← Back
Public elementary, junior or senior high
Hamilton Fish Park Branch Library
116 COLUMBIA STREET · BIN 1004070
💬 Discuss this project
1958Year Built
3Stories
W1Building Class
R7-2Zoning
217,300 sfGross Floor Area
0Units
LL97 Covered8 Open Violations 4 unresolved · 4 paperwork only ▸FDNY Report ↗
Public elementary, junior or senior high · Owner of record: NYC DEPARTMENT OF EDUCATION · 80,040 sf lot · 2.71 FAR built · Flood zone X500
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionEquipmentOther
Permit Issued — active, not yet Signed-off
RoofUnder Construction29p · 4 filings · 20 docs
Floor 3Under Construction4p · 1 filing · 20 docs
Floor 2Under Construction7p · 2 filings · 20 docs
Floor 1Under Construction45p · 7 filings · 20 docs
CellarUnder Construction26p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYCSCA6807/15/2026
LANMARK GROUP507/08/2026
LEMX407/08/2026
NYC DEPARTMENT OF EDUCATION103/22/2026
DEPARTMENT OF EDUCATION703/22/2026
D.O.E. 0403/22/2026
DOE J.H.S. 22503/22/2026
DOE NEW EXPLORATION S040403/22/2026
DOE NEW EXPL SCI TECH040103/22/2026
DEPT. OF EDUCATION 0103/22/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JAM CONSULTANTS, INC.1803/21/2026
SUPERSTRUCTURES ENG + ARCH903/21/2026
PRECISION 3SIXTY NYC, INC1003/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
NATIONAL ENVIROMENTAL SAFETYGeneral Contractor5107/15/2026
LANMARK GROUP INCGeneral Contractor1007/08/2026
TRAX MECHANICAL LLCGeneral Contractor603/21/2026
HEPCO HTG & PLBG INCPlumbing607/25/2026
EON MECHANICAL INCGeneral Contractor507/08/2026
ALPINE ENTERPRISES NY LTDGeneral Contractor407/03/2026
EAGLE MECHANICAL INCFire Protection407/08/2026
MAR-SAL PLBG & HTG, INCPlumbing307/08/2026
LOCAL 40 IRON WORKERS UNIElectrical103/21/2026
PAUL BOCCIAElectrical103/21/2026
RAIKOS ELECTRIC LLCElectrical103/22/2026
ANCO ELECTL CONTCTNG INCElectrical103/22/2026
SIEGEL, SElectrical103/21/2026
STANCO SYSTEM ELEC'L CONTElectrical103/22/2026
LEMX CORPGeneral Contractor107/08/2026
RICHARD NEUElectrical103/22/2026
CAPIZZO, VITOElectrical103/21/2026
CEDOMIR MARAElectrical103/21/2026
FAJARDO, JOSEElectrical103/21/2026
FRANCIS RICHARDSElectrical103/21/2026
FREDERICK LEEElectrical103/21/2026
GIBALDI, CAMILLOElectrical103/21/2026
GILSTON ELEC'L CONTNG LLCElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
JPC LOGISTICS DBA JPCL EN351506/17/2026
MP ENGINEERS & ARCHITECTS1438712/20/2025
20/20 INSPECTIONS INC14711310/16/2024
UNIVERSAL TESTING AND INS400105/13/2022
Building Lifecycle
All (266)Filed (31)Permit Issued (65)Signed Off (1)Violation (60)Inspection (15)Objection (64)Special Inspection (30)
09/02/2026
Inspection — Fail-Final SP - More than 10 Requested Floors
Fail
View inspection ↗
09/01/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
08/18/2026
Special inspection requirement — Mechanical Systems
Asma Hashmi
08/18/2026
Special inspection requirement — Final
Asma Hashmi
08/18/2026
Special inspection requirement — Post-installed Anchors
