| Owner | Filings | Most Recent |
|---|---|---|
| VORNADO REALTY TRUST | 753 | 09/22/2026 |
| 962 THIRD AVENUE ASSOCIATES | 80 | 07/08/2026 |
| 555 1290 HOLDINGS, LLC | 1 | 03/22/2026 |
| 555 1290 HOLDINGS,LLC VOR | 4 | 03/22/2026 |
| COLGATE RESTORATION | 5 | 03/22/2026 |
| VORNADO OFFICE MANAGEMENT, LLC | 635 | 03/22/2026 |
| W5 GROUP | 1 | 03/22/2026 |
| JAMESTOWN 1290 L P | 67 | 03/22/2026 |
| 1290 PARTNERS | 51 | 03/22/2026 |
| TRANS WORLD MUSIC CORP | 2 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| AMA CONSULTING ENGINEERS, PC | 17 | 09/14/2026 |
| TPG ARCHITECTURE, LLP | 8 | 08/25/2026 |
| ROBERT DERECTOR ASSOCIATES | 63 | 08/19/2026 |
| TED MOUDIS ASSOCIATES | 4 | 08/19/2026 |
| PRUDIGM ENGINEERING LLC | 5 | 08/05/2026 |
| GOLDMAN COPELAND ASSOCIATES | 48 | 07/23/2026 |
| JOHN F. GIUSEFFI, ARCHITECT, PC | 10 | 07/02/2026 |
| GILSANZ MURRAY STEFICEK LLP | 23 | 06/23/2026 |
| GENSLER | 16 | 06/22/2026 |
| MG ENGINEERING D.P.C. | 15 | 06/22/2026 |
| MARIA SFINAROLAKIS-KOKOLIS | 1 | 05/21/2026 |
| CFS ENGINEERING, DPC | 16 | 05/06/2026 |
| ASDA ARCHITECTURE + DESIGN | 25 | 04/29/2026 |
| STUDIOS ARCHITECTURE | 3 | 03/30/2026 |
| CONAPAC SERVICES, DBA | 8 | 03/13/2026 |
| LEON SKVIRSKY PE | 1 | 03/13/2026 |
| EMPORIUM DESIGN LLC | 1 | 02/17/2026 |
| FOGARTY FINGER ARCHITECTURE PLLC | 12 | 02/13/2026 |
| WRG ENGINEERING, P.C. | 1 | 02/02/2026 |
| COSENTINI ASSOCIATES | 27 | 01/15/2026 |
| DESIGN REPUBLIC | 14 | 12/17/2025 |
| ACTIVE DESIGN GROUP ENGINEERING | 1 | 12/16/2025 |
| CCS ARCHITECTURE | 2 | 12/11/2025 |
| JMV CONSULTING ENGINEERING | 4 | 11/25/2025 |
| IW ARCHITECTURE, PLLC | 2 | 09/24/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| A1 EXPEDITING SERVICE CORP. | 81 | 03/21/2026 |
| PROJECT EXPEDITERS CONSULTING CO. | 24 | 03/21/2026 |
| ARCHETYPE CONSULTANTS | 392 | 03/21/2026 |
| OUTSOURCE CONSULTANTS, INC. | 30 | 03/21/2026 |
| GREEN STUDIO | 4 | 03/21/2026 |
| SIGNS CAD | 4 | 03/21/2026 |
| NEW APPROACH CONSULTING | 12 | 03/21/2026 |
| VALERIO ARCHITECTS | 8 | 03/21/2026 |
| MAGNUM OPUS ARCHITECTURE | 5 | 03/21/2026 |
| BUILDING BROTHERS | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| PAVARINI MCGOVERN LLC | General Contractor | 39 | 07/08/2026 |
| STRUCTURE TONE, LLC | General Contractor | 37 | 07/09/2026 |
| CLUNE CONSTRUCTION CO LP | General Contractor | 27 | 07/08/2026 |
| W5 GROUP LLC | General Contractor | 20 | 07/08/2026 |
| JOHN GALLIN & SON, INC | General Contractor | 18 | 07/14/2026 |
| JAMES E FITZGERALD INC | General Contractor | 17 | 08/30/2026 |
| TRI-STAR CONSTRUCTION CORP | General Contractor | 16 | 07/08/2026 |
| BENCHMARK BUILDERS LLC | General Contractor | 15 | 07/08/2026 |
| JRM CONSTRUCTION MGMT LLC | General Contractor | 13 | 09/17/2026 |
| COLGATE RESTORATION CORP | General Contractor | 13 | 07/08/2026 |
| ABCO-PEERLESS SPRKLR CORP | Fire Protection | 12 | 08/30/2026 |
| PAR PLUMBING CO., INC | Plumbing | 11 | 07/23/2026 |
