RoofUnder Construction2p · 3 filings · 12 docs
ArchitectureStructuralOther
Issued Permit Scope
Protection and Mechanical Methods
Use of temporary suspended scaffold from building maintenance unit as per plans filed herewith.
On file for this project
2 documents
FISP INSPECTION (Facade Inspection Safety Program) INDUSTRIAL ROPE ACCESS TECHNIQUES AND METHODS. SEE ATTACHED PLANS Designated Primary Site supervisor: Kenneth Cole
On file for this project
2 documents · 1 drawing sheet
HEREWITH FILING ALTERATION TYPE II FOR VARIOUS ALTERATIONS TO APARTMENT AS PER PLANS. NO CHANGE TO USE, EGRESS, OR OCCUPANCY IS PROPOSED UNDER THIS APPLICATION.
On file for this project
8 documents · 1 drawing sheet
Floor 691 filing · 20 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Renovation of an existing duplex apartment on the 68/69 floors. Work to include non-structural demolition and general construction as per plans herewith. No change to use, egress or occupancy.
On file for this project
20 documents
Floor 681 filing · 20 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Renovation of an existing duplex apartment on the 68/69 floors. Work to include non-structural demolition and general construction as per plans herewith. No change to use, egress or occupancy.
On file for this project
20 documents
Floor 67
Floor 66
Floor 65
Floor 64
Floor 63
Floor 62
Floor 61
Floor 60
Floor 59
Floor 581 filing · 2 docs
Structural
Issued Permit Scope
Supported Scaffold
INSTALLATION OF SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
Floor 57
Floor 56
Floor 551 filing · 10 docs
Architecture
Issued Permit Scope
General Construction
Renovation of an existing duplex apartment on the 54/55 construction (60/61 marketing) floors. Work to include minor ceiling work and general construction as per plans herewith. No change in use, egress or occupancy
On file for this project
10 documents
Floor 541 filing · 10 docs
Architecture
Issued Permit Scope
General Construction
Renovation of an existing duplex apartment on the 54/55 construction (60/61 marketing) floors. Work to include minor ceiling work and general construction as per plans herewith. No change in use, egress or occupancy
On file for this project
10 documents
Floor 53
Floor 52
Floor 51
Floor 50
Floor 49
Floor 48
Floor 47
Floor 46
Floor 45Under Construction1 filing · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
The scope of this project includes modifications to existing ductwork and diffuser routing, relocation of a fire smoke damper and CVR, and the addition of an indoor VRF unit and associated ductwork piping distribution.
On file for this project
86 documents
Floor 44Under Construction2 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
The scope of this project includes modifications to existing ductwork and diffuser routing, relocation of a fire smoke damper and CVR, and the addition of an indoor VRF unit and associated ductwork piping distribution.
On file for this project
86 documents
Filing subsequent plumbing filing for cap/removal of fixtures only.
On file for this project
12 documents
Floor 43
Floor 42
Floor 41
Floor 40
Floor 39
Floor 38
Floor 37
Floor 36
Floor 35
Floor 34
Floor 33
Floor 32
Floor 31
Floor 30
Floor 29
Floor 28
Floor 27
Floor 26
Floor 25
Floor 24
Floor 23
Floor 22
Floor 21
Floor 20
Floor 19
Floor 18
Floor 172 filings · 10 docs
ArchitectureGeneral
Issued Permit Scope
General Construction · Protection and Mechanical Methods
HEREWITH FILING ALTERATION TYPE II FOR VARIOUS ALTERATIONS TO APARTMENT AS PER PLANS. NO CHANGE TO USE, EGRESS, OR OCCUPANCY IS PROPOSED UNDER THIS APPLICATION.
