| Owner | Filings | Most Recent |
|---|---|---|
| YAMAHA | 19 | 09/30/2026 |
| JDS CONSCTRUCTION GROUP | 140 | 08/20/2026 |
| JDS DEVELOPMENT GROUP | 7 | 07/08/2026 |
| US CRANE RIGGING LLC | 4 | 03/22/2026 |
| 111 WEST 57 PROPERTY OWNE | 1 | 03/22/2026 |
| 111 WEST 57 LH LLC | 1 | 03/22/2026 |
| 111 WEST 57TH PROPERTY OWNER | 8 | 03/22/2026 |
| VALJATO ENGINEERING P.C | 1 | 03/22/2026 |
| MANHATTAN D ENTERPRISES | 1 | 03/22/2026 |
| JDS CONSTRUCTION GROUPS 1 | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| MARK GETTYS ARCHITECT, P.L.L.C. | 1 | 05/15/2026 |
| GENSLER | 5 | 12/22/2025 |
| MICHAEL ZENREICH ARCHITECT PC | 2 | 12/10/2025 |
| JAROS BAUM & BOLLES | 10 | 10/07/2025 |
| SAUL DAVID HAYUTIN ARCHITECTS | 3 | 10/07/2025 |
| WSP | 5 | 10/06/2025 |
| AMA CONSULTING ENGINEERS, PC | 4 | 07/07/2025 |
| G. BLINN CONSULTING, LLC | 20 | 06/10/2025 |
| JONATHAN B. HELD AIA ARCHITECT | 5 | 05/21/2025 |
| CES ENGINEERING LLC | 4 | 05/06/2024 |
| MAYERFELD ARCHITECTURE PLLC | 2 | 05/05/2024 |
| ENGINEERING GROUP ASSOCIATES, PC | 1 | 02/14/2024 |
| NDKAZALAS ARCHITECTURE P.C. | 3 | 02/10/2024 |
| VISUAL ARCHITECTURE | 1 | 05/16/2023 |
| PATUXENT ENGINEERING LLC | 3 | 08/31/2022 |
| HOWARD I SHAPIRO & ASSOCIATES | 2 | 03/25/2021 |
| JOEL PHAGOO P.E. PLLC | 1 | 08/07/2019 |
| BECKER ENGINEERING, P.C. | 1 | 11/19/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| A1 EXPEDITING SERVICE | 42 | 03/21/2026 |
| MBE CODE ZONING | 54 | 03/21/2026 |
| AGOUTI CONSTRUCTION CONSULTING | 5 | 03/21/2026 |
| JONATHAN B. HELD A.I.A. | 5 | 03/21/2026 |
| PDG BUILDING CONSULTANTS LLC LLC | 2 | 03/21/2026 |
| PATUXENT ENGINEERING | 6 | 03/21/2026 |
| RIGGINING CONSULTANTS | 1 | 03/21/2026 |
| NDKAZALAS ARCHITECTURE | 4 | 03/21/2026 |
| DOMANI CONSULTING | 1 | 03/21/2026 |
| HOWARD I SHAPIRO ASSOCIATES | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| S&E BRIDGE & SCAFFOLD LLC. | General Contractor | 81 | 07/08/2026 |
| THE I. GRACE COMPANY COMM | General Contractor | 9 | 09/30/2026 |
| R & R SCAFFOLDING LTD | General Contractor | 9 | 08/20/2026 |
| JT MAGEN & COMPANY INC | General Contractor | 6 | 07/08/2026 |
| STAT FIRE SPRINKLER NYC C | Fire Protection | 6 | 07/08/2026 |
| MANHATTAN D ENTERPRISES | General Contractor | 6 | 03/21/2026 |
| K & G GEKON INC | General Contractor | 6 | 07/08/2026 |
| DARTOM CABINETRY CORP | General Contractor | 4 | 07/08/2026 |
| PERFECTAIRE CO INC | General Contractor | 3 | 09/01/2026 |
| BEHNAMBAKHSH, SHAYAN | Electrical | 3 | 03/21/2026 |
| OTTEN, GERALD | Electrical | 3 | 03/21/2026 |
| BEDROCK PLBG. & HTG., INC | Plumbing | 3 | 07/08/2026 |
| DONATO PLUMBING, INC | Plumbing | 3 | 09/03/2026 |
| TONY DE FALCO | Electrical | 3 | 03/21/2026 |
| KNS BUILDING REST. INC | General Contractor | 3 | 07/08/2026 |
| MANHATTAN CONCRETE LLC | General Contractor | 3 | 03/21/2026 |
| MINOS CONSTRUCTION CORP | General Contractor | 2 | 03/21/2026 |
| ELICC AMERICAS CORPORATION | General Contractor | 2 | 03/21/2026 |
| URBAN INTELLIGENCE, INC | General Contractor | 2 | 07/08/2026 |
| NEPTUNE MECHANICAL INC | Plumbing | 1 | 07/08/2026 |
| ARROYO, RAFAEL | Electrical | 1 | 03/21/2026 |
| MICHAELOFF, STEVEN | Electrical | 1 | 03/21/2026 |
| NASH ELECTRIC SERVICES IN | Electrical | 1 | 03/22/2026 |
| BEDROCK MECHANICAL INC | Fire Protection | 1 | 07/08/2026 |