Asma Hashmi
08/18/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Asma Hashmi
07/30/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
07/27/2026
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
07/24/2026
Permit issued — Plumbing
M00935924-S1-PL
07/24/2026
Permit issued — Plumbing
M00345650-I1-PL
07/20/2026
Objection resolved — Resolved
07/20/2026
Objection resolved — Resolved
07/20/2026
Objection resolved — Resolved
07/17/2026
Objection raised — Scope
07/17/2026
Objection raised — Other
07/17/2026
Objection raised — Other
07/14/2026
Permit issued — General Construction
M00692119-I1-GC
07/01/2026
Permit issued — Mechanical Systems
M00345688-I1-MS
06/23/2026
Permit issued — Structural
M00692119-S1-GC
06/23/2026
Permit issued — Structural
M00692119-S1-FO
06/22/2026
Permit issued — Supported Scaffold
M00995597-I1-SF
06/22/2026
Permit issued — Construction Fence
M00981140-I1-FN
06/22/2026
Permit issued — Structural
M00692119-S1-ST
06/22/2026
Permit issued — Support of Excavation
M00968683-I1-SE
06/17/2026
Filed — Alteration
THE SCOPE OF WORK INCLUDES ALL LABOR, MATERIALS, AND EQUIPMENT NECESSARY TO COMPLETE INSTALLATION OF THE SUPPLEMENTAL COOLING SYSTEM IN THE AUDITORIUM AND THREE CLASSROOMS.
M01278897-P1
05/22/2026
Permit issued — Plumbing
M00692119-S3-PL
05/22/2026
Permit issued — Plumbing
M00692119-S3-EW-SP
05/08/2026
Permit issued — Sidewalk Shed
M00995325-I1-SH
04/28/2026
Permit issued — General Construction
M00692119-I1-GC
02/17/2026
Permit issued — Support of Excavation
M00968683-I1-SE
02/17/2026
Permit issued — Supported Scaffold
M00995597-I1-SF
02/17/2026
Permit issued — Construction Fence
M00981140-I1-FN
02/06/2026
Special inspection requirement — HVAC and service water heating system controls
JAMES WILSON
02/06/2026
Special inspection requirement — Electrical energy consumption
JAMES WILSON
02/06/2026
Special inspection requirement — Mechanical Systems
JAMES WILSON
02/06/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
JAMES WILSON
02/06/2026
Special inspection requirement — Maintenance information
JAMES WILSON
02/06/2026
Special inspection requirement — Electrical motors
JAMES WILSON
02/06/2026
Special inspection requirement — HVAC and service water heating equipment
JAMES WILSON
02/06/2026
Special inspection requirement — Shutoff dampers
JAMES WILSON
02/06/2026
Special inspection requirement — Final
JAMES WILSON
02/06/2026
Special inspection requirement — HVAC insulation and sealing
JAMES WILSON
02/05/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
01/27/2026
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
01/27/2026
Objection resolved — Addressed
01/21/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
01/20/2026
Objection resolved — Addressed
01/20/2026
Objection resolved — Addressed
01/15/2026
Objection resolved — Addressed
01/14/2026
Violation issued (FDNY_ORDER, closed)
01/14/2026
Violation issued (FDNY_ORDER, closed)
01/14/2026
Violation issued (FDNY_ORDER, closed)