On file for this project
8 documents
INSTALLATION OF TEMPORARY SUSPENDED SCAFFOLD AS PER DRAWINGS DURING BLDG ALTERATION, FILED SEP. SUSPENDED SCAFFOLD SHALL COMPLY WITH CH 33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
Floor 165 filings · 16 docs
ArchitecturePlumbingStructural
Issued Permit Scope
General Construction · Plumbing · Protection and Mechanical Methods · Supported Scaffold
HEREWITH FILING ALTERATION TYPE II FOR VARIOUS ALTERATIONS TO APARTMENT AS PER PLANS. NO CHANGE TO USE, EGRESS, OR OCCUPANCY IS PROPOSED UNDER THIS APPLICATION.
On file for this project
8 documents
SCAFFOLD 6TH TO 16TH. INSTALLATION OF SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
INSTALLATION OF TEMPORARY TROLLEY BEAM SYSTEM AS PER DRAWINGS. TROLLEY BEAM SYSTEM SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THISAPPLICATION.
On file for this project
2 documents
Latest 3 of 5 filings on this floor.
Floor 151 filing · 2 docs
Structural
Issued Permit Scope
Supported Scaffold
SCAFFOLD 6TH TO 16TH. INSTALLATION OF SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
Floor 141 filing · 2 docs
Structural
Issued Permit Scope
Supported Scaffold
SCAFFOLD 6TH TO 16TH. INSTALLATION OF SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
Floor 134 filings · 8 docs
ArchitectureStructural
Issued Permit Scope
Supported Scaffold
SCAFFOLD 6TH TO 16TH. INSTALLATION OF SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
INSTALLATION OF SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
INSTALLATION OF SYSTEM SCAFFOLDING AS PER DRAWINGS. SYSTEM SCAFFOLDING SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
Latest 3 of 4 filings on this floor.
Floor 121p · 5 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers · Supported Scaffold
Interior renovation. Non-structural partition removal and construction of new partitions. No change to use, egress or occupancy.
On file for this project
53 documents · 1 drawing sheet
SCAFFOLD 6TH TO 16TH. INSTALLATION OF SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
INSTALLATION OF SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
Latest 3 of 5 filings on this floor.
Floor 116 filings · 16 docs
ArchitectureEquipmentGeneralStructural
Issued Permit Scope
Supported Scaffold
SCAFFOLD 6TH TO 16TH. INSTALLATION OF SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
INSTALLATION OF TEMPORARY SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
6 documents
INSTALLATION OF SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
Latest 3 of 6 filings on this floor.
Floor 105 filings · 14 docs
ArchitectureEquipmentGeneralStructural
Issued Permit Scope
Supported Scaffold
SCAFFOLD 6TH TO 16TH. INSTALLATION OF SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
INSTALLATION OF TEMPORARY SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
6 documents
INSTALLATION OF SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
Latest 3 of 5 filings on this floor.
Floor 91p · 5 filings · 14 docs
ArchitectureEquipmentGeneralStructural
Issued Permit Scope
Supported Scaffold
SCAFFOLD 6TH TO 16TH. INSTALLATION OF SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
INSTALLATION OF TEMPORARY SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
6 documents
INSTALLATION OF SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
Latest 3 of 5 filings on this floor.
Floor 84 filings · 12 docs
ArchitectureEquipmentGeneralStructural
Issued Permit Scope
Supported Scaffold
SCAFFOLD 6TH TO 16TH. INSTALLATION OF SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
INSTALLATION OF TEMPORARY SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
6 documents
INSTALLATION OF SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
Latest 3 of 4 filings on this floor.
Floor 71p · 6 filings · 16 docs
ArchitectureEquipmentGeneralMechanicalStructural
Issued Permit Scope
Protection and Mechanical Methods · Supported Scaffold
SCAFFOLD 6TH TO 16TH. INSTALLATION OF SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
INSTALLATION OF TEMPORARY SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
6 documents
INSTALLATION OF TEMPORARY WORK PLATFORM AS PER DRAWINGS. TEMPORARY WORK PLATFORM SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents · 1 drawing sheet
Latest 3 of 6 filings on this floor.
Floor 61p · 4 filings · 20 docs
ArchitectureEquipmentGeneralMechanicalStructural
Issued Permit Scope
Structural · Supported Scaffold
Structural renovation for an existing building, for the retail space Bonhams, Ground Fl through 6th Floors. No change of use, egress or occupancy on this application.
