| Owner | Filings | Most Recent |
|---|---|---|
| HITE CONSTRUCTION INC. | 5 | 03/22/2026 |
| 1070 PARK AVENUE | 128 | 03/22/2026 |
| SKYLINE SCAFFOLDING GROUP | 1 | 03/22/2026 |
| EDRAS GROUP | 1 | 03/22/2026 |
| 1070 PARK AVE CORP INSIGN | 1 | 03/22/2026 |
| INSIGNIA RESIDENTIAL GROU | 1 | 03/22/2026 |
| KREISEL COMPANY | 1 | 03/22/2026 |
| YATES GROUP | 2 | 03/22/2026 |
| 50 RIVERSIDE TENANTS | 1 | 03/22/2026 |
| KINGS GROUP NY | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| WYS DESIGN PARTNERSHIP ARCHITECTS | 2 | 07/15/2026 |
| OLGA BAKIC ARCHITECT | 2 | 06/12/2026 |
| ANDREW KLEIN | 3 | 05/22/2026 |
| JOSEPH PELL LOMBARDI, ARCHITECT | 8 | 05/21/2026 |
| A2 ARCHITECT, PC | 5 | 02/24/2026 |
| PIER FINE ASSOCIATES | 4 | 02/17/2026 |
| MOORE ASSOCIATES, LLC | 2 | 11/19/2025 |
| CHRISTIAN M. RICCI ARCHITECTURE + D | 2 | 03/31/2025 |
| FL&M ENGINEERING DESIGN &INSPECTION | 1 | 02/07/2025 |
| SA-DA ARCHITECTURE | 5 | 02/05/2025 |
| R.J. MCGEE ENGINEERING, PLLC | 2 | 06/27/2024 |
| ANTHONY MONTALTO, ARCHITECT | 6 | 11/28/2023 |
| ROBERT SILMAN ASSOC STRUCT ENG DPC | 2 | 07/13/2023 |
| TRI-POWER ENGINEERING, LLC | 5 | 07/11/2023 |
| ENGINEERING PROFESSIONAL SERVICE P. | 2 | 03/13/2023 |
| WILLIAM F. RYAN, JR. P.E. PC | 1 | 11/02/2022 |
| GRASSO-MENZIUSO ARCHITECTS | 1 | 10/26/2022 |
| URBAN INTEGRATIONS | 1 | 10/10/2022 |
| ANDREW FETHES ARCHITECT | 4 | 07/26/2022 |
| GESTURE INK ARCHITECTURE | 2 | 12/13/2021 |
| PVE ENGINEERING | 1 | 09/16/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| CLARKE CONSTRUCTION CONSULTANTS | 8 | 03/21/2026 |
| J A EXPEDITING | 10 | 03/21/2026 |
| STITCHT | 5 | 03/21/2026 |
| AGOUTI CONSTRUCTION CONSULTING | 2 | 03/21/2026 |
| J CALLAHAN CONSULTING | 18 | 03/21/2026 |
| JM ZONING, LLC. | 16 | 03/21/2026 |
| SKYLINE ACCESS | 1 | 03/21/2026 |
| ARINNITY NYC | 2 | 03/21/2026 |
| S M EXPEDITING | 4 | 03/21/2026 |
| NORTHEAST EXPEDITING | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| S. DONADIC INC | General Contractor | 11 | 07/08/2026 |
| SPRING SCAFFOLDING LLC | General Contractor | 7 | 07/08/2026 |
| SKYLINE RESTORATION INC | General Contractor | 6 | 07/08/2026 |
| FIRST STANDARD CONSTR INC | General Contractor | 6 | 03/21/2026 |
| HUDSON PLMBING & MCH, LLC | Plumbing | 3 | 07/08/2026 |
| HITE CONSTRUCTION INC | General Contractor | 3 | 07/08/2026 |
| CEPRINE CONSTRUCTION INC | General Contractor | 3 | 03/21/2026 |
| TMG CONSTRUCTION CORP | General Contractor | 2 | 08/12/2026 |
| ALCA RENOVATIONS INC | General Contractor | 2 | 07/01/2026 |
| ELEZI RENOVATIONS INC | General Contractor | 2 | 03/21/2026 |
| RENOVATION-PLUS CONSTRUC | General Contractor | 2 | 03/21/2026 |
| FRED SMITH P&H CO INC | Plumbing | 2 | 07/08/2026 |
| F.S. SITE CORP | Plumbing | 2 | 07/08/2026 |
| HYDROKINETIC PLBG & HTG I | Plumbing | 2 | 07/08/2026 |
| PRACTICAL PLBG & HTG INC | Plumbing | 2 | 07/08/2026 |
| RITE WAY HEATING CORP | Plumbing | 2 | 07/08/2026 |
| FRED SMITH PLBG & HTG CO. | Fire Protection | 1 | 07/08/2026 |
| BMB BUILDING CONSULTING I | Electrical | 1 | 03/21/2026 |
| KANHAI, ONEIL | Electrical | 1 | 03/21/2026 |
| C. MIZZI CONSTRUCTION COR | General Contractor | 1 | 07/08/2026 |
| G & L PLUMBING CO, INC | Plumbing | 1 | 07/08/2026 |