01/02/2026
Objection raised — Energy
12/30/2025
Permit issued — Sprinklers
M00692119-S3-EW-SP
12/29/2025
Objection resolved — Addressed
12/29/2025
Objection resolved — Addressed
12/20/2025
Filed — Alteration
Mechanical work related to library renovation
M00345688-P2
12/18/2025
Objection raised — Admin
12/18/2025
Objection raised — Scope
12/18/2025
Objection raised — Scope
Latest 60 of 266 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedHEPCO HTG & PLBG INC07/24/2026
DOB NOWPlumbingPermit IssuedHEPCO HTG & PLBG INC07/24/2026
DOB NOWGeneral ConstructionPermit IssuedNATIONAL ENVIROMENTAL SAFETY07/14/2026
DOB NOWMechanical SystemsPermit IssuedALPINE ENTERPRISES NY LTD07/01/2026
DOB NOWStructuralPermit IssuedNATIONAL ENVIROMENTAL SAFETY06/23/2026
DOB NOWStructuralPermit IssuedNATIONAL ENVIROMENTAL SAFETY06/23/2026
DOB NOWSupported ScaffoldPermit IssuedNATIONAL ENVIROMENTAL SAFETY06/22/2026
DOB NOWConstruction FencePermit IssuedNATIONAL ENVIROMENTAL SAFETY06/22/2026
DOB NOWStructuralPermit IssuedNATIONAL ENVIROMENTAL SAFETY06/22/2026
DOB NOWSupport of ExcavationPermit IssuedNATIONAL ENVIROMENTAL SAFETY06/22/2026
DOB NOWPlumbingPermit IssuedMAR-SAL PLBG & HTG, INC05/22/2026
DOB NOWPlumbingPermit IssuedEAGLE MECHANICAL INC05/22/2026
DOB NOWSidewalk ShedPermit IssuedNATIONAL ENVIROMENTAL SAFETY05/08/2026
DOB NOWGeneral ConstructionPermit IssuedNATIONAL ENVIROMENTAL SAFETY04/28/2026
DOB NOWSupport of ExcavationPermit IssuedNATIONAL ENVIROMENTAL SAF02/17/2026
DOB NOWSupported ScaffoldPermit IssuedNATIONAL ENVIROMENTAL SAF02/17/2026
DOB NOWConstruction FencePermit IssuedNATIONAL ENVIROMENTAL SAF02/17/2026
DOB NOWSprinklersPermit IssuedEAGLE MECHANICAL INC12/30/2025
DOB NOWMechanical SystemsPermit IssuedEON MECHANICAL INC11/07/2025
DOB NOWStructuralPermit IssuedLANMARK GROUP INC10/23/2025
DOB NOWEarth WorkPermit IssuedLANMARK GROUP INC10/23/2025
DOB NOWConstruction FencePermit IssuedLANMARK GROUP INC10/21/2025
DOB NOWMechanical SystemsPermit IssuedALPINE ENTERPRISES NY LTD07/21/2025
DOB NOWPlumbingPermit IssuedEAGLE MECHANICAL INC07/07/2025
DOB NOWPlumbingPermit IssuedHEPCO HTG & PLBG INC07/01/2025
DOB NOWPlumbingPermit IssuedHEPCO HTG & PLBG INC07/01/2025
DOB NOWGeneral ConstructionPermit IssuedNATIONAL ENVIROMENTAL SAF06/30/2025
DOB NOWGeneral ConstructionPermit IssuedNATIONAL ENVIROMENTAL SAF06/30/2025
DOB NOWGeneral ConstructionPermit IssuedNATIONAL ENVIROMENTAL SAF06/30/2025
DOB NOWSprinklersPermit IssuedMAR-SAL PLBG & HTG, INC06/10/2025
DOB NOWEarth WorkPermit IssuedLANMARK GROUP INC05/22/2025
DOB NOWStructuralPermit IssuedLANMARK GROUP INC05/21/2025
DOB NOWMechanical SystemsPermit IssuedEON MECHANICAL INC05/05/2025
DOB NOWGeneral ConstructionPermit IssuedNATIONAL ENVIROMENTAL SAF04/21/2025
DOB NOWGeneral ConstructionPermit IssuedNATIONAL ENVIROMENTAL SAF04/15/2025
DOB NOWSupported ScaffoldPermit IssuedNATIONAL ENVIROMENTAL SAF03/03/2025
DOB NOWSidewalk ShedPermit IssuedNATIONAL ENVIROMENTAL SAF02/06/2025
