| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M01401098 ↗ | 770 BROADWAY MANHATTAN | Alteration | Permit Issued | 07/28/2026 | 07/30/2026 | Design ROBERT DERECTOR ASSOCIATES Owner VORNADO REALTY TRUST Contractor L&K PARTNERS, INC | Mechanical work on part of the cellar and 1st floor. |
| M01401101 ↗ | 770 BROADWAY MANHATTAN | Alteration | Permit Issued | 07/20/2026 | 07/22/2026 | Design ROBERT DERECTOR ASSOCIATES Owner VORNADO REALTY TRUST Contractor MAC FELDER INC | Plumbing work on part of the sub-cellar, cellar and 1st floor. |
| M01405012 ↗ | 770 BROADWAY MANHATTAN | Alteration | Filed — no permit on record | 07/18/2026 | — | — | — |
| M01309270 ↗ | 770 BROADWAY MANHATTAN | Alteration | Permit Issued | 02/17/2026 | 05/15/2026 | Contractor L&K PARTNERS, INC | Minor mechanical work on part of 1st floor. |
| M01079367 ↗ | 770 BROADWAY MANHATTAN | Alteration | Signed-off | 08/09/2024 | 11/07/2024 | Design ROBERT DERECTOR ASSOCIATES Owner VORNADO REALTY TRUST Contractor MAC FELDER INC | Plumbing changes on part of cellar and 1st floor as indicated on drawings. |
| M01079357 ↗ | 770 BROADWAY MANHATTAN | Alteration | Permit Issued | 08/09/2024 | 08/27/2024 | Design ROBERT DERECTOR ASSOCIATES Owner VORNADO REALTY TRUST Contractor L&K PARTNERS, INC | Mechanical changes on part of 1st floor including commercial kitchen rangehood ventilation system as indicated on drawings. |
| Name | Projects together | Most recent |
|---|---|---|
| ROBERT DERECTOR ASSOCIATES | 15 | 07/28/2026 |
| SHAABAN ENGINEERING, LLC | 5 | 07/21/2022 |
| GREENBERG FARROW | 2 | 04/22/2025 |
| GRUSKIN ARCHITECTURE + DESIGN PC | 2 | 04/03/2024 |
| GILSANZ MURRAY STEFICEK LLP | 1 | 07/25/2022 |
| Name | Projects together | Most recent |
|---|---|---|
| L&K PARTNERS, INC | 12 | 07/28/2026 |
| NATIONAL MAINTENANCE, INC | 5 | 07/21/2022 |
| MAC FELDER INC | 4 | 07/20/2026 |
| SIRINA FIRE PROT CORP | 4 | 12/12/2024 |
| GEORGE BRESLAW PLBNG LLC | 2 | 02/16/2024 |
| Name | Projects together | Most recent |
|---|---|---|
| VORNADO REALTY TRUST | 22 | 07/28/2026 |
| Name | Projects together | Most recent |
|---|---|---|
| ARCHETYPE CONSULTANTS, INC. | 19 | 07/28/2026 |
| KAZAM CONSULTANTS, INC. | 3 | 07/21/2022 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| M01401098 ↗ | 770 BROADWAY MANHATTAN | Alteration | Permit Issued | 07/28/2026 | 07/30/2026 | Design ROBERT DERECTOR ASSOCIATES Owner VORNADO REALTY TRUST Contractor L&K PARTNERS, INC | Mechanical work on part of the cellar and 1st floor. |
| M01401101 ↗ | 770 BROADWAY MANHATTAN | Alteration | Permit Issued | 07/20/2026 | 07/22/2026 | Design ROBERT DERECTOR ASSOCIATES Owner VORNADO REALTY TRUST Contractor MAC FELDER INC | Plumbing work on part of the sub-cellar, cellar and 1st floor. |
| M01405012 ↗ | 770 BROADWAY MANHATTAN | Alteration | Filed — no permit on record | 07/18/2026 | — | — | — |
| M01309270 ↗ | 770 BROADWAY MANHATTAN | Alteration | Permit Issued | 02/17/2026 | 05/15/2026 | Contractor L&K PARTNERS, INC | Minor mechanical work on part of 1st floor. |
| M01079367 ↗ | 770 BROADWAY MANHATTAN | Alteration | Signed-off | 08/09/2024 | 11/07/2024 | Design ROBERT DERECTOR ASSOCIATES Owner VORNADO REALTY TRUST Contractor MAC FELDER INC | Plumbing changes on part of cellar and 1st floor as indicated on drawings. |
