| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M01275010 ↗ | 101 BARCLAY STREET MANHATTAN | Alteration | Signed-off | 10/07/2025 | 10/23/2025 | Design ROBERT DERECTOR ASSOCIATES Owner The Bank of New York Contractor STRUCTURE TONE, LLC | Filing for removal and installation of HVAC units and related ducts and piping for office renovations. No change in use, egress, or occupanc… |
| M00946092 ↗ | 101 BARCLAY STREET MANHATTAN | Alteration CO | Permit Issued | 11/02/2023 | 10/04/2024 | Design MMOSER ASSOCIATES Owner The Bank of New York Contractor STRUCTURE TONE, LLC | Application filed for interior work only with a change of occupancy for the new PA space. NO CHANGE TO ZONING BULK PROPSED UNDER THIS APPLIC… |
| M00946258 ↗ | 101 BARCLAY STREET MANHATTAN | Alteration | Signed-off | 11/02/2023 | 11/15/2023 | Design ROBERT DERECTOR ASSOCIATES Contractor SIRINA FIRE PROT CORP | Installation of new ductwork, VAVs, air outlets, thermostats, and (1) FCU and its corresponding piping. |
| M00946262 ↗ | 101 BARCLAY STREET MANHATTAN | Alteration | Signed-off | 11/02/2023 | 11/08/2023 | Design GILSANZ MURRAY STEFICEK LLP Contractor STRUCTURE TONE, LLC | Filing for structural modifications and slab-infill of existing floor space. Work does not include partial demolition and does not affect st… |
| M00856110 ↗ | 101 BARCLAY STREET MANHATTAN | Alteration | Signed-off | 06/13/2023 | 06/20/2023 | Design GKV ARCHITECTS Contractor NYCAN BUILDERS LLC | Construction of bridge from 21st floor elevator lobby to roof top terrace. No change in occupancy group. Change in egress. |
| M00856115 ↗ | 101 BARCLAY STREET MANHATTAN | Alteration | Signed-off | 05/31/2023 | 06/15/2023 | Design GILSANZ MURRAY STEFICEK LLP Contractor NYCAN BUILDERS LLC | Filing for structural component of construction of bridge form 21st floor elevator lobby to roof top terrace. |
| Name | Projects together | Most recent |
|---|---|---|
| GKV ARCHITECTS | 4 | 06/15/2023 |
| ROBERT DERECTOR ASSOCIATES | 3 | 10/07/2025 |
| GILSANZ MURRAY STEFICEK LLP | 2 | 11/02/2023 |
| MMOSER ASSOCIATES | 2 | 11/02/2023 |
| GENSLER | 1 | 12/03/2019 |
| METHOD ARCHITECTS PLLC | 1 | 12/22/2022 |
| Name | Projects together | Most recent |
|---|---|---|
| STRUCTURE TONE, LLC | 8 | 10/07/2025 |
| NYCAN BUILDERS LLC | 4 | 06/15/2023 |
| SIRINA FIRE PROT CORP | 1 | 11/02/2023 |
| Name | Projects together | Most recent |
|---|---|---|
| The Bank of New York | 3 | 10/07/2025 |
| BNYMELLON | 1 | 02/22/2021 |
| Name | Projects together | Most recent |
|---|---|---|
| A1 EXPEDITING SERVICE CORP. | 8 | 10/07/2025 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M01275010 ↗ | 101 BARCLAY STREET MANHATTAN | Alteration | Signed-off | 10/07/2025 | 10/23/2025 | Design ROBERT DERECTOR ASSOCIATES Owner The Bank of New York Contractor STRUCTURE TONE, LLC | Filing for removal and installation of HVAC units and related ducts and piping for office renovations. No change in use, egress, or occupanc… |
| M00946092 ↗ | 101 BARCLAY STREET MANHATTAN | Alteration CO | Permit Issued | 11/02/2023 | 10/04/2024 | Design MMOSER ASSOCIATES Owner The Bank of New York Contractor STRUCTURE TONE, LLC | Application filed for interior work only with a change of occupancy for the new PA space. NO CHANGE TO ZONING BULK PROPSED UNDER THIS APPLIC… |