DOB NOWSupport of ExcavationPermit IssuedNATIONAL ENVIROMENTAL SAF02/05/2025
DOB NOWConstruction FencePermit IssuedNATIONAL ENVIROMENTAL SAF02/04/2025
DOB NOWConstruction FencePermit IssuedLANMARK GROUP INC01/02/2025
+ 49 more permits on file
5 projects · most recent 06/17/2026
Air Conditioning Systems Heating Systems Associated Ducts and Piping Heating and Air Conditioning Systems Others Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
06/17/2026——Air Conditioning Systems
Cooling
Lg LG ARNU363SVA4 35,500 BTU · Vrf Indoor ×65
LG ARNU363V2AA 36,200 BTU · Vrf Indoor ×5
LG ARUNO96BSS5 92,000 BTU · Vrf Indoor ×25
12/20/2025Permit IssuedALPINE ENTERPRISES NY LTDAir Conditioning Systems, Heating Systems
Cooling
Daikin REYQ168XATJA 160,000 BTU · Vrf Outdoor ×2
REYQ216AATJA 216,000 BTU · Vrf Outdoor ×2
ACC-1A 92,000 BTU · Vrf Outdoor ×1
ACC-1B 114,000 BTU · Vrf Outdoor ×1
ACC-2 160,000 BTU · Vrf Outdoor ×1
Heating
Daikin REYQ120XATJA 129,000 BTU · Vrf Outdoor ×1
REYQ168XATJA 180,000 BTU · Vrf Outdoor ×1
REYQ96XATJA 103,000 BTU · Vrf Outdoor ×1
09/10/2025——Air Conditioning Systems
Cooling
Lg LG ARNU243TAA4 24,000 BTU · Vrf Indoor ×13
LG ARUNO96BSS5 92,000 BTU · Vrf Indoor ×4
LG ARNU363SVA4 36,000 BTU · Vrf Indoor ×2
LG ARUNO72BSS5 69,000 BTU · Vrf Outdoor ×1
07/28/2025——Air Conditioning Systems
Cooling
Fujitsu FUJITSU - AUUA24TLAV2 24,000 BTU · Fan Coil Indoor ×3
FUJITSU - AOU72RLAVL 72,000 BTU · Condensing Unit ×1
10/16/2024Permit IssuedNATIONAL ENVIROMENTAL SAFAssociated Ducts and Piping, Heating and Air Conditioning Systems, Others, Ventilation Systems
Heat / Cool
Qmark NONE PROVIDED 5 kW · Electric Heater ×8
Lg LSN363HLV 35,000 BTU · Split System ×2
LSU363HLV 33 BTU · Condensing Unit ×2
Ventilation
Loren Cook ACE-B 400 CFM · Exhaust Fan ×2
None Provided 220 CFM · Fan Coil Indoor ×2
Ducts & Piping
Anemostat S30-45 1,250 BTU · Exhaust Fan ×8
Other
Mars Air Systems STD272-2E**-OB 12 kW · Air Curtain ×8
1 project · most recent 10/16/2024
FiledStatusContractorScope
10/16/2024Permit IssuedEAGLE MECHANICAL INC376 heads
4 projects · most recent 11/25/2024
Storm Water/Sanitary
FiledStatusContractorScope
11/25/2024Permit IssuedHEPCO HTG & PLBG INCStorm, Water/Sanitary
10/16/2024Permit IssuedMAR-SAL PLBG & HTG, INCStorm, Water/Sanitary
11/10/2023Permit IssuedHEPCO HTG & PLBG INCStorm
05/13/2022——Water/Sanitary
25 projects · most recent 07/06/2026
General Wiring
FiledStatusContractorScope
07/06/2026CompleteANCO ELECTL CONTCTNG INC—
02/19/2026CompleteGEMINI ELECTRIC CO., INC.—
01/22/2026CompleteGEMINI ELECTRIC CO., INC.—
01/22/2026CompleteGEMINI ELECTRIC CO., INC.—
07/17/2025Permit IssuedNYCOM ELECTRICAL CORP—
06/23/2025Permit IssuedREDD ELECTRICAL SVCS INCGeneral Wiring
03/31/2025CompleteANCO ELECTL CONTCTNG INC—
01/29/2025CompleteDNR ELECTRIC INCORPORATEGeneral Wiring
10/24/2024CompleteRICHARD NEU—
09/15/2024CompleteLIU ELECTRIC, LLC—
07/03/2024Permit IssuedSTANCO SYSTEM ELEC'L CONTGeneral Wiring
12/20/2023Permit IssuedRAIKOS ELECTRIC LLCGeneral Wiring