| SIRINA FIRE PROT CORP | Fire Protection | 9 | 07/25/2026 |
| S.B.A. PLUMBING CORP | Plumbing | 9 | 07/08/2026 |
| ROBERT B. SAMUELS, INC. | Electrical | 9 | 03/22/2026 |
| AGGRESSIVE FIRE PROT LLC | Fire Protection | 8 | 07/08/2026 |
| JKT CONSTRUCTION INC | General Contractor | 7 | 07/08/2026 |
| PAR FIRE PROTECTION LLC | Fire Protection | 7 | 07/22/2026 |
| SAFWAY ATLANTIC, LLC | General Contractor | 7 | 07/08/2026 |
| LAWRENCE J. LEVINE | Fire Protection | 6 | 03/21/2026 |
| KG SPRINKLER CORP | Fire Protection | 6 | 07/08/2026 |
| TITAN INDUSTRIAL SVC CORP | General Contractor | 6 | 07/08/2026 |
| 4IR IDEAL INC | General Contractor | 6 | 07/08/2026 |
| VANGUARD CONSTRUCTION AND | General Contractor | 6 | 06/27/2026 |
| DONATO PLUMBING GROUP INC | Plumbing | 6 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| OUTSOURCE SPECIAL INSPECT | 2827 | 27 | 09/14/2026 |
| HANSEN ENGINEERING PC | 8174 | 48 | 08/25/2026 |
| MILROSE CONSULTANTS LLC | 2003 | 8 | 08/19/2026 |
| PRUDIGM ENGINEERING LLCU | 4304 | 6 | 08/05/2026 |
| AK ENGINEERING PC | 678 | 56 | 07/02/2026 |
| GILSANZ MURRAY STEFICEK | 240 | 2 | 05/27/2026 |
| ALAN MARGOLIN & ASSOC | 423 | 24 | 05/06/2026 |
| ASDA ARCHITECTURE + DESIG | 2015 | 10 | 04/29/2026 |
| SKYLINE ENGINEERING, PLLC | 267 | 15 | 01/15/2026 |
| ADVANCED ENGINEERING & IN | 1224 | 1 | 12/16/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | JRM CONSTRUCTION MGMT LLC | 09/16/2026 |
| DOB NOW | General Construction | Permit Issued | JAMES E FITZGERALD INC | 08/28/2026 |
| DOB NOW | Sprinklers | Permit Issued | ABCO-PEERLESS SPRKLR CORP | 08/27/2026 |
| DOB NOW | Plumbing | Permit Issued | BYPASS MECHANICAL CORP | 08/26/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | JAMES E FITZGERALD INC | 08/24/2026 |
| DOB NOW | Plumbing | Permit Issued | PARKVIEW P&H INC | 08/05/2026 |
| DOB NOW | Sprinklers | Permit Issued | SIRINA FIRE PROT CORP | 07/24/2026 |
| DOB NOW | Plumbing | Permit Issued | PAR PLUMBING CO., INC | 07/22/2026 |
| DOB NOW | Sprinklers | Permit Issued | PAR FIRE PROTECTION LLC | 07/21/2026 |
| DOB NOW | Standpipe | Permit Issued | RRP PLUMBING CORP | 07/14/2026 |
| DOB NOW | Plumbing | Permit Issued | A&A PLUMBING CORP | 07/14/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | JOHN GALLIN & SON, INC | 07/13/2026 |
| DOB NOW | Sprinklers | Permit Issued | BEDROCK MECHANICAL INC | 07/09/2026 |
| DOB NOW | Standpipe | Permit Issued | BEDROCK MECHANICAL INC | 07/09/2026 |
| DOB NOW | Sprinklers | Permit Issued | RRP PLUMBING CORP | 07/09/2026 |
| DOB NOW | Plumbing | Permit Issued | RRP PLUMBING CORP | 07/09/2026 |
| DOB NOW | Plumbing | Permit Issued | RRP PLUMBING CORP | 07/09/2026 |
| DOB NOW | General Construction | Permit Issued | JOHN GALLIN & SON, INC | 07/08/2026 |
| DOB NOW | Plumbing | Permit Issued | RRP PLUMBING CORP | 07/07/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | STRUCTURE TONE, LLC | 07/07/2026 |
