1 project with open permitsBRONX · 4BROOKLYN · 2MANHATTAN · 1
3 buildings
7
Total Filings
7
Projects on File
3
Buildings Worked
1
Projects w/ Open Permits
Tenant
Primary Trade
Activity
Projects by first filing month7 projects all-time
0235Dec '19 · 4Jan '20 · 2Nov '23 · 12020202120222023
bars = month · line = 3-mo average
Portfolio status
Browse projects →
Open permit114%
Signed off686%
By project type
Alteration7
Most active buildings
All buildings →
349 EAST 149TH STREETBRONX · latest 10/18/2021
4 projects
44 COURT STREETBROOKLYN · latest 06/11/2020
2 projects
26 BLEECKER STREETMANHATTAN · 1 open · latest 03/19/2024
1 projects
Key relationships
Everyone →
Design firms
1 projects
1 projects
Contractors
Owners
4 projects
Filed under
Planned Parenthood of New York City6Planned Parenthood of New York City1
Identified by the contact ids of the people who file for the firm and by its email domain, not by matching names.
Most recent projects
All projects →
ProjectAddressTypeStatusFiledLatest permitOn the projectDescription
M00942060 ↗26 BLEECKER STREET
MANHATTAN
AlterationPermit Issued11/03/202303/19/2024
Design EOC-NY
HEREWITH FILE APPLICATION TO RESTORE FACADE AS PER PLANS
X00217861 ↗349 EAST 149TH STREET
BRONX
AlterationSigned-off12/02/201910/18/2021Sprinkler work for Planned Parenthood space. No change in use, egress or occupancy.
X00217723 ↗349 EAST 149TH STREET
BRONX
AlterationSigned-off12/02/201910/05/2021Mechanical work for Planned Parenthood space. No change in use, egress or occupancy.
X00217792 ↗349 EAST 149TH STREET
BRONX
AlterationSigned-off12/02/201904/30/2021Post Approval Amendment filed to submit revised drawings adding 3rd floor and increase job cost FROM: $28,996.96 to NEW: $104,000.13. No ch…
X00221979 ↗349 EAST 149TH STREET
BRONX
AlterationSigned-off12/04/201909/28/2020
Design SILMAN
Propose to perform structural work for acoustical operable partition support, new staircase opening. No change in use, egress or occupancy.
B00236738 ↗44 COURT STREET
BROOKLYN
AlterationSigned-off01/08/202006/11/2020PPNYC - Modifications to Sprinkler system and installation of Temporary Sprinkler loop as per plans filed herewith. No change in use, egres…
Counts cover all 7 projects (7 DOB NOW). Dated by first filing; BIS projects by first permit issuance.
Who this entity's projects were filed with. Top 25 per group by shared jobs.
NameProjects togetherMost recent
Loring Consulting Engineers507/26/2022
Eoc-NY111/03/2023
Silman104/14/2021
Who this entity's projects were filed with. Top 25 per group by shared jobs.
NameProjects togetherMost recent
Constructomics207/26/2022
Aqua Plumbing & Heating109/09/2020
Denair HVAC101/08/2020
Full Capacity Fire104/16/2021
Par Fire Protection101/08/2020
RK Best Construction111/03/2023
SKH Mechanical104/16/2021
Who this entity's projects were filed with. Top 25 per group by shared jobs.
NameProjects togetherMost recent
GFP Real Estate407/26/2022
7 DOB NOW projects, anchored the same way as Buildings Worked. Status is the project's permit state today: open = at least one permit currently issued. BIS projects show their raw permit status and are not counted as open.
All 7Open permit 1Signed off 6
7 projects
ProjectAddressTypeStatusFiledLatest permitOn the projectDescription
M00942060 ↗26 BLEECKER STREET
MANHATTAN
AlterationPermit Issued11/03/202303/19/2024
Design EOC-NY
HEREWITH FILE APPLICATION TO RESTORE FACADE AS PER PLANS
X00217861 ↗349 EAST 149TH STREET
BRONX
AlterationSigned-off12/02/201910/18/2021Sprinkler work for Planned Parenthood space. No change in use, egress or occupancy.