| HF GROUP PLMBG & SPNKLER | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| MICHAEL ZENREICH ARCHITEC | 1724 | 2 | 12/10/2025 |
| SOCOTEC ENGINEERING | 4983 | 6 | 12/08/2025 |
| RHL ENGINEERING, LLC | 712 | 11 | 10/07/2025 |
| JAROS, BAUM & BOLLES | 1092 | 4 | 10/07/2025 |
| RICHMOND TESTING LAB | 263 | 2 | 10/06/2025 |
| WSP USA CORP | 1848 | 3 | 10/06/2025 |
| G. BLINN CONSULTING, LLC | 2894 | 2 | 06/10/2025 |
| JONATHAN B. HELD AIA ARCH | 1288 | 5 | 05/21/2025 |
| AG ENGINEERING PLLC | 8899 | 5 | 05/21/2025 |
| INTEGRITY CONSULTING SERV | 666 | 4 | 05/06/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Permit Issued | THE I. GRACE COMPANY COMM | 09/29/2026 |
| DOB NOW | General Construction | Permit Issued | THE I. GRACE COMPANY COMM | 09/29/2026 |
| DOB NOW | General Construction | Permit Issued | THE I. GRACE COMPANY COMM | 09/29/2026 |
| DOB NOW | Plumbing | Permit Issued | DONATO PLUMBING, INC | 09/02/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | PERFECTAIRE CO INC | 08/31/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | R & R SCAFFOLDING LTD | 08/18/2026 |
| DOB NOW | Structural | Signed-off | THE I. GRACE COMPANY COMM | 06/22/2026 |
| DOB NOW | Plumbing | Permit Issued | AMN PLUMBING CORP | 01/09/2026 |
| DOB NOW | General Construction | Permit Issued | CARDINAL BUILDERS, INC | 12/22/2025 |
| DOB NOW | Sprinklers | Permit Issued | STAT FIRE SPRINKLER NYC C | 12/11/2025 |
| DOB NOW | Standpipe | Permit Issued | STAT FIRE SPRINKLER NYC C | 10/01/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | PERFECTAIRE CO INC | 09/29/2025 |
| DOB NOW | Structural | Signed-off | JT MAGEN & COMPANY INC | 09/26/2025 |
| DOB NOW | Mechanical Systems | Signed-off | JT MAGEN & COMPANY INC | 09/26/2025 |
| DOB NOW | General Construction | Signed-off | JT MAGEN & COMPANY INC | 09/26/2025 |
| DOB NOW | Supported Scaffold | Permit Issued | S&E BRIDGE & SCAFFOLD LLC | 09/26/2025 |
| DOB NOW | Structural | Signed-off | JT MAGEN & COMPANY INC | 09/17/2025 |
| DOB NOW | Plumbing | Permit Issued | DONATO PLUMBING, INC | 09/05/2025 |
| DOB NOW | General Construction | Permit Issued | THE I. GRACE COMPANY COMM | 09/02/2025 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | R & R SCAFFOLDING LTD | 08/12/2025 |
| DOB NOW | Structural | Permit Issued | THE I. GRACE COMPANY COMM | 07/31/2025 |
| DOB NOW | Mechanical Systems | Signed-off | PERFECTAIRE CO INC | 07/07/2025 |
| DOB NOW | Standpipe | Permit Issued | STAT FIRE SPRINKLER NYC C | 06/24/2025 |
| DOB NOW | Supported Scaffold | Permit Issued | S&E BRIDGE & SCAFFOLD LLC | 06/11/2025 |
| DOB NOW | Sprinklers | Permit Issued | STAT FIRE SPRINKLER NYC C | 06/02/2025 |
| DOB NOW | Plumbing | Permit Issued | DONATO PLUMBING, INC | 06/01/2025 |
| DOB NOW | General Construction | Permit Issued | THE I. GRACE COMPANY COMM | 05/08/2025 |
| DOB NOW | Structural | Signed-off | THE I. GRACE COMPANY COMM | 05/08/2025 |
| DOB NOW | Sprinklers | Permit Issued | ARCO PLBG AND HTG INC | 04/23/2025 |
| DOB NOW | Sprinklers | Permit Issued | STAT FIRE SPRINKLER NYC C | 03/18/2025 |
| DOB NOW | Plumbing | Signed-off | BEDROCK PLBG. & HTG., INC | 03/11/2025 |
| DOB NOW | Sprinklers | Signed-off | BEDROCK MECHANICAL INC | 03/11/2025 |
| DOB NOW | Mechanical Systems | Signed-off | JT MAGEN & COMPANY INC | 03/10/2025 |
