| Owner | Filings | Most Recent |
|---|---|---|
| Park Hill Tenants | 75 | 03/22/2026 |
| 70 East 96th St | 6 | 03/21/2026 |
| Brown, Harris, Stevens | 4 | 03/21/2026 |
| Floorever Carpets | 2 | 03/21/2026 |
| Edelman | 1 | 03/21/2026 |
| Herkimer Partners | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Lam & Lam Engineering | 2 | 08/13/2026 |
| Reaves Architecture | 3 | 08/06/2026 |
| Lam & Lam Designs | 1 | 01/15/2026 |
| The Vilnits Group | 1 | 01/10/2026 |
| Jong Hae Chang Architect | 2 | 01/02/2026 |
| Topos Designs | 1 | 10/30/2025 |
| Jillian Sheedy Architect | 1 | 02/19/2025 |
| McLaren Engineering Group | 3 | 12/06/2024 |
| Robert Papazian Architect | 1 | 05/14/2024 |
| Robert Bassolino | 1 | 04/18/2024 |
| Kane Architecture and Urban Design | 2 | 01/12/2024 |
| IP Group | 1 | 10/30/2023 |
| Jock Deboer, AIA | 1 | 10/06/2023 |
| Ayuso Architecture | 4 | 03/13/2023 |
| Ethelind Coblin Architect | 2 | 09/07/2022 |
| FL&M Engineering Design & Inspection | 3 | 06/29/2022 |
| Eisner Design | 2 | 06/29/2022 |
| Margaret Salamone, Architect | 2 | 12/08/2021 |
| Kay Leong Akerlof Architecture | 2 | 08/19/2021 |
| The Asimakis Group | 3 | 01/11/2021 |
| Nyron Hall Engineering | 1 | 12/06/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| East Coast Expediting | 3 | 03/21/2026 |
| A+ Expediting | 2 | 03/21/2026 |
| Idm Associates | 10 | 03/21/2026 |
| Jenny Flores Expediting | 2 | 03/21/2026 |
| Robert Papazian Architect | 2 | 03/21/2026 |
| Robert R Bisaccia | 2 | 03/21/2026 |
| Anthony Morali Architect | 4 | 03/21/2026 |
| BMB Building Consulting | 4 | 03/21/2026 |
| Code | 4 | 03/21/2026 |
| Mark Montoya | 2 | 03/21/2026 |
| Resolution Expediting | 4 | 03/21/2026 |
| KM Associates of New York | 3 | 03/21/2026 |
| MJB Consultants | 2 | 03/21/2026 |
| K & M Associates | 3 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Alan Construction | General Contractor | 4 | 07/08/2026 |
| Nail on the Head | General Contractor | 4 | 03/21/2026 |
| Apollo Plumbing & Heating | Plumbing | 3 | 07/08/2026 |
| SSL Construction | General Contractor | 3 | 03/21/2026 |
| Rambal Contractors | General Contractor | 3 | 03/21/2026 |
| Tap Plumbing | Plumbing | 2 | 08/21/2026 |
| Ari Group | General Contractor | 2 | 03/21/2026 |
| Design Renovate | General Contractor | 2 | 07/08/2026 |
| Hamilton Air Company | General Contractor | 2 | 03/21/2026 |
| Schnellbacher-Sendon Group* | General Contractor | 2 | 07/08/2026 |
| SJB Interiors | General Contractor | 2 | 03/21/2026 |
| Waxtel | General Contractor | 2 | 07/08/2026 |
| A & M Warshaw Plumbing & Heating | Plumbing | 2 | 07/08/2026 |
| DP FLYNN Plumbing & Heating | Plumbing | 2 | 07/08/2026 |
| Aqueduct Mechanical | Plumbing | 1 | 07/08/2026 |
| Artur Kalaj | General Contractor | 1 | 07/03/2026 |
| Azm Home Improvements | General Contractor | 1 | 04/09/2026 |
| Craft Design Construction | General Contractor | 1 | 04/09/2026 |
| Donato | Plumbing | 1 | 07/08/2026 |
| Century Electric Co | Electrical | 1 | 03/22/2026 |
| H & D Maintenance Co | General Contractor | 1 | 07/08/2026 |
| M&C Design Group | General Contractor | 1 | 07/08/2026 |
| Jorden-Ash Electric | Electrical | 1 | 03/22/2026 |
| Inner City Electrical Contractors | Electrical | 1 | 03/21/2026 |
| DPH Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| Express PL SWR & WTR A | Plumbing | 1 | 07/08/2026 |
| Everbright Electric | Electrical | 1 | 03/22/2026 |
| Genesis Plumbing and Heating | Plumbing | 1 | 07/08/2026 |
| Gregg NY Plumbing | Plumbing | 1 | 07/08/2026 |
| Magnetic Electrical Cons | Electrical | 1 | 03/21/2026 |
| Ket Electric | Electrical | 1 | 03/21/2026 |
| Lens Electric | Electrical | 1 | 03/21/2026 |
| WCK Electric | Electrical | 1 | 03/21/2026 |
| New Century Electrical Contracting | Electrical | 1 | 03/21/2026 |
| Update Systems Electrical | Electrical | 1 | 03/22/2026 |
| Vertex Electric | Electrical | 1 | 03/22/2026 |
| Joseph Weinstein Electric | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AA Building & Inspection | 1519 | 6 | 08/13/2026 |