| DOB NOW | Sprinklers | Permit Issued | RRP PLUMBING CORP | 07/07/2026 |
| DOB NOW | Plumbing | Permit Issued | BYPASS MECHANICAL CORP | 07/06/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | JOHN GALLIN & SON, INC | 07/01/2026 |
| DOB NOW | Standpipe | Permit Issued | CAPITOL FIRE SPRINKLER CO | 07/01/2026 |
| DOB NOW | Sprinklers | Permit Issued | CAPITOL FIRE SPRINKLER CO | 06/30/2026 |
| DOB NOW | Sprinklers | Permit Issued | CAPITOL FIRE SPRINKLER CO | 06/30/2026 |
| DOB NOW | General Construction | Permit Issued | STRUCTURE TONE, LLC | 06/26/2026 |
| DOB NOW | Structural | Permit Issued | STRUCTURE TONE, LLC | 06/25/2026 |
| DOB NOW | General Construction | Permit Issued | VANGUARD CONSTRUCTION AND | 06/23/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | CLUNE CONSTRUCTION CO LP | 06/18/2026 |
| DOB NOW | General Construction | Permit Issued | CLUNE CONSTRUCTION CO LP | 06/18/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | CLUNE CONSTRUCTION CO LP | 06/16/2026 |
| DOB NOW | General Construction | Permit Issued | CLUNE CONSTRUCTION CO LP | 06/16/2026 |
| DOB NOW | General Construction | Permit Issued | JOHN GALLIN & SON, INC | 06/12/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | JOHN GALLIN & SON, INC | 06/12/2026 |
| DOB NOW | General Construction | Permit Issued | JOHN GALLIN & SON, INC | 06/10/2026 |
| DOB NOW | Plumbing | Permit Issued | S.B.A. PLUMBING CORP | 06/04/2026 |
| DOB NOW | Structural | Permit Issued | W5 GROUP LLC | 06/01/2026 |
| DOB NOW | General Construction | Permit Issued | W5 GROUP LLC | 06/01/2026 |
| DOB NOW | Sprinklers | Permit Issued | CROSSFIELD PLBG.&HTG.CORP | 05/21/2026 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/05/2026 | Permit Issued | YAD REALTY MANAGEMENT LLC | Air Conditioning Systems, Heating Systems, Ventilation Systems | Cooling Climatemaster SBH096 93,600 BTU · Wshp ×2 Daikin WSLH096 87,882 BTU · Wshp ×2 |
| 07/02/2026 | Permit Issued | STRUCTURE TONE, LLC | Air Conditioning Systems | Cooling Above Air AWC024S 1,200 CFM ×2 |
| 06/25/2026 | Permit Issued | JOHN GALLIN & SON, INC | Air Conditioning Systems, Ventilation Systems | |
| 06/22/2026 | Permit Issued | VANGUARD CONSTRUCTION AND | Air Conditioning Systems, Heating Systems, Ventilation Systems | |
| 06/10/2026 | Permit Issued | JOHN GALLIN & SON, INC | Ventilation Systems | Ventilation Titus N/A 50 CFM · Exhaust Fan ×1 |
| 01/15/2026 | Signed-off | VERICON CONSTRUCTION CO | Air Conditioning Systems, Heating Systems | Cooling Water Furnace VERSATEC 700 VARIABLE SPEED HORIZONTAL (VV) 048 45,760 BTU · Wshp ×11 VERSATEC 700 VARIABLE SPEED HORIZONTAL (VV) 072 69,340 BTU · Wshp ×4 VERSATEC 700 VARIABLE SPEED HORIZONTAL (VV) 036 36,310 BTU · Wshp ×2 VERSATEC 700 VARIABLE SPEED HORIZONTAL (VV) 120 98,180 BTU · Wshp ×2 VERSATEC 700 VARIABLE SPEED HORIZONTAL (VV) 024 24,060 BTU · Wshp ×1 VERSATEC 