10/13/2023CompleteGEMINI ELECTRIC CO., INC.—
06/08/2023CompleteGEMINI ELECTRIC CO., INC.—
05/09/2023CompleteCHARAN ELEC'L ENTERP'S IN—
2 projects · most recent 10/16/2024
Steel Concrete Masonry
FiledStatusContractorScope
10/16/2024Permit IssuedNATIONAL ENVIROMENTAL SAFSteel, Concrete, Masonry
03/01/2024Permit IssuedNATIONAL ENVIROMENTAL SAF2 scope_items
1 project · most recent 12/27/2023
Fence
FiledStatusContractorScope
12/27/2023Permit IssuedNATIONAL ENVIROMENTAL SAFFence
▾Field Inspections (DOB CAP) — 15
DateTypeResultReport
09/02/2026Fail-Final SP - More than 10 Requested FloorsFailView ↗
09/01/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
07/30/2026Pass-Final CND-Occupancy InspectionPassView ↗
07/27/2026Fail-Final PL - Up to 3 Requested FloorsFailView ↗
02/05/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
01/27/2026Certified Gas-Gas-Piping-RoughingCertifiedView ↗
01/21/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
10/23/2025Fail-Final CND-Occupancy InspectionFailView ↗
08/27/2025Pass-Final PL - UndergroundPassView ↗
08/18/2025Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
08/18/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
08/05/2025Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
08/05/2025Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
12/24/2024Pass-Final PL - UndergroundPassView ↗
01/10/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 123
DateRequirementInspectorRole
08/18/2026Post-installed AnchorsAsma Hashmispecial
08/18/2026Fire-Resistant Penetrations and JointsAsma Hashmispecial
08/18/2026FinalAsma Hashmiprogress
08/18/2026Mechanical SystemsAsma Hashmispecial
02/06/2026Electrical energy consumptionJAMES WILSONenergy_progress
02/06/2026HVAC insulation and sealing JAMES WILSONenergy_progress
02/06/2026HVAC and service water heating equipment JAMES WILSONenergy_progress
02/06/2026Shutoff dampersJAMES WILSONenergy_progress
02/06/2026Fire-Resistant Penetrations and JointsJAMES WILSONspecial
02/06/2026FinalJAMES WILSONprogress
02/06/2026Mechanical SystemsJAMES WILSONspecial
02/06/2026Electrical motorsJAMES WILSONenergy_progress
02/06/2026HVAC and service water heating system controls JAMES WILSONenergy_progress
02/06/2026Maintenance informationJAMES WILSONenergy_progress
12/16/2025HVAC insulation and sealing JAMES WILSONenergy_progress
12/16/2025HVAC and service water heating equipment JAMES WILSONenergy_progress
12/16/2025Shutoff dampersJAMES WILSONenergy_progress
12/16/2025Electrical motorsJAMES WILSONenergy_progress
12/16/2025Maintenance informationJAMES WILSONenergy_progress
12/16/2025Electrical energy consumptionJAMES WILSONenergy_progress
12/16/2025HVAC and service water heating system controls JAMES WILSONenergy_progress
12/16/2025FinalJAMES WILSONprogress
12/16/2025Mechanical SystemsJAMES WILSONspecial
12/16/2025Fire-Resistant Penetrations and JointsJAMES WILSONspecial
08/28/2025Post-installed AnchorsAsma Hashmispecial
Latest 25 of 123.
