| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M01322719 | 919 3RD AVENUE MANHATTAN | Alteration | Permit Issued | 01/20/2026 | 01/30/2026 | Design MG ENGINEERING D.P.C. Contractor ABCO-PEERLESS SPRKLR CORP | Modifications to the existing sprinkler system on the 46th Floor, as per plans. No change to use, egress, or occupancy. |
| M01322724 | 919 3RD AVENUE MANHATTAN | Alteration | Permit Issued | 01/20/2026 | 01/30/2026 | Design MG ENGINEERING D.P.C. Owner SL Green Contractor ABCO-PEERLESS SPRKLR CORP Filer RIZZO GROUP | Modifications to the existing standpipe system on the 46th Floor, as per plans. No change to use, egress, or occupancy. |
| M01322733 | 919 3RD AVENUE MANHATTAN | Alteration | Permit Issued | 12/22/2025 | 01/30/2026 | Design MG ENGINEERING D.P.C. Contractor ABCO-PEERLESS SPRKLR CORP | Modifications to the existing sprinkler system on the 47th Floor, as per plans. No change to use, egress, or occupancy. |
| M01322738 | 919 3RD AVENUE MANHATTAN | Alteration | Permit Issued | 12/22/2025 | 01/30/2026 | Design MG ENGINEERING D.P.C. Owner SL Green Contractor ABCO-PEERLESS SPRKLR CORP Filer RIZZO GROUP | Modifications to the existing standpipe system on the 47th Floor, as per plans. No change to use, egress, or occupancy. |
| M01322293 ↗ | 919 3RD AVENUE MANHATTAN | Alteration | Permit Issued | 12/22/2025 | 01/28/2026 | Design MG ENGINEERING D.P.C. Owner SL Green Contractor LAB PLBG & HTG CO INC Filer RIZZO GROUP | Modifications, replacements, and additions to the existing plumbing fixtures and piping on the 45th Floor, as per plans. No change to use, … |
| M01322716 | 919 3RD AVENUE MANHATTAN | Alteration | Signed-off | 01/20/2026 | 01/28/2026 | Design MG ENGINEERING D.P.C. Owner SL Green Contractor LAB PLBG & HTG CO INC Filer RIZZO GROUP | Modifications, replacements, and additions to the existing plumbing fixtures and piping on the 46th Floor, as per plans. No change to use, … |
| Name | Projects together | Most recent |
|---|---|---|
| MG Engineering | 12 | 04/28/2026 |
| Loffredo Brooks Architects | 3 | 06/03/2026 |
| MSS Engineering | 2 | 02/27/2020 |
| Ramboll | 1 | 09/13/2024 |
| Severud Associates | 1 | 01/22/2026 |
| Name | Projects together | Most recent |
|---|---|---|
| JT Magen & Company | 7 | 06/03/2026 |
| Abco-Peerless Sprinkler | 6 | 01/20/2026 |
| Lab Plumbing & Heating Co | 3 | 04/28/2026 |
| R J Green Construction | 2 | 02/27/2020 |
| Suffolk Construction Company | 1 | 09/13/2024 |
| Name | Projects together | Most recent |
|---|---|---|
| SL Green Realty | 10 | 06/03/2026 |
| Nysif | 2 | 02/27/2020 |
| NH Expediting and Consulting | 1 | 09/13/2024 |
| Name | Projects together | Most recent |
|---|---|---|
| Rizzo Group | 10 | 06/03/2026 |
| Almadina Engineering | 1 | 11/27/2018 |
| NH Expediting and Consulting | 1 | 09/13/2024 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M01322719 | 919 3RD AVENUE MANHATTAN | Alteration | Permit Issued | 01/20/2026 | 01/30/2026 | Design MG ENGINEERING D.P.C. Contractor ABCO-PEERLESS SPRKLR CORP | Modifications to the existing sprinkler system on the 46th Floor, as per plans. No change to use, egress, or occupancy. |
| M01322724 | 919 3RD AVENUE MANHATTAN | Alteration | Permit Issued | 01/20/2026 | 01/30/2026 | Design MG ENGINEERING D.P.C. Owner SL Green Contractor ABCO-PEERLESS SPRKLR CORP Filer RIZZO GROUP | Modifications to the existing standpipe system on the 46th Floor, as per plans. No change to use, egress, or occupancy. |
| M01322733 | 919 3RD AVENUE MANHATTAN | Alteration | Permit Issued | 12/22/2025 | 01/30/2026 | Design MG ENGINEERING D.P.C. Contractor ABCO-PEERLESS SPRKLR CORP | Modifications to the existing sprinkler system on the 47th Floor, as per plans. No change to use, egress, or occupancy. |
| M01322738 | 919 3RD AVENUE MANHATTAN | Alteration | Permit Issued | 12/22/2025 | 01/30/2026 | Design MG ENGINEERING D.P.C. Owner SL Green Contractor ABCO-PEERLESS SPRKLR CORP Filer RIZZO GROUP | Modifications to the existing standpipe system on the 47th Floor, as per plans. No change to use, egress, or occupancy. |
| M01322293 ↗ | 919 3RD AVENUE MANHATTAN | Alteration | Permit Issued | 12/22/2025 | 01/28/2026 | Design MG ENGINEERING D.P.C. Owner SL Green Contractor LAB PLBG & HTG CO INC Filer RIZZO GROUP | Modifications, replacements, and additions to the existing plumbing fixtures and piping on the 45th Floor, as per plans. No change to use, … |