| JTE ELECTRICAL SERVICES | Electrical | 1 | 03/22/2026 |
| GALLERY RESTORATION LTD | General Contractor | 1 | 07/08/2026 |
| GURRI INSTALLATION INC | General Contractor | 1 | 08/13/2026 |
| ESSEX ELECTRIC INC | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| INM ARCHITECT, P.C. | 3351 | 2 | 07/15/2026 |
| WYS DESIGN, LLC | 8257 | 1 | 07/15/2026 |
| IVA FILIPOVIC ARCHITECT | 3142 | 1 | 06/12/2026 |
| OUTSOURCE SPECIAL INSPECT | 2827 | 3 | 05/22/2026 |
| A2 ARCHITECT, PC | 2504 | 5 | 02/24/2026 |
| ALAN MARGOLIN & ASSOC | 423 | 2 | 02/17/2026 |
| PIER, FINE ASSOCIATES | 1069 | 2 | 02/17/2026 |
| O'ROURKE ENGINEERING, LLC | 5873 | 2 | 11/19/2025 |
| MOORE ENG. OF NY, DPC | 9134 | 2 | 11/19/2025 |
| H. A. BADER CONSULTANTS | 2332 | 1 | 03/31/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | AAA TOTAL PLUMBING, INC | 09/08/2026 |
| DOB NOW | Plumbing | Permit Issued | F1 MECHANICAL INC | 08/12/2026 |
| DOB NOW | General Construction | Permit Issued | GURRI INSTALLATION INC | 08/12/2026 |
| DOB NOW | General Construction | Permit Issued | TMG CONSTRUCTION CORP | 08/11/2026 |
| DOB NOW | General Construction | Permit Issued | MAC INTERIOR CONSTRUCTION | 08/10/2026 |
| DOB NOW | General Construction | Permit Issued | RAFFERTY BROTHERS INC | 08/03/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | ALCA RENOVATIONS INC | 06/29/2026 |
| DOB NOW | General Construction | Permit Issued | PROLINE RESTORATION SVC | 04/10/2026 |
| DOB NOW | Plumbing | Permit Issued | ALAN J BRUTOSKY PLBR CONT | 12/05/2025 |
| DOB NOW | Plumbing | Permit Issued | ALAN J BRUTOSKY PLBR CONT | 12/01/2025 |
| DOB NOW | General Construction | Permit Issued | TMG CONSTRUCTION CORP | 11/06/2025 |
| DOB NOW | Plumbing | Signed-off | HUDSON PLMBING & MCH, LLC | 10/08/2025 |
| DOB NOW | General Construction | Permit Issued | ALCA RENOVATIONS INC | 10/07/2025 |
| DOB NOW | Plumbing | Signed-off | PRACTICAL PLBG & HTG INC | 07/21/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | SKYLINE RESTORATION INC | 07/10/2025 |
| DOB NOW | Plumbing | Signed-off | LS PLUMBING CORP | 06/27/2025 |
| DOB NOW | Plumbing | Signed-off | SUPER PLUMBERS CORP | 05/16/2025 |
| DOB NOW | General Construction | Signed-off | INTEGKRAL DESIGN CONSTR | 05/14/2025 |
| DOB NOW | General Construction | Signed-off | LOGIC CONSTRUCTION CORP | 03/14/2025 |
| DOB NOW | Plumbing | Signed-off | HYDROKINETIC PLBG & HTG I | 03/13/2025 |
| DOB NOW | General Construction | Permit Issued | SKYLINE RESTORATION INC | 02/26/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | SKYLINE RESTORATION INC | 02/24/2025 |
| DOB NOW | General Construction | Permit Issued | SKYLINE RESTORATION INC | 02/21/2025 |
| DOB NOW | Standpipe | Signed-off | FRED SMITH PLBG & HTG CO. | 02/13/2025 |
| DOB NOW | Standpipe | Signed-off | FRED SMITH P&H CO INC | 02/12/2025 |
| DOB NOW | Sprinklers | Signed-off | FRED SMITH P&H CO INC | 02/12/2025 |
| DOB NOW | Supported Scaffold | Signed-off | CEPRINE CONSTRUCTION INC | 02/07/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | SPRING SCAFFOLDING LLC | 09/12/2024 |
| DOB NOW | General Construction | Signed-off | C. MIZZI CONSTRUCTION COR | 09/05/2024 |
| DOB NOW | Mechanical Systems | Signed-off | HITE CONSTRUCTION | 07/15/2024 |