| New Line Construction | 7226 | 2 | 01/15/2026 |
| The Vilnits Group | 1223 | 1 | 01/10/2026 |
| Ryan Special Engineering | 2018 | 1 | 01/02/2026 |
| M.G. McLaren Engineering | 2999 | 3 | 12/06/2024 |
| Robert Papazian Architect | 3491 | 1 | 05/14/2024 |
| Fsi Architecture | 354 | 2 | 01/23/2024 |
| AR Architect | 1171 | 1 | 01/12/2024 |
| IP Group | 2542 | 1 | 10/30/2023 |
| Jock Deboer, AIA - Sia | 7008 | 1 | 10/06/2023 |
| Ayuso Architecture | 7720 | 2 | 03/13/2023 |
| Jack Green Associates | 422 | 1 | 09/07/2022 |
| Katz Engineering | 238 | 1 | 12/08/2021 |
| Crosscheck Inspection Services | 544 | 3 | 01/11/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | Tap Plumbing | 08/20/2026 |
| DOB NOW | General Construction | Permit Issued | Design Renovate | 05/07/2026 |
| DOB NOW | General Construction | Permit Issued | Artur Kalaj | 04/27/2026 |
| DOB NOW | Plumbing | Permit Issued | Tap Plumbing | 03/20/2026 |
| DOB NOW | General Construction | Permit Issued | Design Renovate | 03/18/2026 |
| DOB NOW | Plumbing | Signed-off | Gregg NY Plumbing | 02/12/2026 |
| DOB NOW | General Construction | Signed-off | Azm Home Improvements | 02/03/2026 |
| DOB NOW | General Construction | Signed-off | Craft Design Construction | 11/24/2025 |
| DOB NOW | General Construction | Signed-off | H & D Maintenance Co | 03/03/2025 |
| DOB NOW | General Construction | Signed-off | Waxtel | 01/09/2025 |
| DOB NOW | General Construction | Signed-off | Waxtel | 10/15/2024 |
| DOB NOW | General Construction | Signed-off | Rambal Contractors | 05/31/2024 |
| DOB NOW | Structural | Signed-off | Schnellbacher-Sendon Group* | 05/22/2024 |
| DOB NOW | Plumbing | Signed-off | Apollo Plumbing & Heating | 04/18/2024 |
| DOB NOW | General Construction | Signed-off | Alan Construction | 04/17/2024 |
| DOB NOW | Plumbing | Signed-off | Express Plumbing SWR & WTR Ma | 12/14/2023 |
| DOB NOW | General Construction | Signed-off | SSL Construction | 12/13/2023 |
| DOB NOW | Structural | Signed-off | Schnellbacher-Sendon Group* | 08/03/2023 |
| DOB NOW | General Construction | Signed-off | Nail on the Head | 05/04/2023 |
| DOB NOW | Plumbing | Signed-off | Donato | 05/04/2023 |
| DOB NOW | General Construction | Signed-off | M&C Design Group | 01/19/2023 |
| DOB NOW | Plumbing | Signed-off | DPH Plumbing & Heating | 10/20/2022 |
| DOB NOW | Plumbing | Signed-off | Aqueduct Mechanical | 10/19/2022 |
| DOB NOW | General Construction | Signed-off | Nail on the Head | 10/18/2022 |
| DOB NOW | Mechanical Systems | Permit Issued | Hamilton Air Company | 10/14/2022 |
| DOB NOW | General Construction | Signed-off | Ari Group | 09/30/2022 |
| DOB NOW | Plumbing | Signed-off | Apollo Plumbing & Heating | 03/31/2022 |
| DOB NOW | Plumbing | Signed-off | DP FLYNN Plumbing & Heating | 03/28/2022 |
| DOB NOW | Plumbing | Signed-off | Apollo Plumbing & Heating | 03/04/2022 |
| DOB NOW | General Construction | Signed-off | Alan Construction | 02/18/2022 |
| DOB NOW | Plumbing | Signed-off | A & M Warshaw Plumbing & Heating | 09/14/2021 |
| DOB NOW | Plumbing | Signed-off | DP FLYNN Plumbing & Heating | 09/13/2021 |
| DOB NOW | General Construction | Signed-off | SJB Interiors | 08/17/2021 |
| DOB NOW | Plumbing | Signed-off | A & M Warshaw Plumbing & Heating | 09/21/2020 |
| DOB NOW | Plumbing | Signed-off | Genesis Plumbing and Heating | 07/09/2020 |
| BIS | OT | ISSUED | Jbuild | 09/03/2020 |
| BIS | OT | ISSUED | Idc Construction | 07/16/2020 |
| BIS | PL | RE-ISSUED | Hydrokinetic Plumbing & Heating I | 06/14/2019 |
| BIS | OT | ISSUED | Hudson Green Craft | 06/11/2019 |
| BIS | OT | ISSUED | Standard Environmental | 03/15/2019 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/13/2026 | Permit Issued | Tap Plumbing | Gas, Water/Sanitary |
| 01/15/2026 | Permit Issued | Tap Plumbing | Gas, Water/Sanitary |
| 07/08/2021 | Signed-off | DP FLYNN Plumbing & Heating | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/11/2026 | Complete | PK Electric | — |
| 05/13/2026 | Complete | Testa Electric Co | General Wiring |