| M01079357 ↗ | 770 BROADWAY MANHATTAN | Alteration | Permit Issued | 08/09/2024 | 08/27/2024 | Design ROBERT DERECTOR ASSOCIATES Owner VORNADO REALTY TRUST Contractor L&K PARTNERS, INC | Mechanical changes on part of 1st floor including commercial kitchen rangehood ventilation system as indicated on drawings. |
| M01079371 ↗ | 770 BROADWAY MANHATTAN | Alteration | Permit Issued | 08/09/2024 | 08/19/2024 | Design ROBERT DERECTOR ASSOCIATES Owner VORNADO REALTY TRUST Contractor SIRINA FIRE PROT CORP | Sprinkler changes on part of cellar and 1st floor as indicated on drawings. |
| M00965286 ↗ | 770 BROADWAY MANHATTAN | Alteration | Signed-off | 06/28/2024 | 07/17/2024 | Design ROBERT DERECTOR ASSOCIATES Owner VORNADO REALTY TRUST Contractor SIRINA FIRE PROT CORP | sprinkler (wet and dry) work to establish new customer and employee bathrooms on cellar and 1st floor; plus relocation of dry sprinkler sys… |
| M00965265 ↗ | 770 BROADWAY MANHATTAN | Alteration | Signed-off | 07/01/2024 | 07/11/2024 | Design GREENBERG FARROW Owner VORNADO REALTY TRUST Contractor L&K PARTNERS, INC | Architectural work to establish new customer and employee bathrooms on cellar and 1st floor; plus relocation of dry sprinkler system piping … |
| M00965274 ↗ | 770 BROADWAY MANHATTAN | Alteration | Signed-off | 07/01/2024 | 07/11/2024 | Design ROBERT DERECTOR ASSOCIATES Contractor L&K PARTNERS, INC | Mechanical work to establish new customer and employee bathrooms on cellar and 1st floor; plus relocation of dry sprinkler system piping for… |
| M00965280 ↗ | 770 BROADWAY MANHATTAN | Alteration | Signed-off | 06/28/2024 | 07/10/2024 | Design ROBERT DERECTOR ASSOCIATES Owner VORNADO REALTY TRUST Contractor MAC FELDER INC | Plumbing work to establish new customer and employee bathrooms on sub-cellar, cellar and 1st floor; plus relocation of dry sprinkler system … |
| M00964502 ↗ | 770 BROADWAY MANHATTAN | Alteration | Signed-off | 02/29/2024 | 03/19/2024 | Owner VORNADO REALTY TRUST Contractor L&K PARTNERS, INC | Install shaft wall in existing freight elevator shaft from cellar to roof above 15th floor to create new utility shaft. |
| M00838410 ↗ | 770 BROADWAY MANHATTAN | Alteration | Signed-off | 03/23/2023 | 12/07/2023 | Design ROBERT DERECTOR ASSOCIATES Owner VORNADO REALTY TRUST Contractor L&K PARTNERS, INC | Mechanical work on part of 1st floor for accessory retail dining space. |
| M00729206 ↗ | 770 BROADWAY MANHATTAN | Alteration | Signed-off | 09/30/2022 | 08/07/2023 | Design ROBERT DERECTOR ASSOCIATES Owner VORNADO REALTY TRUST Contractor SIRINA FIRE PROT CORP | Sprinkler and standpipe work on parts of cellar, 1st floor and mezzanine for retail tenant per drawings. |
| M00701218 ↗ | 770 BROADWAY MANHATTAN | Alteration | Signed-off | 07/25/2022 | 07/14/2023 | Design GILSANZ MURRAY STEFICEK LLP Owner VORNADO REALTY TRUST Contractor L&K PARTNERS, INC | Structural modifications on subcellar through 3rd floor to accommodate future tenant work (to be filed separately). |
| M00843561 ↗ | 770 BROADWAY MANHATTAN | Alteration | Signed-off | 03/23/2023 | 04/20/2023 | Design ROBERT DERECTOR ASSOCIATES Owner VORNADO REALTY TRUST Contractor SIRINA FIRE PROT CORP | Sprinkler work on part of 1st floor for accessory retail dining space. |