X00217723 ↗349 EAST 149TH STREET
BRONX
AlterationSigned-off12/02/201910/05/2021Mechanical work for Planned Parenthood space. No change in use, egress or occupancy.
X00217792 ↗349 EAST 149TH STREET
BRONX
AlterationSigned-off12/02/201904/30/2021Post Approval Amendment filed to submit revised drawings adding 3rd floor and increase job cost FROM: $28,996.96 to NEW: $104,000.13. No ch…
X00221979 ↗349 EAST 149TH STREET
BRONX
AlterationSigned-off12/04/201909/28/2020
Design SILMAN
Propose to perform structural work for acoustical operable partition support, new staircase opening. No change in use, egress or occupancy.
B00236738 ↗44 COURT STREET
BROOKLYN
AlterationSigned-off01/08/202006/11/2020PPNYC - Modifications to Sprinkler system and installation of Temporary Sprinkler loop as per plans filed herewith. No change in use, egres…
B00236119 ↗44 COURT STREET
BROOKLYN
AlterationSigned-off01/08/202005/12/2020
Contractor DENAIR HVAC INC
PPNY - Mechanical modifications as per plans filed herewith. No change in use egress or occupancy.
Click a row for this entity's own projects, plans and documents at that building.
BuildingFilingsMost Recent
26 BLEECKER STREET ↗111/03/2023
349 EAST 149TH STREET ↗407/26/2022
44 COURT STREET ↗201/08/2020
▾Documents — 115 on file (BIS + DOB NOW)
▸Plans & Drawings18
▸DOB NOWPlans/Sketch - Mechanical Systems7
09/02/2026B00236119-I1 · 44 COURT STREETRequest digital key ↗
Showing 1 of 7 on file for this type
▸DOB NOWPlans/Sketch - Sprinkler5
09/02/2026B00236738-I1 · 44 COURT STREETRequest digital key ↗
Showing 3 of 5 on file for this type
▸DOB NOWPlans/Sketch - Structural3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸DOB NOWPlans/Sketch - Plumbing2
▸DOB NOWPlans/Sketch1
▸Applications & Permits2
▸DOB NOWLPC Approval/Permit2
08/13/2026B00236119-I1 · 44 COURT STREETOpen ↗
08/13/2026M00942060-I1 · 26 BLEECKER STREETOpen ↗
▸Seals & Professional Certifications77
▸DOB NOWProgress Inspector Seal & Signature31
09/01/2026X00217723-P2 · 349 EAST 149TH STREETOpen ↗
09/01/2026X00217723-P2 · 349 EAST 149TH STREETOpen ↗
09/01/2026X00217723-P2 · 349 EAST 149TH STREETOpen ↗
Showing 3 of 31 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature29
09/01/2026X00217723-P2 · 349 EAST 149TH STREETOpen ↗
09/01/2026X00217723-P2 · 349 EAST 149TH STREETOpen ↗
09/01/2026X00217723-P2 · 349 EAST 149TH STREETOpen ↗
Showing 3 of 29 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature17
08/28/2026M00942060-I1 · 26 BLEECKER STREETOpen ↗
08/25/2026X00221979-P1 · 349 EAST 149TH STREETOpen ↗
08/25/2026X00221979-I1 · 349 EAST 149TH STREETOpen ↗
Showing 3 of 17 on file for this type
▸Environmental & Asbestos17
▸DOB NOWDEP ACP-5: Asbestos Assessment Report17
08/28/2026M00942060-I1 · 26 BLEECKER STREETOpen ↗
08/25/2026X00221979-I1 · 349 EAST 149TH STREETOpen ↗
08/25/2026X00217861-P3 · 349 EAST 149TH STREETOpen ↗
Showing 3 of 17 on file for this type
▸Approvals, Objections & Sign-offs1
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter1
08/13/2026M00942060-I1 · 26 BLEECKER STREETOpen ↗