Install combined sprinkler/standpipe system as per plans filed. No change to use, egress oroccupancy. Filed in conjunction with NB# B00640761.
On file for this project
14 documents
Demolition and infill of 8 lot line windows. No change to use, egress or occupancy.
On file for this project
14 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents
Latest 3 of 4 filings on this floor.
RoofKotobuki, Cooper UnionUnder Construction11p · 5 filings · 20 docs
ArchitectureDMMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Structural
REVISED PLUMBING RISER DIAGRAM BASED ON AS-BUILT CONDITIONS
On file for this project
35 documents · 4 drawing sheets
Plumbing / Sprinkler scope related to the retail store whitebox interior renovation, no change in use, egress or occupancy.
On file for this project
11 documents · 3 drawing sheets
Structural application filed for structural framing, floor infill, column work, joist repair, removal and masonry repairs. No change in use, egress or occupancy..
On file for this project
20 documents · 2 drawing sheets
Latest 3 of 5 filings on this floor.
Floor 2Kotobuki, Cooper UnionUnder Construction23p · 7 filings · 20 docs
ArchitectureDMEquipmentFire ProtectionGeneralPlumbingStructural
Issued Permit Scope
General Construction · Plumbing · Sprinklers · Structural · Supported Scaffold
REVISED PLUMBING RISER DIAGRAM BASED ON AS-BUILT CONDITIONS
On file for this project
35 documents · 6 drawing sheets
Plumbing / Sprinkler scope related to the retail store whitebox interior renovation, no change in use, egress or occupancy.
On file for this project
11 documents · 10 drawing sheets
SEQUENCE, MEANS AND METHODS FOR THE PROPOSED PARTIAL DEMOLITION OF THE 2ND FLOOR SLAB OF THE 15 STORY BUILDING
On file for this project
4 documents · 1 drawing sheet
Latest 3 of 7 filings on this floor.
Floor 1Kotobuki, Wonder +1Under Construction22p · 7 filings · 20 docs
ArchitectureDMElectricalEquipmentFire ProtectionGeneralPlumbingStructural
Issued Permit Scope
General Construction · Plumbing · Sign · Sprinklers · Structural · Supported Scaffold
REVISED PLUMBING RISER DIAGRAM BASED ON AS-BUILT CONDITIONS
On file for this project
35 documents · 1 drawing sheet
Plumbing / Sprinkler scope related to the retail store whitebox interior renovation, no change in use, egress or occupancy.
On file for this project
11 documents · 6 drawing sheets
STRUCTURAL APPLICATION FILED IN CONJUNCTION WITH TENANT FIT OUT
On file for this project
38 documents · 10 drawing sheets
Latest 3 of 7 filings on this floor.
CellarKotobuki, Wonder +1Under Construction24p · 6 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
REVISED PLUMBING RISER DIAGRAM BASED ON AS-BUILT CONDITIONS
On file for this project
35 documents · 1 drawing sheet
Plumbing / Sprinkler scope related to the retail store whitebox interior renovation, no change in use, egress or occupancy.
On file for this project
11 documents · 8 drawing sheets
STRUCTURAL APPLICATION FILED IN CONJUNCTION WITH TENANT FIT OUT
On file for this project
38 documents · 9 drawing sheets
Latest 3 of 6 filings on this floor.
Site & exteriorWonder3 filings · 8 docs
ArchitectureCivilElectricalEquipmentGeneralMechanicalStructural
Issued Permit Scope
Construction Fence · Sidewalk Shed · Supported Scaffold
Proposed construction fence. No change to use egress or occupancy.
On file for this project
2 documents · 2 drawing sheets
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. LIVE LOAD 300PSF.
On file for this project
4 documents · 6 drawing sheets
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents · 2 drawing sheets
Filed — no permit issuedCellar and two-story modifications1 filing · 10 docs
ArchitectureCivilDMGeneralMechanicalStructural
Filed for modifications to demising and occupant loads of existing cellar and two-story prior to 1968 code class three non-fireproof use group 6 retail bakeries and eating and drinking establishments also filed for interior renovations.
On file for this project
10 documents · 12 drawing sheets