▾Documents — 298 on file (BIS + DOB NOW)
▸Plans & Drawings31
▸DOB NOWPlans/Sketch24
08/28/2026M00935924-S1Request digital key ↗
08/28/2026M00935924-I1Request digital key ↗
08/28/2026M00980200-I1Request digital key ↗
Showing 3 of 24 on file for this type
▸DOB NOWPlans/Sketch - Plumbing3
08/15/2026M00345650-I1Request digital key ↗
08/15/2026M00345650-P2Request digital key ↗
08/15/2026M00345650-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Mechanical Systems3
08/27/2026M00345688-I1Request digital key ↗
08/15/2026M00345688-P1Request digital key ↗
08/15/2026M00345688-P2Request digital key ↗
▸DOB NOWPlans/Sketch - Structural1
09/04/2026M00345706-I1Request digital key ↗
▸Applications & Permits7
▸BISPLAN / WORK APPROVAL APPLICATION6
03/01/2024123922265Open ↗
01/30/2024123922265Open ↗
11/22/2023123922265Open ↗
Showing 3 of 6 on file for this type
▸BISWORK PERMIT APPLICATION1
06/05/2024123922265Open ↗
▸Zoning, Tax Lot & Property Records4
▸DOB NOWZD1: DOB Zoning Diagram3
08/26/2026M00692119-P1Open ↗
08/14/2026M00692119-I1Open ↗
08/13/2026M00692119-P2Open ↗
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED1
05/11/2020123922265Open ↗
▸Seals & Professional Certifications109
▸DOB NOWSpecial Inspector Seal & Signature40
09/01/2026M00692119-S1Open ↗
09/01/2026M00692119-S1Open ↗
09/01/2026M00692119-S1Open ↗
Showing 3 of 40 on file for this type
▸DOB NOWProgress Inspector Seal & Signature37
09/01/2026M00692119-S1Open ↗
09/01/2026M00692119-S1Open ↗
09/01/2026M00692119-S1Open ↗
Showing 3 of 37 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature31
09/02/2026M00665291-I1Open ↗
08/28/2026M00935924-S1Open ↗
08/28/2026M00935924-I1Open ↗
Showing 3 of 31 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION1
08/08/2012121173648Open ↗
▸Trade Schedules & Equipment1
▸BISFA - FDNY APPROVAL : FD-FAA1
12/03/2013121173648Open ↗
▸Safety & Tenant Protection3
▸DOB NOWNYCSCA - Approved Site Safety Plans3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸Environmental & Asbestos4
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form4
08/28/2026M00935924-I1Open ↗
08/15/2026M00345650-I1Open ↗
08/13/2026M00345706-I1Open ↗
Showing 3 of 4 on file for this type
▸Energy Compliance11
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
03/05/2024123922265Open ↗
01/26/2024123922265Open ↗
05/14/2020123922265Open ↗
▸BISINSULATION PLACEMENT & R VALUES1
04/04/2024123922265Open ↗
▸BISINTERIOR LIGHTING POWER1
04/04/2024123922265Open ↗
▸BISFENESTRATION AREAS1
04/04/2024123922265Open ↗
▸BISFENESTRATION U-FACTOR & PRODUCT RATING1
04/04/2024123922265Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
04/04/2024123922265Open ↗
▸BISLIGHTING CONTROLS1
04/04/2024123922265Open ↗
▸BISFENESTRATION AIR LEAKAGE1
04/04/2024123922265Open ↗
▸BISAIR SEALING AND INSULATION - VISUAL1
04/04/2024123922265Open ↗
▸Inspections & Test Reports13
▸BISTECHNICAL REPORT: RESPONSIBILITY4
03/05/2024123922265Open ↗
01/26/2024123922265Open ↗
01/04/2024123922265Open ↗
Showing 3 of 4 on file for this type