| DOB NOW | General Construction | Signed-off | JT MAGEN & COMPANY INC | 03/03/2025 |
| DOB NOW | Sprinklers | Permit Issued | HF GROUP PLMBG & SPNKLER | 02/04/2025 |
| DOB NOW | General Construction | Permit Issued | K G GEKON | 12/09/2024 |
| DOB NOW | General Construction | Permit Issued | K G GEKON | 12/05/2024 |
| DOB NOW | General Construction | Permit Issued | K G GEKON | 08/28/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | K G GEKON | 08/28/2024 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | R & R SCAFFOLDING LTD | 07/29/2024 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 12/08/2025 | Signed-off | JT MAGEN & COMPANY INC | Air Conditioning Systems | Cooling |
| 10/07/2025 | Permit Issued | THE I. GRACE COMPANY COMM | Heating and Air Conditioning Systems | Heat / Cool |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/08/2025 | Signed-off | BEDROCK MECHANICAL INC | Sprinkler System |
| 10/07/2025 | Permit Issued | STAT FIRE SPRINKLER NYC C | Sprinkler System |
| 05/21/2025 | Permit Issued | STAT FIRE SPRINKLER NYC C | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/10/2025 | Permit Issued | AMN PLUMBING CORP | Water/Sanitary |
| 12/08/2025 | Signed-off | BEDROCK PLBG. & HTG., INC | Water/Sanitary |
| 10/07/2025 | Permit Issued | DONATO PLUMBING, INC | Water/Sanitary |
| 05/21/2025 | Permit Issued | ARCO PLBG AND HTG INC | Water/Sanitary |
| 08/28/2023 | Signed-off | NEPTUNE MECHANICAL INC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/01/2026 | Permit Issued | DEFALCO ASSOCIATES, LLC./ | General Wiring |
| 05/29/2026 | Permit Issued | GLENDALE ELECTL CONTNG IN | General Wiring |
| 04/17/2026 | Permit Issued | M.C. ELECTRICAL NY INC | General Wiring |
| 07/09/2025 | Permit Issued | WARREN OSTROFF ELEC., INC | General Wiring |
| 06/23/2025 | Complete | APOLLO ELECTRIC NYG, INC | General Wiring |
| 05/22/2025 | Permit Issued | WARREN OSTROFF ELEC., INC | — |
| 12/11/2024 | Permit Issued | TF ELECTRICAL CORP | General Wiring |
| 09/23/2024 | Permit Issued | DEFALCO ASSOCIATES, LLC./ | General Wiring |
| 09/10/2024 | Permit Issued | KINGS ELECTRIC CO., INC. | General Wiring |
| 08/27/2024 | Complete | LTC ELEC'L CONTR'G LLC | General Wiring |
| 08/07/2024 | Complete | GLENDALE ELECTL CONTNG IN | General Wiring |
| 05/28/2024 | Complete | DEFALCO ASSOCIATES, LLC./ | General Wiring |
| 05/21/2024 | Permit Issued | DEFALCO ASSOCIATES, LLC./ | General Wiring |
| 03/28/2024 | Complete | A.L. ELECTRICAL CORP. | General Wiring |
| 07/06/2023 | Complete | GLENDALE ELECTL CONTNG IN | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/08/2025 | Signed-off | JT MAGEN & COMPANY INC | Steel, Concrete |
| 10/07/2025 | Permit Issued | THE I. GRACE COMPANY COMM | Steel |
| 02/14/2024 | — | — | Wood |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/10/2025 | Permit Issued | S&E BRIDGE & SCAFFOLD LLC | Scaffold |
| 08/07/2019 | Permit Issued | KNS BUILDING REST. INC | Scaffold |
| 11/19/2018 | Permit Issued | MANHATTAN CONCRETE LLC | Scaffold |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/07/2025 | Permit Issued | THE I. GRACE COMPANY COMM | Tenant Protection Plan 72 Hour |
| Date | Type | Result | Report |
|---|---|---|---|
