| Owner | Filings | Most Recent |
|---|---|---|
| NEW YORK CITY HOUSING AUTHORITY | 14 | 03/21/2026 |
| NYC Housing Authority | 5 | 03/21/2026 |
| FAIRSTEAD MANAGEMENT | 4 | 04/09/2026 |
| NYC PACT PRESERVATION PARTNERS | 3 | 09/13/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| SLM ARCHITECTURE, P.C. | 2 | 07/08/2026 |
| DAGHER ENGINEERING PLLC | 6 | 03/05/2026 |
| G3 ARCHITECTURE INTERIORS PLANNING | 1 | 05/13/2025 |
| ASHRAF CORP | 1 | 04/03/2025 |
| SOCOTEC, INC. | 1 | 03/08/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| RIGGING CONSULTANTS | 2 | 03/21/2026 |
| METROPOLIS GROUP INC | 14 | 03/21/2026 |
| CONVERSANO ASSOCIATES, INC. | 1 | 03/21/2026 |
| BARNWELL CONSULTANTS | 1 | 03/21/2026 |
| KD DESIGNS | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| FSC D&C LLC | General Contractor | 6 | 07/08/2026 |
| ARSENAL SCAFFOLD INC | General Contractor | 3 | 07/08/2026 |
| LS GENERAL CORP | General Contractor | 2 | 04/09/2026 |
| DUAL FUEL PLUBING & HTING | Plumbing | 2 | 06/28/2026 |
| DUAL FUEL COMPANY LLC | General Contractor | 1 | 04/09/2026 |
| PYRAMID ETC COMPANIES, LL | General Contractor | 1 | 04/09/2026 |
| A & E PLUMBING CORP | Plumbing | 1 | 07/08/2026 |
| SUPREME MECH NYC LLC | Plumbing | 1 | 07/08/2026 |
| LET IT GROW, INCORPORATED | General Contractor | 1 | 04/09/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| METRIC CONSULTING AND INS | 1803 | 10 | 07/08/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sidewalk Shed | Signed-off | ARSENAL SCAFFOLD INC | 06/09/2026 |
| DOB NOW | General Construction | Signed-off | FSC D&C LLC | 03/18/2026 |
| DOB NOW | General Construction | Signed-off | LS GENERAL CORP | 02/10/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | LUAN SELA | 02/10/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | LUAN SELA | 01/06/2026 |
| DOB NOW | General Construction | Signed-off | LS GENERAL CORP | 12/15/2025 |
| DOB NOW | Boiler Equipment | Signed-off | DUAL FUEL PLUBING & HTING | 07/22/2025 |
| DOB NOW | General Construction | Permit Issued | LET IT GROW, INCORPORATED | 06/17/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | ARSENAL SCAFFOLD INC | 04/04/2025 |
| DOB NOW | General Construction | Signed-off | FSC D&C LLC | 03/17/2025 |
| DOB NOW | Boiler Equipment | Signed-off | SUPREME MECH NYC LLC | 03/07/2025 |
| DOB NOW | Mechanical Systems | Signed-off | DUAL FUEL COMPANY LLC | 01/22/2025 |
| DOB NOW | Boiler Equipment | Signed-off | DUAL FUEL PLUBING & HTING | 01/16/2025 |
| DOB NOW | Plumbing | Signed-off | A & E PLUMBING CORP | 04/01/2024 |
| DOB NOW | Mechanical Systems | Signed-off | PYRAMID ETC COMPANIES, LL | 03/29/2024 |
| DOB NOW | General Construction | Signed-off | FSC D&C LLC | 03/22/2024 |
| DOB NOW | General Construction | Signed-off | FSC D&C LLC | 01/17/2024 |
| BIS | BL | ISSUED | ACE CONTRACTING, INC | 04/04/2017 |
| BIS | PL | ISSUED | ACE CONTRACTING, INC | 10/28/2016 |
| BIS | BL | ISSUED | ACE CONTRACTING, INC | 10/28/2016 |
| BIS | EQ | ISSUED | POWERS BRIDGING & SCAFFOLDING | 04/05/2007 |
| BIS | OT | ISSUED | BRI-DEN CONST CO INC | 04/04/2007 |
| BIS | EQ | ISSUED | BRI-DEN CONST CO INC | 04/04/2007 |
| BIS | EQ | ISSUED | BRI-DEN CONST CO INC | 01/11/2007 |
| BIS | EQ | ISSUED | POWERS BRIDGING & SCAFFOLDING | 01/06/2007 |
| BIS | EQ | ISSUED | POWERS BRIDGING & SCAFFOLDING | 04/13/2006 |
| BIS | EQ | ISSUED | BRI-DEN CONST CO INC | 01/23/2006 |
| BIS | OT | ISSUED | BRI-DEN CONST CO INC | 01/23/2006 |
