| Owner | Filings | Most Recent |
|---|---|---|
| Northwell Health Lenox Hill Hospita | 94 | 10/15/2026 |
| Hospital | 1 | 03/22/2026 |
| LIC | 1 | 03/22/2026 |
| Director | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Jin Lee, RA | 1 | 10/14/2026 |
| Lizardos Engineering | 9 | 06/25/2026 |
| Robert Dructor | 1 | 04/27/2026 |
| Mascioni & Behrmann, Architecture | 1 | 04/20/2026 |
| Gilsanz Murray Steficek | 9 | 04/17/2026 |
| Jack L. Gordon Architects | 2 | 10/02/2025 |
| Jaros Baum & Bolles | 8 | 09/26/2025 |
| Ewingcole | 1 | 11/18/2024 |
| FL&M Engineering Design & Inspection | 1 | 06/15/2022 |
| Pamela A. Smith | 3 | 01/24/2022 |
| H. F. Lenz Company | 4 | 12/22/2021 |
| Patuxent Engineering | 3 | 09/15/2021 |
| Tohfaz Uddin PE | 2 | 07/15/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| Upright Expediters | 58 | 03/21/2026 |
| Riggining Consultants | 1 | 03/21/2026 |
| Patuxent Engineering | 8 | 03/21/2026 |
| Direct Access Expediting | 8 | 03/21/2026 |
| A1 Expediting Service | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Central Consulting & Cont | General Contractor | 24 | 07/08/2026 |
| Capital Contracting P&H | Plumbing | 9 | 07/08/2026 |
| Manhattan D Enterprises | Scaffold | 7 | 07/08/2026 |
| Empire General Contracting | General Contractor | 6 | 07/08/2026 |
| Urban Intelligence | Scaffold | 6 | 08/20/2026 |
| Americon Construction | General Contractor | 6 | 04/09/2026 |
| Hatzel and Buehler | Electrical | 5 | 03/22/2026 |
| L.F. Driscoll Company | General Contractor | 4 | 07/08/2026 |
| York Scaffold Equipment | Scaffold | 4 | 03/21/2026 |
| Brosna Construction | General Contractor | 4 | 07/08/2026 |
| Exterior Wall & Building | Scaffold | 3 | 07/08/2026 |
| Alliance Plumbing | Plumbing | 3 | 07/08/2026 |
| Diane Electric | Electrical | 2 | 03/22/2026 |
| Bigman Brothers | Electrical | 2 | 03/21/2026 |
| Dooley Electric Co | Electrical | 2 | 03/21/2026 |
| Aljer Plumbing & Heating | Plumbing | 2 | 07/08/2026 |
| Diane Electric | Electrical | 2 | 03/21/2026 |
| Sirina Fire Protection | Fire Protection | 1 | 07/08/2026 |
| Hatzel and Buehler | Electrical | 1 | 03/21/2026 |
| Commercial Electric Cont | Electrical | 1 | 03/21/2026 |
| Nee Electrical | Electrical | 1 | 03/22/2026 |
| R. Donovan & Son Electric | Electrical | 1 | 03/21/2026 |
| Five Star Electric | Electrical | 1 | 03/21/2026 |
| Aljer Plumbing & Heating | Fire Protection | 1 | 07/08/2026 |
| Archer Consultants Group | Fire Protection | 1 | 06/28/2026 |
| Cardoza Plumbing | Plumbing | 1 | 07/08/2026 |
| NYC Fire Sprinkler | Fire Protection | 1 | 07/08/2026 |
| Par Plumbing Co | Plumbing | 1 | 07/08/2026 |
| 5 J'S Electl Conts | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CC@A Engineering | 1854 | 26 | 06/25/2026 |
| Gilsanz Murray Steficek | 240 | 7 | 10/28/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sidewalk Shed | Signed-off | Urban Intelligence | 08/18/2026 |
| DOB NOW | Sprinklers | Signed-off | NYC Fire Sprinkler | 06/17/2026 |
| DOB NOW | Plumbing | Signed-off | Alliance Plumbing | 06/15/2026 |
| DOB NOW | Sidewalk Shed | Signed-off | Urban Intelligence | 05/28/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | L.F. Driscoll Company | 05/14/2026 |
| DOB NOW | Structural | Signed-off | L.F. Driscoll Company | 05/12/2026 |
| DOB NOW | General Construction | Signed-off | L.F. Driscoll Company | 05/11/2026 |
| DOB NOW | General Construction | Permit Issued | L.F. Driscoll Company | 05/04/2026 |
| DOB NOW | Mechanical Systems | Signed-off | Americon Construction | 03/24/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Empire General Contracting | 01/14/2026 |
| DOB NOW | Sidewalk Shed | Signed-off | Exterior Wall & Building | 12/30/2025 |
| DOB NOW | Plumbing | Permit Issued | Cardoza Plumbing Wmbe | 12/10/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Empire General Contracting | 11/05/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Americon Construction | 04/22/2025 |
| DOB NOW | Sprinklers | Signed-off | Archer Consultants Group | 04/22/2025 |
| DOB NOW | Plumbing | Signed-off | Capital Contracting P&H | 04/21/2025 |