700 VARIABLE SPEED HORIZONTAL (VV) 060 54,850 BTU · Wshp ×1 UVH048ER471DBWEN0B32SSC 45,290 BTU · Wshp ×8 UVH072EL471DBWEN0B32SSC 98,180 BTU · Wshp ×8 UVH048EL471DBWEN0B32SSC 45,760 BTU · Wshp ×7 UVH024EL471DBWEN0B32SSC 24,060 BTU · Wshp ×2 UVH036EL471DBWEN0B32SSC 28,620 BTU · Wshp ×2 UVH036ER471DBWEN0B32SSC 36,600 BTU · Wshp ×2 UVH048EL471DBWENOB32SSC 40,420 BTU · Wshp ×2 UVH060EL471DBWEN0B32SSC 54,850 BTU · Wshp ×2 UVH072ER471DBWEN0B32SSC 69,340 BTU · Wshp ×2 UVH120EL475DBWEN2B32SSB 98,180 BTU · Wshp ×2 Task TGC023WC 24,000 BTU · Split System ×1 TGC033WC-30K 30,000 BTU · Split System ×1 TGE021-24K-WALH 24,000 BTU · Wshp ×2 TGE031-30K-WALH 30,000 BTU · Wshp ×2 Heating Water Furnace VERSATEC 700 VARIABLE SPEED HORIZONTAL (VV) 048 62,690 BTU · Wshp ×9 VERSATEC 700 VARIABLE SPEED HORIZONTAL (VV) 072 86,120 BTU · Wshp ×4 VERSATEC 700 VARIABLE SPEED HORIZONTAL (VV) 036 45,870 BTU · Wshp ×2 VERSATEC 700 VARIABLE SPEED HORIZONTAL (VV) 120 103,510 BTU · Wshp ×2 VERSATEC 700 VARIABLE SPEED HORIZONTAL (VV) 024 30,480 BTU · Wshp ×1 VERSATEC 700 VARIABLE SPEED HORIZONTAL (VV) 060 72,580 BTU · Wshp ×1 UVH048ER471DBWEN0B32SSC 62,210 BTU · Wshp ×10 UVH048EL471DBWEN0B32SSC 62,690 BTU · Wshp ×8 UVH072EL471DBWEN0B32SSC 86,120 BTU · Wshp ×6 UVH120EL475DBWEN2B32SSB 103,510 BTU · Wshp ×4 UVH024EL471DBWEN0B32SSC 30,480 BTU · Wshp ×2 UVH036EL471DBWEN0B32SSC 36,890 BTU · Wshp ×2 UVH036ER471DBWEN0B32SSC 45,870 BTU · Wshp ×2 UVH060EL471DBWEN0B32SSC 72,580 BTU · Wshp ×2 UVH072ER471DBWEN0B32SSC 86,120 BTU · Wshp ×2 |
| 12/17/2025 | Signed-off | STRUCTURE TONE, LLC | Air Conditioning Systems | Cooling Vertiv PX011UW 32,000 BTU · Crac Unit ×1 Water Furnace VERSATEC 16,680 BTU ×1 |
| 11/25/2025 | Signed-off | QUINN & FEINER SVC CO.INC | Heating and Air Conditioning Systems | Heat / Cool Daikin RWEQ120TBYDA 10 tons · Vrf Outdoor ×2 |
| 04/21/2025 | Permit Issued | STRUCTURE TONE, LLC | Air Conditioning Systems | Cooling Florida Heat Pump CL024 800 CFM · Wshp ×3 |
| 05/28/2021 | — | — | Air Conditioning Systems, Heating Systems | Cooling Florida Heat Pump LV042 39,200 BTU · Wshp ×5 LV070 64,300 BTU · Wshp ×3 EC096 96,700 BTU · Wshp ×2 LV048 44,600 BTU · Wshp ×2 LV024 24,400 BTU · Wshp ×1 LV030 28,300 BTU · Wshp ×1 LV036 37,600 BTU · Wshp ×1 LV060 58,000 BTU · Wshp ×1 LV096 94,500 BTU · Wshp ×1 Heating Florida Heat Pump LV042 46,900 BTU · Wshp ×5 EC096 114,800 BTU · Wshp ×3 LV070 77,900 BTU · Wshp ×3 LV048 60,500 BTU · Wshp ×2 LV030 33,700 BTU · Wshp ×1 LV036 41,200 BTU · Wshp ×1 LV060 72,600 BTU · Wshp ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/14/2026 | Permit Issued | PAR FIRE PROTECTION LLC | Sprinkler System |
| 08/19/2026 | Permit Issued | ABCO-PEERLESS SPRKLR CORP | 15 heads |
| 07/23/2026 | Permit Issued | SIRINA FIRE PROT CORP | Sprinkler System |
| 07/09/2026 | Permit Issued | RRP PLUMBING CORP | 301 heads, 2 outlets |
| 07/06/2026 | Signed-off | BEDROCK MECHANICAL INC | — |