| M01322716 | 919 3RD AVENUE MANHATTAN | Alteration | Signed-off | 01/20/2026 | 01/28/2026 | Design MG ENGINEERING D.P.C. Owner SL Green Contractor LAB PLBG & HTG CO INC Filer RIZZO GROUP | Modifications, replacements, and additions to the existing plumbing fixtures and piping on the 46th Floor, as per plans. No change to use, … |
| M01322730 | 919 3RD AVENUE MANHATTAN | Alteration | Signed-off | 12/22/2025 | 01/28/2026 | Design MG ENGINEERING D.P.C. Owner SL Green Contractor LAB PLBG & HTG CO INC Filer RIZZO GROUP | Modifications, replacements, and additions to the existing plumbing fixtures and piping on the 47th Floor, as per plans. No change to use, … |
| M01322241 ↗ | 919 3RD AVENUE MANHATTAN | Alteration | Permit Issued | 12/22/2025 | 01/27/2026 | Contractor JT MAGEN & COMPANY INC | Interior renovation of existing office space with minor interior demolition, and work on partitions, doors, ceilings and finishes on the 45t… |
| M01322267 | 919 3RD AVENUE MANHATTAN | Alteration | Permit Issued | 12/22/2025 | 01/27/2026 | Design MG ENGINEERING D.P.C. Contractor JT MAGEN & COMPANY INC | Modifications of the existing HVAC system and associated ducts & piping on the 45th Floor, as per plans. No change to use, egress, or occupa… |
| M01322324 ↗ | 919 3RD AVENUE MANHATTAN | Alteration | Permit Issued | 12/22/2025 | 01/27/2026 | Design MG ENGINEERING D.P.C. Owner SL Green Contractor ABCO-PEERLESS SPRKLR CORP Filer RIZZO GROUP | Modifications to the existing sprinkler system on the 45th Floor, as per plans. No change to use, egress, or occupancy. |
| M01322354 ↗ | 919 3RD AVENUE MANHATTAN | Alteration | Permit Issued | 12/22/2025 | 01/27/2026 | Design MG ENGINEERING D.P.C. Owner SL Green Contractor ABCO-PEERLESS SPRKLR CORP Filer RIZZO GROUP | Modifications to the existing standpipe system on the 45th Floor, as per plans. No change to use, egress, or occupancy. |
| M01322689 ↗ | 919 3RD AVENUE MANHATTAN | Alteration | Permit Issued | 12/24/2025 | 01/27/2026 | Owner SL Green Contractor JT MAGEN & COMPANY INC Filer RIZZO GROUP | Interior renovation of existing office space with minor interior demolition, and work on partitions, doors, ceilings and finishes on the 45t… |
| M01322705 | 919 3RD AVENUE MANHATTAN | Alteration | Permit Issued | 01/22/2026 | 01/27/2026 | Design SEVERUD ASSOCIATES Owner SL Green Contractor JT MAGEN & COMPANY INC Filer RIZZO GROUP | Structural reinforcement on the 46th Floor, as per plans. No change to use, egress, or occupancy. |
| M01322713 ↗ | 919 3RD AVENUE MANHATTAN | Alteration | Permit Issued | 12/24/2025 | 01/27/2026 | Design MG ENGINEERING D.P.C. Owner SL Green Contractor JT MAGEN & COMPANY INC Filer RIZZO GROUP | Modifications of the existing HVAC system and associated ducts & piping on the 46th Floor, as per plans. No change to use, egress, or occupa… |
| M01322726 | 919 3RD AVENUE MANHATTAN | Alteration | Permit Issued | 12/22/2025 | 01/27/2026 | Contractor JT MAGEN & COMPANY INC | Interior renovation of existing office space with minor interior demolition, and work on partitions, doors, ceilings and finishes on the 47t… |
| M01322728 | 919 3RD AVENUE MANHATTAN | Alteration | Permit Issued | 12/22/2025 | 01/27/2026 | Design MG ENGINEERING D.P.C. Contractor JT MAGEN & COMPANY INC | Modifications of the existing HVAC system and associated ducts & piping on the 47th Floor, as per plans. No change to use, egress, or occupa… |
| Q01010107 | 93-05 168TH STREET QUEENS | Alteration | Signed-off | 03/04/2024 | 09/06/2024 | Design RAMBOLL Contractor SUFFOLK CONSTRUCTION COMP | Curb cut application filed to relocate existing curb cut so that it aligns with the new location of the garage door opening. |
| M00322493 | 199 CHURCH STREET MANHATTAN | Alteration | Permit Issued | 02/27/2020 | 03/02/2020 | Design MSS ENGINEERING PLLC Owner NYSIF Contractor R J GREEN CONSTRUCTI CORP | SUBMITTED ON BEHALF OF CONTRACTOR FOR THE INSTALLATION OF TEMPORARY CONSTRUCTION EQUIPMENT (SHED) 600 LF , IN CONJUNCTION WITH NYS-PROJECT# … |
| M00097951 | 199 CHURCH STREET MANHATTAN | Alteration | Permit Issued | 11/27/2018 | 01/17/2019 | Design MSS ENGINEERING PLLC Owner NYSIF Contractor R J GREEN CONSTRUCTI CORP Filer ALMADINA ENGINEERING PC | SUBMITTED ON BEHALF OF CONTRACTOR FOR THE INSTALLATION OF TEMPORARY CONSTRUCTION EQUIPMENT (650 LF OF SIDE-WALK SHED), IN CONJUNCTION WITH N… |