP | 1 | 02/22/2023 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M00636541 ↗ | 790 8 AVENUE MANHATTAN | Alteration | Signed-off | 12/15/2021 | 04/01/2024 | Design SURFACE DESIGN Contractor ENTERPRISE ARCHITECTURAL* | FACADE RE-CLADDING AT MASS WALL AND COLUMNS AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY |
| M00721664 ↗ | 790 8 AVENUE MANHATTAN | Alteration | Filed — no permit on record | 05/02/2022 | — | — | |
| M00674652 ↗ | 150 WEST 79 STREET MANHATTAN | Alteration | Signed-off | 04/08/2022 | 04/28/2022 | Design ERIK SCHULTZ ARCHITECTURE Contractor EURO GROUP DESIGN GROUP Filer RIZZO GROUP | Architectural, structural and HVAC modifications to apartment 2B as per plans. No change to use, egress or occupancy. |
| Building | Filings | Most Recent |
|---|---|---|
| 150 WEST 79 STREET ↗ | 2 | 02/22/2023 |
| 790 8 AVENUE ↗ | 2 | 05/02/2022 |
| Date | Requirement | Building | Inspector | Role |
|---|---|---|---|---|
| 03/08/2023 | Structural Steel - Details | 150 WEST 79 STREET | BRADFORD KIEFER | special |
| 03/08/2023 | Mechanical Systems | 150 WEST 79 STREET | YURI KATZ | special |
| 03/08/2023 | Fire-Resistant Penetrations and Joints | 150 WEST 79 STREET | YURI KATZ | special |
| 03/08/2023 | Final | 150 WEST 79 STREET | ERIK SCHULTZ | progress |
| 03/08/2023 | Lighting in dwelling units | 150 WEST 79 STREET | ERIK SCHULTZ | energy_progress |
| 03/08/2023 | Lighting controls | 150 WEST 79 STREET | ERIK SCHULTZ | energy_progress |
| 08/23/2022 | Lighting in dwelling units | 150 WEST 79 STREET | ERIK SCHULTZ | energy_progress |
| 08/23/2022 | Lighting controls | 150 WEST 79 STREET | ERIK SCHULTZ | energy_progress |
| 08/23/2022 | Final | 150 WEST 79 STREET | ERIK SCHULTZ | progress |
| 08/23/2022 | Structural Steel - Details | 150 WEST 79 STREET | BRADFORD KIEFER | special |
| 08/23/2022 | Mechanical Systems | 150 WEST 79 STREET | YURI KATZ | special |
| 08/23/2022 | Fire-Resistant Penetrations and Joints | 150 WEST 79 STREET | YURI KATZ | special |