| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M00465611 | 1 POLICE PLAZA MANHATTAN | Alteration | Permit Issued | 02/26/2021 | 11/21/2024 | Design THORNTON TOMASETTI Contractor PADILLA CONSTRUCTION SERVICES | Various repairs exterior repairs to building courtyard |
| M00800899 | 80 JOHN STREET MANHATTAN | Alteration | Signed-off | 05/24/2023 | 09/28/2023 | Design CAMERON ENGINEERING Contractor CBG BUILDERS INC | Modifications to existing Mechanical System as per plans filed herewith. No change in use, egress or occupancy. |
| M00800897 | 80 JOHN STREET MANHATTAN | Alteration | Signed-off | 05/24/2023 | 09/25/2023 | Design CAMERON ENGINEERING Contractor P.H. WORKS INC | Modifications to existing plumbing fixtures as per plans filed herewith. No change in use, egress or occupancy. |
| M00800900 | 80 JOHN STREET MANHATTAN | Alteration | Signed-off | 05/24/2023 | 09/25/2023 | Design CAMERON ENGINEERING Contractor F.S. WORKS INC | Modification to existing Sprinkler System as per plans filed herewith. No change of use, egress or occupancy. |
| M00802679 | 27 CLIFF STREET MANHATTAN | Alteration | Signed-off | 05/04/2023 | 09/21/2023 | Design CAMERON ENGINEERING Contractor CBG BUILDERS INC | Filing structural repair work in existing commercial space as per plan filed herewith. No change in use, egress, and occupancy. |
| M00285760 | 375 PEARL STREET MANHATTAN | Alteration | Signed-off | 01/23/2020 | 11/12/2020 | Design SEVERUD ASSOCIATES Owner SABEY DATA CENTERS Contractor AMERICON CONSTRUCTION INC. | Slab infill at existing cable pull shafts on the 15th floor through the 17th Floor s as per plans filed herewith. No change in use, egress o… |
| Name | Projects together | Most recent |
|---|---|---|
| Cameron Engineering | 4 | 05/24/2023 |
| Robert Derector Associates | 1 | 02/21/2020 |
| Severud Associates | 1 | 07/19/2021 |
| Thornton Tomasetti | 1 | 02/26/2021 |
| Name | Projects together | Most recent |
|---|---|---|
| CBG Builders | 2 | 05/24/2023 |
| Americon Construction | 1 | 07/19/2021 |
| F.S. Works | 1 | 05/24/2023 |
| P.H. Works | 1 | 05/24/2023 |
| Padilla Construction Service | 1 | 02/26/2021 |
| Tristate Air Conditioning | 1 | 02/21/2020 |
| Name | Projects together | Most recent |
|---|---|---|
| Sabey Data Centers | 1 | 07/19/2021 |
| Name | Projects together | Most recent |
|---|---|---|
| William Vitacco Associates | 4 | 05/24/2023 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M00465611 | 1 POLICE PLAZA MANHATTAN | Alteration | Permit Issued | 02/26/2021 | 11/21/2024 | Design THORNTON TOMASETTI Contractor PADILLA CONSTRUCTION SERVICES | Various repairs exterior repairs to building courtyard |
| M00800899 | 80 JOHN STREET MANHATTAN | Alteration | Signed-off | 05/24/2023 | 09/28/2023 | Design CAMERON ENGINEERING Contractor CBG BUILDERS INC | Modifications to existing Mechanical System as per plans filed herewith. No change in use, egress or occupancy. |
| M00800897 | 80 JOHN STREET MANHATTAN | Alteration | Signed-off | 05/24/2023 | 09/25/2023 | Design CAMERON ENGINEERING Contractor P.H. WORKS INC | Modifications to existing plumbing fixtures as per plans filed herewith. No change in use, egress or occupancy. |
| M00800900 | 80 JOHN STREET MANHATTAN | Alteration | Signed-off | 05/24/2023 | 09/25/2023 | Design CAMERON ENGINEERING Contractor F.S. WORKS INC | Modification to existing Sprinkler System as per plans filed herewith. No change of use, egress or occupancy. |
| M00802679 | 27 CLIFF STREET MANHATTAN | Alteration | Signed-off | 05/04/2023 | 09/21/2023 | Design CAMERON ENGINEERING Contractor CBG BUILDERS INC | Filing structural repair work in existing commercial space as per plan filed herewith. No change in use, egress, and occupancy. |
| M00285760 | 375 PEARL STREET MANHATTAN | Alteration | Signed-off | 01/23/2020 | 11/12/2020 | Design SEVERUD ASSOCIATES Owner SABEY DATA CENTERS Contractor AMERICON CONSTRUCTION INC. | Slab infill at existing cable pull shafts on the 15th floor through the 17th Floor s as per plans filed herewith. No change in use, egress o… |
| M00285881 | 375 PEARL STREET MANHATTAN | Alteration | Signed-off | 02/21/2020 | 09/10/2020 | Design ROBERT DERECTOR ASSOCIATES Contractor TRISTATE AIR CONDITIONING | Modification to existing HVAC system as per plans filed herewith. No change in use, egress or occupancy under this application |
| Building | Filings | Most Recent |
|---|---|---|
| 80 JOHN STREET ↗ | 3 | 05/24/2023 |
| 27 CLIFF STREET ↗ | 1 | 05/04/2023 |
| 375 PEARL STREET ↗ | 2 | 07/19/2021 |
| 1 POLICE PLAZA ↗ | 1 | 02/26/2021 |