| DOB NOW | Structural | Signed-off | Americon Construction | 04/14/2025 |
| DOB NOW | General Construction | Signed-off | Americon Construction | 04/14/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | Empire General Contracting | 02/06/2025 |
| DOB NOW | General Construction | Signed-off | Empire General Contracting | 02/06/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | Exterior Wall & Building | 12/27/2024 |
| DOB NOW | Structural | Signed-off | Central Consulting & Cont | 11/01/2024 |
| DOB NOW | Plumbing | Permit Issued | Cardoza Plumbing Wmbe | 10/24/2024 |
| DOB NOW | Structural | Signed-off | Empire General Contracting | 06/10/2024 |
| DOB NOW | Suspended Scaffold | Signed-off | Structural Preservation System | 02/16/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | Urban Intelligence | 01/05/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | Urban Intelligence | 05/19/2023 |
| DOB NOW | Structural | Signed-off | Central Consulting & Cont | 03/20/2023 |
| DOB NOW | General Construction | Signed-off | Brosna Construction | 11/09/2022 |
| DOB NOW | Plumbing | Signed-off | Capital Contracting P&H | 11/09/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | Manhattan D Enterprises | 06/16/2022 |
| DOB NOW | Plumbing | Permit Issued | Cardoza Plumbing | 04/15/2022 |
| DOB NOW | Mechanical Systems | Signed-off | Brosna Construction | 03/22/2022 |
| DOB NOW | Structural | Signed-off | Central Consulting & Cont | 03/18/2022 |
| DOB NOW | General Construction | Signed-off | Central Consulting & Cont | 03/18/2022 |
| DOB NOW | General Construction | Signed-off | Brosna Construction | 01/26/2022 |
| DOB NOW | General Construction | Signed-off | Central Consulting & Cont | 12/27/2021 |
| DOB NOW | Structural | Signed-off | Central Consulting & Cont | 12/23/2021 |
| DOB NOW | General Construction | Signed-off | Central Consulting & Cont | 12/23/2021 |
| DOB NOW | Plumbing | Signed-off | Capital Contracting P&H | 12/09/2021 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 10/14/2026 | — | — | Air Conditioning Systems, Heating and Air Conditioning Systems | Cooling Mitsubishi Electric PUY-AK12N 12,000 BTU ×1 PUY-AK18NL 18,000 BTU · Condensing Unit ×1 PUY-AK36N 36,000 BTU · Condensing Unit ×1 Heat / Cool Daikin DPSC07B 7 tons · Rooftop Unit ×1 |
| 06/25/2026 | Signed-off | Americon Construction | Air Conditioning Systems | Cooling Liebert Minimate MT060HE1A00XTS 59,000 BTU · Crac Unit ×1 PFD067A-CAL1 59,000 BTU · Condensing Unit ×1 Magic-Aire HHA16 47,500 BTU · Ahu ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/14/2026 | — | — | Sprinkler System |
| 11/05/2025 | Signed-off | Archer Consultants Group | 80 heads |
| 04/08/2025 | Signed-off | NYC Fire Sprinkler | 12 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/14/2026 | — | — | Medical Gas, Water/Sanitary |
| 11/05/2025 | Signed-off | Capital Contracting P&H | Medical Gas, Water/Sanitary |
| 04/08/2025 | Signed-off | Cardoza Plumbing | Water/Sanitary |
| 12/22/2021 | Signed-off | Capital Contracting P&H | Medical Gas |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/07/2026 | Permit Issued | Hatzel and Buehler | General Wiring |
| 02/04/2026 | Permit Issued | Hatzel and Buehler | General Wiring |
| 04/04/2025 | Complete | Hatzel and Buehler | General Wiring |
| 03/12/2025 | Permit Issued | NJS Electrical Services | General Wiring |
| 08/27/2024 | Complete | Premier Electric | General Wiring |
| 10/12/2023 | Permit Issued | Commercial Electric Cont | General Wiring, Lighting |
| 08/21/2023 | Complete | Diane Electric | General Wiring |
| 08/11/2023 | Complete | Hatzel and Buehler | General Wiring |
| 07/19/2022 | Permit Issued | 5 J'S Electl Conts | — |
| 07/18/2022 | Complete | Hatzel and Buehler | — |
| 08/19/2021 | Permit Issued | NJS Electrical Services | General Wiring |
| 11/30/2020 | Complete | 5 J'S Electl Conts | — |
| 07/13/2020 | Permit Issued | Diane Electric | General Wiring |
| 10/16/2019 | Complete | Diane Electric | General Wiring |
| 08/27/2019 | Complete | Hatzel and Buehler | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/14/2026 | — | — | Steel |