| 06/25/2026 | Permit Issued | BEDROCK MECHANICAL INC | — |
| 06/25/2026 | Permit Issued | BEDROCK MECHANICAL INC | 2 outlets |
| 06/25/2026 | Permit Issued | RRP PLUMBING CORP | 330 heads |
| 06/22/2026 | Permit Issued | A PLUS PLUMBING CORP | 197 heads |
| 06/10/2026 | Permit Issued | RRP PLUMBING CORP | Sprinkler System |
| 05/06/2026 | Signed-off | PREFERRED SPKLR AND MECH | 427 heads |
| 04/02/2026 | Permit Issued | A PLUS PLUMBING CORP | 5 heads |
| 03/25/2026 | Permit Issued | CAPITOL FIRE SPRINKLER CO | 229 heads |
| 03/24/2026 | Permit Issued | CAPITOL FIRE SPRINKLER CO | 205 heads, 1 outlets |
| 01/15/2026 | Signed-off | SIRINA FIRE PROT CORP | 1,023 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/14/2026 | Permit Issued | PAR PLUMBING CO., INC | Water/Sanitary |
| 08/19/2026 | — | — | — |
| 08/05/2026 | Permit Issued | CROSSFIELD PLBG.&HTG | Water/Sanitary |
| 07/23/2026 | Permit Issued | S.B.A. PLUMBING CORP | Gas, Water/Sanitary |
| 07/15/2026 | Permit Issued | PARKVIEW P&H INC | Water/Sanitary |
| 06/25/2026 | Permit Issued | A&A PLUMBING CORP | Water/Sanitary |
| 06/25/2026 | Permit Issued | RRP PLUMBING CORP | Water/Sanitary |
| 06/22/2026 | Permit Issued | A PLUS PLUMBING CORP | Gas, Storm, Water/Sanitary |
| 06/10/2026 | Permit Issued | RRP PLUMBING CORP | Water/Sanitary |
| 05/06/2026 | Signed-off | PAR PLUMBING CO., INC | Water/Sanitary |
| 04/02/2026 | — | — | — |
| 03/24/2026 | Permit Issued | PLUMBING WORKS CORP | Water/Sanitary |
| 03/24/2026 | Permit Issued | PLUMBING WORKS CORP | Water/Sanitary |
| 03/24/2026 | — | — | — |
| 01/15/2026 | Signed-off | M&T PLBG AND HTG CO., INC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/10/2026 | Permit Issued | RONAN ELECTRICAL LLC | — |
| 07/06/2026 | Permit Issued | A2K ELECTRIC CORP | General Wiring |
| 06/25/2026 | Permit Issued | MRD ELEC'L SERVICES, INC | General Wiring |
| 05/12/2026 | Permit Issued | P.L. ELEC'L CONTR'G CORP | General Wiring |
| 04/09/2026 | Permit Issued | S & D ELECTRIC NY CORP | General Wiring |
| 04/09/2026 | Complete | S & D ELECTRIC NY CORP | General Wiring |
| 02/18/2026 | Permit Issued | POLO ELECTRIC CORP. D/B/A | General Wiring |
| 02/12/2026 | Permit Issued | METROPOLIS ELECTRIC CORP | General Wiring |
| 12/18/2025 | Permit Issued | RIGID ELECTRIC, INC. | General Wiring |
| 10/31/2025 | Complete | TUXEDO ELEC'L CONTR'G INC | — |
| 10/24/2025 | Complete | ROBERT B SAMUELS, INC | General Wiring |
| 07/16/2025 | Complete | SIGNS CAD CORP | — |
| 07/02/2025 | Complete | M.C. ELECTRICAL NY INC | General Wiring |
| 06/17/2025 | Complete | BORRELLI ELECTRIC INC | General Wiring |
| 06/16/2025 | Complete | ROBERT B SAMUELS, INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/23/2026 | Permit Issued | SIRINA FIRE PROT CORP | 1 scope_items |
| 06/23/2026 | Permit Issued | STRUCTURE TONE, LLC | Steel |
| 06/22/2026 | Permit Issued | VANGUARD CONSTRUCTION AND | Steel, Concrete, Masonry |
