| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| X01049513 ↗ | 4499 WALDO AVENUE BRONX | Alteration | Signed-off | 07/22/2024 | 11/19/2024 | Design BUILT ENGINEERS, P. C. Contractor CAPITAL CONTR P & H CORP Filer CSR EXPEDITERS | INSTALLATION OF SPRINKLER PIPING, HEADS, AND APPURTANCES AT FIRST FLOOR GARAGE. TIE INTO EXISTING BUILDING SPRINKLER SYSTEM. |
| X00974164 ↗ | 4499 WALDO AVENUE BRONX | Alteration | Signed-off | 01/15/2024 | 07/03/2024 | Design STEVEN LEONE Contractor CENTRAL CONSULTING & CONT | REPLACE CONCRETE RAMP AND HANDRAILS FOR THE ENTRANCE TO THE EXISTING PARKING GARAGE ON 2ND FLOOR AS PER PLANS FILED HEREWITH, NO CHANGE TO U… |
| X00401460 ↗ | 4499 WALDO AVENUE BRONX | Alteration | Signed-off | 09/23/2020 | 03/23/2022 | Design JFK&M CONSULTING ENGINEERS Contractor ALJER PLBG & HTG CORP | PLUMBING FIXTURES INSTALLATION AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OROCCUPANCY |
| Name | Projects together | Most recent |
|---|---|---|
| BUILT ENGINEERS, P. C. | 1 | 01/14/2025 |
| JFK&M CONSULTING ENGINEERS | 1 | 09/23/2020 |
| STEVEN LEONE | 1 | 01/15/2024 |
| Name | Projects together | Most recent |
|---|---|---|
| ALJER PLBG & HTG CORP | 1 | 09/23/2020 |
| CAPITAL CONTR P & H CORP | 1 | 01/14/2025 |
| CENTRAL CONSULTING & CONT | 1 | 01/15/2024 |
| Name | Projects together | Most recent |
|---|---|---|
| METHODIST HOME FOR NURSING AND REHA | 3 | 01/14/2025 |
| Name | Projects together | Most recent |
|---|---|---|
| CSR EXPEDITERS | 1 | 01/14/2025 |
| MUNICIPAL BUILDING CONSULTANTS | 1 | 01/15/2024 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| X01049513 ↗ | 4499 WALDO AVENUE BRONX | Alteration | Signed-off | 07/22/2024 | 11/19/2024 | Design BUILT ENGINEERS, P. C. Contractor CAPITAL CONTR P & H CORP Filer CSR EXPEDITERS | INSTALLATION OF SPRINKLER PIPING, HEADS, AND APPURTANCES AT FIRST FLOOR GARAGE. TIE INTO EXISTING BUILDING SPRINKLER SYSTEM. |
| X00974164 ↗ | 4499 WALDO AVENUE BRONX | Alteration | Signed-off | 01/15/2024 | 07/03/2024 | Design STEVEN LEONE Contractor CENTRAL CONSULTING & CONT | REPLACE CONCRETE RAMP AND HANDRAILS FOR THE ENTRANCE TO THE EXISTING PARKING GARAGE ON 2ND FLOOR AS PER PLANS FILED HEREWITH, NO CHANGE TO U… |
| X00401460 ↗ | 4499 WALDO AVENUE BRONX | Alteration | Signed-off | 09/23/2020 | 03/23/2022 | Design JFK&M CONSULTING ENGINEERS Contractor ALJER PLBG & HTG CORP | PLUMBING FIXTURES INSTALLATION AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OROCCUPANCY |
| Building | Filings | Most Recent |
|---|---|---|
| 4499 WALDO AVENUE ↗ | 3 | 01/14/2025 |