| 04/17/2026 | Signed-off | L.F. Driscoll Company | Steel |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/21/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/17/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/26/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/25/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/19/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/17/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 04/01/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 03/26/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 10/23/2025 | Certified Medical Gas - MG - PL - Finish | Certified | View ↗ |
| 10/23/2025 | Certified Medical Gas - MG - PL - Roughing | Certified | View ↗ |
| 10/23/2025 | Certified Medical Gas - MG - PL - Test | Certified | View ↗ |
| 10/23/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/01/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/01/2022 | Certified Medical Gas - MG - PL - Finish | Certified | View ↗ |
| 04/01/2022 | Certified Medical Gas - MG - PL - Test | Certified | View ↗ |
| 04/01/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 04/01/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/10/2022 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 02/02/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 12/10/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/14/2026 | Lighting controls | — | energy_progress |
| 10/14/2026 | Interior lighting power | — | energy_progress |
| 10/14/2026 | Maintenance information | — | energy_progress |
| 07/08/2026 | Ventilation and air distribution system | CHAROULIS CHARALAMBOUS | energy_progress |
| 07/08/2026 | HVAC-R and service water heating system controls | CHAROULIS CHARALAMBOUS | energy_progress |
| 07/08/2026 | Duct leakage testing, insulation and design | CHAROULIS CHARALAMBOUS | energy_progress |
| 07/08/2026 | HVAC-R and service water heating equipment | CHAROULIS CHARALAMBOUS | energy_progress |
| 07/08/2026 | HVAC-R and service water piping design and insulation | CHAROULIS CHARALAMBOUS | energy_progress |
| 07/08/2026 | Energy Code Compliance Inspections | CHAROULIS CHARALAMBOUS | progress |
| 07/08/2026 | Heating Systems | CHAROULIS CHARALAMBOUS | special |
| 07/08/2026 | Mechanical Systems | CHAROULIS CHARALAMBOUS | special |
| 07/08/2026 | Final | CHAROULIS CHARALAMBOUS | progress |
| 07/06/2026 | Energy Code Compliance Inspections | — | progress |
| 07/06/2026 | Final | — | progress |
| 07/06/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 07/06/2026 | Fire-Resistance Rated Construction | — | progress |
| 06/24/2026 | Energy Code Compliance Inspections | CHAROULIS CHARALAMBOUS | progress |
| 06/24/2026 | HVAC-R and service water heating equipment | CHAROULIS CHARALAMBOUS | energy_progress |
| 06/24/2026 | HVAC-R and service water piping design and insulation | CHAROULIS CHARALAMBOUS | energy_progress |
| 06/24/2026 | Duct leakage testing, insulation and design | CHAROULIS CHARALAMBOUS | energy_progress |
| 06/24/2026 | Final | CHAROULIS CHARALAMBOUS | progress |
| 06/24/2026 | Mechanical Systems | CHAROULIS CHARALAMBOUS | special |
| 06/24/2026 | Heating Systems | CHAROULIS CHARALAMBOUS | special |
| 06/24/2026 | HVAC-R and service water heating system controls | CHAROULIS CHARALAMBOUS | energy_progress |
| 06/24/2026 | Ventilation and air distribution system | CHAROULIS CHARALAMBOUS | energy_progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| NH Lenox Hill Hospital Campus | Medical / Healthcare | Sub-basement, Floors 1–9, Roof | Project M01390346 Project M01379826 Project M01379825 Project M01379851 Project M01280595 Project M01059515 Project M01003830 Project M00757421 Project M00628021 Project M00630140 Project M00591860 Project M00463948 |
| Northwell Health | Medical / Healthcare | Floors 2–5, 7–9, 11, 12, Roof | Project M01082893 Project M01172986 Project M01172940 Project M01173835 Project M01173842 Project M01082851 Project M01064700 Project M01121736 Project M00836076 Project M00627963 Project M00502157 Project M00502207 |