| DOB NOW | Plumbing | Signed-off | PRACTICAL PLBG & HTG INC | 07/11/2024 |
| DOB NOW | General Construction | Signed-off | HITE CONSTRUCTION | 07/10/2024 |
| DOB NOW | Suspended Scaffold | Permit Issued | SKYLINE RESTORATION INC | 02/22/2024 |
| DOB NOW | General Construction | Permit Issued | SKYLINE RESTORATION INC | 02/20/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | SPRING SCAFFOLDING LLC | 09/12/2023 |
| DOB NOW | Mechanical Systems | Signed-off | SAPOL CONSTRUCTION LLC | 08/01/2023 |
| DOB NOW | Structural | Signed-off | SAPOL CONSTRUCTION LLC | 08/01/2023 |
| DOB NOW | Plumbing | Signed-off | G.P. MECHANICAL CORP | 07/27/2023 |
| DOB NOW | General Construction | Signed-off | ELEZI RENOVATIONS | 07/21/2023 |
| DOB NOW | Mechanical Systems | Signed-off | FIRST STANDARD CONSTR INC | 05/22/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/15/2026 | Permit Issued | RAFFERTY BROTHERS INC | Heating and Air Conditioning Systems | Heat / Cool Task TYE021-LM030 29,900 BTU · Ptac ×1 |
| 04/10/2026 | — | — | Heating and Air Conditioning Systems | Heat / Cool |
| 02/17/2026 | Permit Issued | ALCA RENOVATIONS INC | Air Conditioning Systems | Cooling Islandaire ×8 |
| — | — | — | Air Conditioning Systems | Cooling Task Applied Products TGC021TWEC-25K 24,400 BTU · Condensing Unit ×1 TGC041TWEC 48,800 BTU · Condensing Unit ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/19/2025 | Signed-off | FRED SMITH PLBG & HTG CO. | 6 heads, 1 outlets |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/15/2026 | Permit Issued | F1 MECHANICAL INC | Water/Sanitary |
| 06/12/2026 | Permit Issued | OTC PLUMBING CORP | Water/Sanitary |
| 05/21/2026 | Permit Issued | ALAN J BRUTOSKY PLBR CONT | Gas, Water/Sanitary |
| 02/17/2026 | Signed-off | GOLDS PLUMBING CORP | Gas, Water/Sanitary |
| 11/19/2025 | Signed-off | FRED SMITH P&H CO INC | Water/Sanitary |
| — | — | — | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/09/2026 | Permit Issued | RM ELECTRIC CO., INC. | General Wiring |
| 09/01/2026 | Permit Issued | AMSTERDAM ELECTRIC CORP | General Wiring |
| 08/22/2026 | Permit Issued | POWER MASTERS ELEC'L CONT | — |
| 08/16/2026 | Permit Issued | POWER MASTERS ELEC'L CONT | General Wiring |
| 08/16/2026 | Permit Issued | ELPO ELECTRICAL CONTG INC | General Wiring |
| 05/22/2026 | Complete | THE METRO GROUP ELECTRIC | General Wiring |
| 04/15/2026 | Permit Issued | SHUIR ELEC'L CONTR'S CORP | General Wiring |
| 02/05/2026 | Complete | THE METRO GROUP ELECTRIC | General Wiring |
| 11/18/2025 | Permit Issued | EVS ELECTRIC CORP | General Wiring |
| 10/08/2025 | Permit Issued | ENTERPRISE ELEC'L SYSTEMS | General Wiring |
| 09/27/2025 | Complete | JAM ELECTRICAL CORP | — |
| 09/22/2025 | Complete | OPTIMAL ELECTRIC, INC | General Wiring |
| 07/02/2025 | Complete | W 8 ELECTRIC CORP | — |
| 06/27/2025 | Permit Issued | CONDUCTOR ELECL SVCS INC | General Wiring |