| BIS | EQ | ISSUED | POWERS BRIDGING & SCAFFOLDING | 01/18/2006 |
| BIS | EQ | ISSUED | BRI-DEN CONST CORP | 01/12/2006 |
| BIS | EQ | ISSUED | POWERS BRIDGING & SCAFFOLDING | 12/27/2005 |
| BIS | EQ | ISSUED | ROCKLEDGE SCAFFOLD CORP | 01/10/2003 |
| BIS | EQ | ISSUED | ROCKLEDGE SCAFFOLD CORP | 06/28/2002 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/05/2026 | Complete | SOLAS ELECTRICAL CORP | — |
| 12/20/2025 | Complete | ATLAS-ACON ELEC. SERVICE | General Wiring |
| 01/26/2025 | Permit Issued | ITKIN ELECTRIC CORP. | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/13/2025 | Permit Issued | LET IT GROW, INCORPORATED | 1 scope_items |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/03/2025 | Signed-off | ARSENAL SCAFFOLD INC | Sidewalk Shed |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/13/2026 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| 03/26/2026 | No Access-Final Boiler Equipment Inspection | No Access | View ↗ |
| 06/12/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/10/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/10/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 03/08/2024 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 08/28/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/02/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/24/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/15/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/12/2026 | Tenant Protection Plan Compliance | SAMI HAJJAR P.E | special |
| 04/12/2026 | Fenestration and door U-factor and product ratings | SAMI HAJJAR P.E | energy_progress |
| 04/12/2026 | Exterior lighting power | SAMI HAJJAR P.E | energy_progress |
| 04/12/2026 | Lighting controls | SAMI HAJJAR P.E | energy_progress |
| 04/12/2026 | Vestibules | SAMI HAJJAR P.E | energy_progress |
| 04/12/2026 | Fenestration air leakage | SAMI HAJJAR P.E | energy_progress |
| 04/12/2026 | Air barrier - visual inspection | SAMI HAJJAR P.E | energy_progress |
| 04/12/2026 | Interior lighting power | SAMI HAJJAR P.E | energy_progress |
| 04/12/2026 | Lighting in dwelling units | SAMI HAJJAR P.E | energy_progress |
| 04/12/2026 | Final | SAMI HAJJAR P.E | progress |
| 04/12/2026 | Energy Code Compliance Inspections | SAMI HAJJAR P.E | progress |
| 03/06/2026 | Tenant Protection Plan Compliance | SAMI HAJJAR P.E | special |
| 03/06/2026 | HVAC-R and service water heating system controls | SAMI HAJJAR P.E | energy_progress |
| 03/06/2026 | HVAC-R and service water piping design and insulation | SAMI HAJJAR P.E | energy_progress |
| 03/06/2026 | HVAC-R and service water heating equipment | SAMI HAJJAR P.E | energy_progress |
| 03/06/2026 | Heating Systems | SAMI HAJJAR P.E | special |
| 03/06/2026 | Maintenance information | SAMI HAJJAR P.E | energy_progress |
| 03/03/2026 | HVAC-R and service water heating system controls | SAMI HAJJAR P.E | energy_progress |
| 03/03/2026 | Heating Systems | SAMI HAJJAR P.E | special |
| 03/03/2026 | Tenant Protection Plan Compliance | SAMI HAJJAR P.E | special |
| 03/03/2026 | HVAC-R and service water piping design and insulation | SAMI HAJJAR P.E | energy_progress |
| 03/03/2026 | HVAC-R and service water heating equipment | SAMI HAJJAR P.E | energy_progress |
| 03/03/2026 | Maintenance information | SAMI HAJJAR P.E | energy_progress |
| 02/21/2025 | Final | SAMI HAJJAR P.E | progress |
| 02/21/2025 | Tenant Protection Plan Compliance | SAMI HAJJAR P.E | special |