On file for this project
42 documents · 1 drawing sheet
SCAFFOLD 6TH TO 16TH. INSTALLATION OF SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
INSTALLATION OF TEMPORARY SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
6 documents
Latest 3 of 4 filings on this floor.
Floor 51p · 3 filings · 20 docs
ArchitectureGeneralMechanicalStructural
Issued Permit Scope
Structural · Supported Scaffold
Structural renovation for an existing building, for the retail space Bonhams, Ground Fl through 6th Floors. No change of use, egress or occupancy on this application.
On file for this project
42 documents · 1 drawing sheet
TEMPORARY SUPPORTED SCAFFOLD AS PER DRAWINGS. SUPPORTED SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
3 documents
INSTALLATION OF SCAFFOLD IN ATRIUM AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
Floor 42p · 4 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural · Supported Scaffold
Structural renovation for an existing building, for the retail space Bonhams, Ground Fl through 6th Floors. No change of use, egress or occupancy on this application.
On file for this project
42 documents · 2 drawing sheets
TEMPORARY SUPPORTED SCAFFOLD AS PER DRAWINGS. SUPPORTED SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
3 documents
INSTALLATION OF SCAFFOLD IN ATRIUM AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
Latest 3 of 4 filings on this floor.
Floor 31p · 4 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural · Supported Scaffold
Structural renovation for an existing building, for the retail space Bonhams, Ground Fl through 6th Floors. No change of use, egress or occupancy on this application.
On file for this project
42 documents · 1 drawing sheet
TEMPORARY SUPPORTED SCAFFOLD AS PER DRAWINGS. SUPPORTED SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
3 documents
INSTALLATION OF SCAFFOLD IN ATRIUM AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
Latest 3 of 4 filings on this floor.
Floor 21p · 3 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural · Supported Scaffold
Structural renovation for an existing building, for the retail space Bonhams, Ground Fl through 6th Floors. No change of use, egress or occupancy on this application.
On file for this project
42 documents · 1 drawing sheet
TEMPORARY SUPPORTED SCAFFOLD AS PER DRAWINGS. SUPPORTED SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
3 documents
INSTALLATION OF SCAFFOLD IN ATRIUM AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
Floor 11p · 4 filings · 20 docs
ArchitectureElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructuralOther
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sidewalk Shed · Sprinklers · Structural · Supported Scaffold
Structural renovation for an existing building, for the retail space Bonhams, Ground Fl through 6th Floors. No change of use, egress or occupancy on this application.
On file for this project
42 documents · 1 drawing sheet
TEMPORARY SUPPORTED SCAFFOLD AS PER DRAWINGS. SUPPORTED SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
3 documents
INSTALLATION OF SIDEWALK SHED FOR PEDESTRIAN SAFETY DURING CONSTRUCTION. SIDEWALK SHED SHALL COMPLY WITH NYCC 2014 CHAPTER 33 . NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
On file for this project
6 documents
Latest 3 of 4 filings on this floor.
Cellar13p · 1 filing · 20 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Structural renovation for an existing building, for the retail space Bonhams, Ground Fl through 6th Floors. No change of use, egress or occupancy on this application.
On file for this project
42 documents · 13 drawing sheets
Site & exterior5 filings · 15 docs
ArchitectureEquipmentGeneralStructural
Issued Permit Scope
Supported Scaffold
INSTALLATION OF TEMPORARY SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
6 documents · 10 drawing sheets
INSTALLATION OF SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents · 1 drawing sheet
INSTALLATION OF SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents · 1 drawing sheet
Latest 3 of 5 filings on this floor.
Filed — no permit issued5 filings · 20 docs
ArchitectureDMGeneralStructural
No filed description on record for this project.
On file for this project
3 documents · 12 drawing sheets
No filed description on record for this project.
On file for this project
4 documents · 3 drawing sheets
No filed description on record for this project.
On file for this project
4 documents · 3 drawing sheets
Latest 3 of 5 filings on this floor.