| 06/18/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/15/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/15/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/07/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/27/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 02/24/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/30/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 01/28/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/15/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/06/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/30/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 12/18/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/11/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/05/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/04/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/31/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/31/2025 | Certified Sprinkler-Dry Pipe Valve (SP)-Dry Pipe Valve Test | Certified | View ↗ |
| 10/31/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/31/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/19/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/09/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 09/09/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/08/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 09/04/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 09/04/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/24/2026 | Final | — | progress |
| 12/15/2025 | Final | RYAN LEAN | progress |
| 12/15/2025 | Post-installed Anchors | Vincent Gentile | special |
| 12/15/2025 | Fire-Resistant Penetrations and Joints | Vincent Gentile | special |
| 12/15/2025 | Mechanical Systems | RYAN LEAN | special |
| 12/15/2025 | HVAC-R and service water heating system controls | RYAN LEAN | energy_progress |
| 12/15/2025 | HVAC-R and service water heating equipment | RYAN LEAN | energy_progress |
| 12/15/2025 | Energy Code Compliance Inspections | RYAN LEAN | progress |
| 12/15/2025 | HVAC-R and service water piping design and insulation | RYAN LEAN | energy_progress |
| 12/09/2025 | Lighting controls | ALEXIS SCHLESSINGERMAN | energy_progress |
| 12/09/2025 | Interior lighting power | ALEXIS SCHLESSINGERMAN | energy_progress |
| 12/09/2025 | Final | Thomas Lanzelotti | progress |
| 12/09/2025 | Fire-Resistance Rated Construction | ALEXIS SCHLESSINGERMAN | progress |
| 12/09/2025 | Fire-Resistant Penetrations and Joints | ALEXIS SCHLESSINGERMAN | special |
| 12/09/2025 | Mastic and Intumescent Fire-resistant Coatings | ALEXIS SCHLESSINGERMAN | special |
| 12/09/2025 | Post-installed Anchors | ALEXIS SCHLESSINGERMAN | special |
| 12/09/2025 | Sprayed fire-resistant materials | ALEXIS SCHLESSINGERMAN | special |
| 11/19/2025 | Post-installed Anchors | ALEXIS SCHLESSINGERMAN | special |
| 11/19/2025 | Mastic and Intumescent Fire-resistant Coatings | ALEXIS SCHLESSINGERMAN | special |
| 11/19/2025 | Fire-Resistant Penetrations and Joints | ALEXIS SCHLESSINGERMAN | special |
| 11/19/2025 | Final | Thomas Lanzelotti | progress |
| 11/19/2025 | Lighting controls | ALEXIS SCHLESSINGERMAN | energy_progress |
| 11/19/2025 | Fire-Resistance Rated Construction | ALEXIS SCHLESSINGERMAN | progress |
| 11/19/2025 | Interior lighting power | ALEXIS SCHLESSINGERMAN | energy_progress |
| 11/19/2025 | Sprayed fire-resistant materials | ALEXIS SCHLESSINGERMAN | special |