| M00838421 ↗ | 770 BROADWAY MANHATTAN | Alteration | Signed-off | 03/23/2023 | 04/05/2023 | Design ROBERT DERECTOR ASSOCIATES Owner VORNADO REALTY TRUST Contractor GEORGE BRESLAW PLBNG LLC | Plumbing work on part of 1st floor for accessory retail dining space. |
| M00729093 ↗ | 770 BROADWAY MANHATTAN | Alteration | Signed-off | 09/30/2022 | 02/03/2023 | Design ROBERT DERECTOR ASSOCIATES Owner VORNADO REALTY TRUST Contractor GEORGE BRESLAW PLBNG LLC | Plumbing work on parts of subcellar, cellar, 1st floor and mezzanine for retail tenant per drawings. |
| M00729086 ↗ | 770 BROADWAY MANHATTAN | Alteration | Signed-off | 10/04/2022 | 10/11/2022 | Design ROBERT DERECTOR ASSOCIATES Owner VORNADO REALTY TRUST Contractor L&K PARTNERS, INC | Mechanical work on parts of cellar, 1st floor/mezzanine for retail tenant including rangehood cooking exhaust system per drawings. Mechanica… |
| M00729367 ↗ | 770 BROADWAY MANHATTAN | Alteration | Signed-off | 10/05/2022 | 10/11/2022 | Design GREENBERG FARROW Owner VORNADO REALTY TRUST Contractor L&K PARTNERS, INC | Construction work on parts of cellar, 1st floor and mezzanine for retail tenant per drawings. |
| M00743956 ↗ | 770 BROADWAY MANHATTAN | Alteration | Signed-off | 08/19/2022 | 08/22/2022 | Design ROBERT DERECTOR ASSOCIATES Owner VORNADO REALTY TRUST Contractor L&K PARTNERS, INC | Mechanical work to remove an replace tenant cooling tower and install new standby generator at roof. |
| M00738077 ↗ | 770 BROADWAY MANHATTAN | Alteration | Signed-off | 07/21/2022 | 07/23/2022 | Design SHAABAN ENGINEERING, LLC Contractor NATIONAL MAINTENANCE, INC | Erect illuminated accessory business wall sign; copy reading Wegmans |
| M00738091 ↗ | 770 BROADWAY MANHATTAN | Alteration | Signed-off | 07/21/2022 | 07/22/2022 | Design SHAABAN ENGINEERING, LLC Owner VORNADO REALTY TRUST Contractor NATIONAL MAINTENANCE, INC Filer KAZAM CONSULTANTS, INC. | Erect illuminated accessory business wall sign; copy reading Wegmans |
| M00738100 ↗ | 770 BROADWAY MANHATTAN | Alteration | Signed-off | 07/21/2022 | 07/22/2022 | Design SHAABAN ENGINEERING, LLC Contractor NATIONAL MAINTENANCE, INC | Erect illuminated accessory business wall sign; copy reading Wegmans |
| M00738107 ↗ | 770 BROADWAY MANHATTAN | Alteration | Signed-off | 07/21/2022 | 07/22/2022 | Design SHAABAN ENGINEERING, LLC Owner VORNADO REALTY TRUST Contractor NATIONAL MAINTENANCE, INC Filer KAZAM CONSULTANTS, INC. | Erect illuminated accessory business wall sign; copy reading Wegmans |
| M00738112 ↗ | 770 BROADWAY MANHATTAN | Alteration | Signed-off | 07/21/2022 | 07/22/2022 | Design SHAABAN ENGINEERING, LLC Owner VORNADO REALTY TRUST Contractor NATIONAL MAINTENANCE, INC Filer KAZAM CONSULTANTS, INC. | Erect illuminated accessory business wall sign; copy reading Wegmans |
| M00635844 ↗ | 770 BROADWAY MANHATTAN | Alteration | Signed-off | 05/04/2022 | 06/13/2022 | Owner VORNADO REALTY TRUST Contractor L&K PARTNERS, INC | Modifications to part of the 1st and 2nd floor facades as indicated on drawings, including new curtain wall system, new glazing, new entry d… |
| Building | Filings | Most Recent |
|---|---|---|
| 770 BROADWAY ↗ | 27 | 07/28/2026 |