| M00946258 ↗ | 101 BARCLAY STREET MANHATTAN | Alteration | Signed-off | 11/02/2023 | 11/15/2023 | Design ROBERT DERECTOR ASSOCIATES Contractor SIRINA FIRE PROT CORP | Installation of new ductwork, VAVs, air outlets, thermostats, and (1) FCU and its corresponding piping. |
| M00946262 ↗ | 101 BARCLAY STREET MANHATTAN | Alteration | Signed-off | 11/02/2023 | 11/08/2023 | Design GILSANZ MURRAY STEFICEK LLP Contractor STRUCTURE TONE, LLC | Filing for structural modifications and slab-infill of existing floor space. Work does not include partial demolition and does not affect st… |
| M00856110 ↗ | 101 BARCLAY STREET MANHATTAN | Alteration | Signed-off | 06/13/2023 | 06/20/2023 | Design GKV ARCHITECTS Contractor NYCAN BUILDERS LLC | Construction of bridge from 21st floor elevator lobby to roof top terrace. No change in occupancy group. Change in egress. |
| M00856115 ↗ | 101 BARCLAY STREET MANHATTAN | Alteration | Signed-off | 05/31/2023 | 06/15/2023 | Design GILSANZ MURRAY STEFICEK LLP Contractor NYCAN BUILDERS LLC | Filing for structural component of construction of bridge form 21st floor elevator lobby to roof top terrace. |
| M08047616 ↗ | 101 BARCLAY STREET MANHATTAN | Alteration | Signed-off | 12/22/2022 | 01/04/2023 | Design METHOD ARCHITECTS PLLC Contractor NYCAN BUILDERS LLC | Filing for interior renovations to existing office space to create 17th floor boardroom. Removal and installation of non load-bearing partit… |
| M08049019 ↗ | 101 BARCLAY STREET MANHATTAN | Alteration | Signed-off | 12/19/2022 | 12/22/2022 | Design GKV ARCHITECTS Contractor STRUCTURE TONE, LLC | Filing for interior renovation of existing office space on 1st floor. Removal and installation of non load-bearing partitions, doors, and fi… |
| M00767417 ↗ | 101 BARCLAY STREET MANHATTAN | Alteration | Signed-off | 08/15/2022 | 08/19/2022 | Design GKV ARCHITECTS Contractor STRUCTURE TONE, LLC | Filing for interior renovations as per plans filed herewith. Removal and installation of non bearing partitions, doors, and finishes. No cha… |
| M00694773 ↗ | 101 BARCLAY STREET MANHATTAN | Alteration | Signed-off | 05/25/2022 | 06/01/2022 | Design GKV ARCHITECTS Contractor NYCAN BUILDERS LLC | Installation on non bearing partitions and finishes as per plans filed herewith. No change in use, egress, or occupancy under this applicati… |
| M00315321 ↗ | 101 BARCLAY STREET MANHATTAN | Alteration | Signed-off | 02/22/2021 | 03/04/2021 | Design ROBERT DERECTOR ASSOCIATES Owner Bank Of New York Contractor STRUCTURE TONE, LLC | Modifications to existing mechanical system. No change in use, occupancy or egress. |
| M00450268 ↗ | 101 BARCLAY STREET MANHATTAN | Alteration | Signed-off | 02/22/2021 | 03/04/2021 | Design MMOSER ASSOCIATES Owner BNYMELLON Contractor STRUCTURE TONE, LLC | Removal and installation of interior non bearing partitions and related finishes as per plans filed herewith. No change in use, egress or oc… |
| M00269442 ↗ | 101 BARCLAY STREET MANHATTAN | No Work | Filed — no permit on record | 12/03/2019 | — | Design GENSLER | — |
| Building | Filings | Most Recent |
|---|---|---|
| 101 BARCLAY STREET ↗ | 13 | 10/07/2025 |