| 05/15/2025 | Complete | R-2 ELECTRIC INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/21/2026 | Permit Issued | TMG CONSTRUCTION CORP | Tenant Protection Plan 72 Hour |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/28/2025 | Permit Issued | SKYLINE ACCESS LLC | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/07/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/25/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/24/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/23/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/13/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/10/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/02/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/16/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/17/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/04/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/31/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/17/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/14/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/14/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/12/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/13/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 08/13/2025 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| 08/12/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/07/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/06/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/06/2025 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 07/17/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/17/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/23/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/15/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/12/2026 | Fire-Resistant Penetrations and Joints | IVA FILIPOVIC | special |
| 06/12/2026 | Lighting in dwelling units | OLGA BAKIC | energy_progress |
| 06/03/2026 | Tenant Protection Plan Compliance | Nikola Martinovic | special |
| 06/03/2026 | Final | OLGA BAKIC | progress |
| 02/23/2026 | Final | — | progress |
| 02/23/2026 | Mechanical Systems | — | special |
| 02/12/2026 | Fire-Resistant Penetrations and Joints | Jeffrey Fine | special |
| 02/12/2026 | Post-installed Anchors | Young Suh | special |
| 02/12/2026 | Mechanical Systems | Jeffrey Fine | special |
| 02/12/2026 | Final | Jeffrey Fine | progress |
| 11/19/2025 | Tenant Protection Plan Compliance | JAMES MOORE | special |
| 11/19/2025 | Standpipe Systems | BRIAN O'ROURKE | special |
| 11/19/2025 | Fire-Resistant Penetrations and Joints | JAMES MOORE | special |
| 11/19/2025 | Sprinkler Systems | BRIAN O'ROURKE | special |
| 07/31/2025 | Air barrier - visual inspection | Ann Macklin | energy_progress |
| 07/31/2025 | HVAC-R and service water heating equipment | Ann Macklin | energy_progress |
| 07/31/2025 | HVAC-R and service water heating system controls | Ann Macklin | energy_progress |
| 07/31/2025 | Energy Code Compliance Inspections | Ann Macklin | progress |
| 07/31/2025 | Final | Ann Macklin | progress |
| 07/31/2025 | Fire-Resistant Penetrations and Joints | Ann Macklin | special |
| 07/31/2025 | Mechanical Systems | Ann Macklin | special |
| 07/31/2025 | Lighting in dwelling units | Ann Macklin | energy_progress |
| 05/09/2025 | Energy Code Compliance Inspections | Ann Macklin | progress |
| 05/09/2025 | HVAC-R and service water heating system controls | Ann Macklin | energy_progress |
| 05/09/2025 | HVAC-R and service water heating equipment | Ann Macklin | energy_progress |