| 05/06/2026 | Permit Issued | Titanium Electrical | General Wiring |
| 03/26/2026 | Permit Issued | Ket Electric | General Wiring |
| 02/04/2026 | Complete | Lens Electric | General Wiring |
| 01/06/2026 | Complete | Ket Electric | General Wiring |
| 12/12/2025 | Complete | V Electric NY | General Wiring |
| 09/17/2025 | Complete | Prudent Electric | General Wiring |
| 08/18/2025 | Complete | Testa Electric Co | General Wiring |
| 07/07/2025 | Complete | Power Surge Electric | General Wiring |
| 04/23/2025 | Complete | Horsepower Electric | General Wiring |
| 01/06/2025 | Complete | Errigal Electrical | General Wiring |
| 11/18/2024 | Complete | Horsepower Electric | General Wiring |
| 10/25/2024 | Complete | Joseph Weinstein Electric | General Wiring |
| 07/30/2024 | Complete | Denmar Electric | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/15/2026 | Permit Issued | Tap Plumbing | Tenant Protection Plan 72 Hour |
| 01/02/2026 | Signed-off | Gregg NY Plumbing | Tenant Protection Plan 72 Hour |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/27/2026 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 07/22/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/29/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/13/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/23/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/17/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/17/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/17/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 01/31/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/31/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/26/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/26/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/18/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/08/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/27/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/26/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/18/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/14/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/02/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/05/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/18/2026 | Fire-Resistant Penetrations and Joints | Younes Abouyaala | special |
| 08/18/2026 | Tenant Protection Plan Compliance | Younes Abouyaala | special |
| 08/13/2026 | Fire-Resistant Penetrations and Joints | Younes Abouyaala | special |
| 08/13/2026 | Final | NAVEEN KUMAR | progress |
| 08/13/2026 | Tenant Protection Plan Compliance | Younes Abouyaala | special |
| 08/13/2026 | Fire-Resistance Rated Construction | JEFFREY BELL | progress |
| 07/30/2026 | Fire-Resistant Penetrations and Joints | Younes Abouyaala | special |
| 07/30/2026 | Tenant Protection Plan Compliance | Younes Abouyaala | special |
| 12/30/2025 | Fire-Resistant Penetrations and Joints | AUGUSTINE OKUNDAYE | special |
| 12/30/2025 | Tenant Protection Plan Compliance | Younes Abouyaala | special |
| 12/19/2025 | Fire-Resistant Penetrations and Joints | William Ryan | special |
| 02/11/2025 | Final | Jillian Sheedy | progress |
| 02/11/2025 | Fire-Resistance Rated Construction | Howard Bader | progress |
| 12/11/2024 | Concrete - Cast-In-Place | Jeremy Billig | special |
| 12/11/2024 | Final | SPIRO ANXHARA | progress |
| 12/11/2024 | Structural Steel - Welding | Jeremy Billig | special |
| 12/11/2024 | Structural Stability – Alterations of existing buildings | Jeremy Billig | special |
| 12/11/2024 | Tenant Protection Plan Compliance | James Cicalo | special |
| 01/23/2024 | Structural Stability – Alterations of existing buildings | Jeremy Billig | special |
| 01/23/2024 | Structural Steel - Welding | Jeremy Billig | special |
| 01/23/2024 | Concrete - Cast-In-Place | Jeremy Billig | special |
| 01/23/2024 | Tenant Protection Plan Compliance | James Cicalo | special |
| 01/18/2024 | Final | SPIRO ANXHARA | progress |
| 11/26/2023 | Interior lighting power | ANGEL ROJAS | energy_progress |
| 11/26/2023 | Fire-Resistant Penetrations and Joints | ANGEL ROJAS | special |