▸BISTR3: CONCRETE DESIGN MIX TECHNICAL REPORT1
04/04/2024123922265Open ↗
▸BISSTRUCTURAL STABILITY - ALTERATIONS OF EXISTING BUILDINGS1
04/04/2024123922265Open ↗
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)1
04/04/2024123922265Open ↗
▸BISFIRE-RESISTIVE RATED CONSTRUCTION1
04/04/2024123922265Open ↗
▸BISDIR-14 ID OF RESPONSIBILITY (TR1)1
04/04/2024123922265Open ↗
▸BISWALL PANELS, CURTAIN WALLS, AND VENEERS1
04/04/2024123922265Open ↗
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
07/07/2025123922265Open ↗
▸BISCONCRETE - CAST-IN-PLACE1
04/04/2024123922265Open ↗
▸BISTR2: CONCRETE FIELD TESTING TECHNICAL REPORT1
04/04/2024123922265Open ↗
▸Approvals, Objections & Sign-offs70
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter31
08/28/2026M00995597-I1Open ↗
08/27/2026M00345688-I1Open ↗
08/27/2026M00345688-P1Open ↗
Showing 3 of 31 on file for this type
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)26
08/27/2026M00345688-I1Open ↗
08/27/2026M00345688-P1Open ↗
08/26/2026M00692119-S2Open ↗
Showing 3 of 26 on file for this type
▸DOB NOWDEP Variance (V5) letter4
08/13/2026M00692119-S3Open ↗
08/13/2026M00692119-I1Open ↗
Showing 2 of 4 on file for this type
▸DOB NOWDesign Commission Sign Off City Owned (Exterior Work)4
08/13/2026M00692119-S1Open ↗
08/13/2026M00692119-S3Open ↗
08/13/2026M00692119-I1Open ↗
Showing 3 of 4 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
12/03/2013121173648Open ↗
▸BISDESIGN COMM. APPROVAL: CITY-OWNED PROPERTY (EXTERIOR WORK)1
05/18/2021123922265Open ↗
▸BISFINAL1
04/04/2024123922265Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
08/08/2012121173648Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
01/18/2024123922265Open ↗
▸Cost, Insurance & Ownership3
▸BISCOST AFFIDAVIT3
05/14/2020123922265Open ↗
12/03/2013121173648Open ↗
08/08/2012121173648Open ↗
▸Filing & Intake Forms6
▸BISADDITIONAL INFORMATION3
03/08/2024123922265Open ↗
01/12/2024123922265Open ↗
05/18/2021123922265Open ↗
▸BISEFILING COVER SHEET2
05/14/2020123922265Open ↗
05/11/2020123922265Open ↗
▸BISBOROUGH INTAKE FORM1
05/11/2020123922265Open ↗
▸Other Documents36
▸DOB NOWNYCSCA - BCC Plan Examination Transmittal15
08/26/2026M00692119-S2Open ↗
08/26/2026M00692119-S3Open ↗
08/26/2026M00692119-P1Open ↗
Showing 3 of 15 on file for this type
▸DOB NOWProof of Historic Building8
08/26/2026M00692119-P1Open ↗
08/15/2026M01278897-P1Open ↗
08/14/2026M00665291-I1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSite Survey: Initial3
08/26/2026M00692119-P1Open ↗
08/14/2026M00692119-I1Open ↗
08/13/2026M00692119-P2Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone3
08/26/2026M00692119-P1Open ↗
08/14/2026M00692119-I1Open ↗
Showing 2 of 3 on file for this type
▸DOB NOWPlot Diagram3
08/26/2026M00692119-P1Open ↗
08/14/2026M00692119-I1Open ↗
08/13/2026M00692119-P2Open ↗
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION2
03/05/2024123922265Open ↗
12/05/2023123922265Open ↗
▸DOB NOWAdjoining Owners Notification2
08/13/2026M00968683-I1Open ↗
08/13/2026M00935924-I1Open ↗