| 03/16/2026 | Permit Issued | STRUCTURE TONE, LLC | Steel, Concrete |
| 01/15/2026 | Signed-off | SIRINA FIRE PROT CORP | Steel |
| 01/21/2025 | Signed-off | TITAN INDUSTRIAL SVC CORP | Steel, Concrete |
| 06/22/2021 | — | — | Steel, Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/16/2025 | Permit Issued | SPYDER WINDOW CLEANING IN | Suspended Scaffold (SC) |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/25/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/11/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/07/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/30/2026 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 07/30/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/28/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/17/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/15/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/15/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/15/2026 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 07/09/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/09/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/03/2026 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 06/01/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 06/01/2026 | Pass-Final SP - More than 10 Requested Floors | Pass | View ↗ |
| 05/26/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/20/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/15/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 05/15/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/13/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/12/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/06/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 04/20/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/02/2026 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 04/02/2026 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/15/2026 | Post-installed Anchors | JONAR MADRIAGA | special |
| 09/15/2026 | Sprinkler Systems | JONAR MADRIAGA | special |
| 09/15/2026 | Fire-Resistant Penetrations and Joints | JONAR MADRIAGA | special |
| 09/02/2026 | Post-installed Anchors | JONAR MADRIAGA | special |
| 09/02/2026 | Sprinkler Systems | JONAR MADRIAGA | special |
| 09/02/2026 | Fire-Resistant Penetrations and Joints | JONAR MADRIAGA | special |
| 08/11/2026 | Interior lighting power | Benjamin Plotnick | energy_progress |
| 08/11/2026 | Lighting controls | Benjamin Plotnick | energy_progress |
| 08/11/2026 | Duct leakage testing, insulation and design | Benjamin Plotnick | energy_progress |
| 08/07/2026 | Fire-Resistant Penetrations and Joints | Naeem Anwar | special |
| 07/16/2026 | Sprinkler Systems | Benjamin Plotnick | special |
| 07/16/2026 | Fire-Resistant Penetrations and Joints | Benjamin Plotnick | special |
| 07/16/2026 | Mechanical Systems | Benjamin Plotnick | special |
| 07/16/2026 | Post-installed Anchors | Benjamin Plotnick | special |
| 07/16/2026 | Final | Benjamin Plotnick | progress |
| 07/16/2026 | Fire-Resistant Penetrations and Joints | Benjamin Plotnick | special |
| 07/16/2026 | Final | Benjamin Plotnick | progress |
| 07/07/2026 | Sprinkler Systems | Ryan Hansen | special |
| 07/06/2026 | HVAC-R and service water piping design and insulation | JONAR MADRIAGA | energy_progress |
| 07/06/2026 | HVAC-R and service water heating equipment | JONAR MADRIAGA | energy_progress |
| 07/06/2026 | HVAC-R and service water heating system controls | JONAR MADRIAGA | energy_progress |
| 07/06/2026 | Post-installed Anchors | JONAR MADRIAGA | special |
| 07/06/2026 | Fire-Resistant Penetrations and Joints | JONAR MADRIAGA | special |
| 07/02/2026 | Post-installed Anchors | Ari Kamo | special |
| 07/02/2026 | Maintenance information | Ari Kamo | energy_progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Linklaters | Office | Floors 11, 31–34 | Project M01397537 Project M01397547 Project M01397564 Project M01401701 Project M01397509 Project M01397501 Project M01209592 Project M01209602 Project M01209628 Project M01197329 Project M01181223 Project M01181234 |
| Portage Point Partners | Office | Floors 8, 9 | Project M01368516 Project M01368580 Project M01373723 Project M01368583 Project M01368589 Project M01368619 Project M01368623 |
| Carrot Express | Restaurant / Food Service | Ground | Project M01347306 |
| Oaktree | Office | Floors 11, 12 | Project M01337402 Project M01337572 |
| First Sentier Investors | Office | Floor 17 | Project M01271924 Project M01196315 Project M01196322 Project M01196341 Project M01196639 |
| Maple & Ash | Restaurant / Food Service | Cellar, Floor 1 | Project M01242747 |
| Bisnow | Office | — | Project M01213280 |
| Chase Bank | Retail | Floor 1 | Project M01088272 Project M00634112 |
| King & Spalding | Office | Floors 13–15 | Project M01101980 Project M01056374 |
| Selendy Gay Elsberg | Office | Floors 18–21 | Project M00969306 Project M00964036 Project M00969498 Project M00969558 Project M00964042 Project M00969500 Project M00964047 Project M00964051 Project M00964059 Project M00969505 Project M00969515 Project M00969534 |
| Neuberger Berman | Office | Floor 30 | Project M00861822 Project M00861807 |
| Simo Falco, Simo Pizza | Unknown | — | Project M00812150 |
| Walgreens | Retail | Floor 1 | Project M00658117 Project M00658142 |
| Chase and Duane Reade | Retail | Sub-cellar, Cellar, Floor 1 | Project M00570532 |
| fubo TV | Office | Floor 9 | Project M00512359 Project M00512380 Project M00514908 Project M00512340 |
| CUIMC | Medical / Healthcare | Floor 3 | Project M00466933 |
| Berman Neuberger | Office | Floor 24 | Project M00468414 |
| Chase | Retail | Cellar, Floor 1 | Project M00440418 Project M00440425 |
| ColumbiaDoctors | Medical / Healthcare | Floor 3 | Project M00309464 Project M00309590 |